on 781030,deluge Valves Isolated to Facilitate Drumming Room & New Fuel Receiving Area as Result of Repair on Fire Sys Headers.Followup Rept Will Be Issued on 781110
ML17317A705
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 10/30/1978
From: Shaller D
INDIANA MICHIGAN POWER CO.
To:
References
NUDOCS 7811020252
Download: ML17317A705 (6)


Text

1 REGULATO INFORMATION DISTRIBUTION . STEM DOCKET NBR: DOC DATE: 781030 RECIPIENT: Keppler, J.G. ACCESSION NBR: 7811020252 ORIGINATOR:Shaller, D.V. COPIES RECEIVED:

COMPANY:" 'IN 'a'Ml'Pwr' LTR ENCL 0

'UBJECT:

SIZE: 1 On 781030, it became necessary to isolate deluge valves to facil Drumming Room 6 New Fuels Receiving Area as result of repair on Five Sys headers.

Follow up rept will be issued 781510.

OISTRyRUTION CODE t Ano I NOTARIZEDF "DISTRIBUTION TITLE j GFMERAL DISTRISUTION FOR AFTER ISSUANCE OPFRATING LICENSE, l

FOR ACTION ENCL'/7 ENCL ~ ORBgl BC R G~ W/ENCL NRC PAR w/ENcL I 8 E w/g ENCL

~ GELD l. TR AN( Y

'ANAUER w/ENCL

,'ORE PFRFDRNANCE RR w/ENCL AD FOR SYS L PROJ w/ENCL ENGINFERING BR W/ENCL REACTAR SAFFTY BR W/ENCL PLANT SYSTEMS BR W/ENCL EER W/ENCL EFFLUENT TREAT SYS W/ENCL J HCGnUGH, w/ENCL LPDR W/ENCL TERA w/ENCL

, NSIC W/ENCL ACRS w/16 ENCl TOTAl. NUMBER OF. COPIES REQUIRED I LTR 40 ENCL- 39 NOTES: I s E 3 cys all material.

fe C'g t

l I

Mmerioen G "*i~~MIAl/Aa JvVCtlLGAPJHOR'Ell CONPANY DONALD C. COOK NUCLEAR PLANT P.O. Box 458, Bridgman, Michigan 49100 October 30, 1978 Mr. J.G. Keppler, Regional Director Office of Inspection and Enforcement United States Nuclear Regulatory Commission Region III 799 Roosevelt Road Glen Ellyn, IL 60137 Operating License DPR-58/DPR-74 Docket Nos. 50-315/50-316

Dear Mr. Keppler:

This is to confirm our verbal report to NRC Region III Inspector, Hr. K.R. Baker, at 0830 hours0.00961 days <br />0.231 hours <br />0.00137 weeks <br />3.15815e-4 months <br /> on October 30, 1978.

At that time vie reported that due to a repair on our Fire System headers it became necessary to isolate the deluge valves to the Plant's Drumming Room and Nevi Fuel Receiving Area. This report is being made in compliance with the ACTION statement of Fire Suppression Technical Speci fication Sections 3. 7. 9. 1 and 3. 7. 9. 2.

A followup report will be submitted by November 10, 1978, as required by Technical Specification 6. 9.2.

Sincerely,

.D.V: Shaller Plant Manager KQlLNMP fllgI<g pgI: ~gp~i

/bab

. cc: J.E. Dolan R. Wal sh, Esq.

R.W. Jurgensen G. Charnoff, Esq.

R.F. Kroeger G. Olson R. Kilburn J.M. Henni gan R.J. Vollen BPI PNSRC K.R. Baker RO:III J.F. Stietzel R.C. Callen MPSC Dir IE (40 cooies)

P.W. Steketee, Esq. Di r., MIPC (4 copies)

4 DONALD C. COOK NUCLEAR PLANT P.O. Box 458, Bridgman, Michigan 49106 October 30, 1978 Mr. J.G. Keppler, Regional Director Office of Inspection and Enforcement United States Nuclear R'egulatory Coilnission" Region III 799 Roosevelt Road Glen Ellyn, IL 60137

, Operating License DPR-58/DPR-74 Docket Nos. 50-315/50-316

Dear Mr. Keppler:

This is to confirm our verbal report to NRC Region III Inspector, Mr. K.R. Baker, at 0830 hours0.00961 days <br />0.231 hours <br />0.00137 weeks <br />3.15815e-4 months <br /> on October 30, 1978.

At that time we reported that due to a repai r on our Fire System headers it became necessary to isolate the deluge valves to the Plant's Drumming Room and New Fuel Receiving Area. This report is being made in compliance with the ACTION statement of Fire Suppression Technical Specification Sections 3. 7. 9. 1 and 3. 7. 9. 2 ~

A followup report will be submitted by November 10, 1978, as required by Technical Specification 6. 9.2.

Sincerely, D.V. Shaller Plant Manager

/bab cc: J.E. Dolan R. Walsh, Esq.