PR.ICBM.I EV ACCELERATED RIDS PROCESSING REGULATORY INFORMATION DISTRIBUTlON SYSTEM (RIDS) r ACCESSION NBR:9412010192 DOC.DATE: 94/11/16 NOTARIZED- NO DOCKET Alt FACXL:STN-50-528 Palo Verde Nuclear Station, Unit 1, Arizona Publi 05000528 STN-50-529 Palo Verde Nuclear Station, Unit 2, Arizona Publi 05000529 STN-50-530 Palo Verde Nuclear Station, Unit 3, Arizona Publi 05000530 p AUTH. NAME AUTHOR AFFILIATION LEVINE,J.M. Arizona Public Service Co. (formerly Arizona Nuclear Power RECIP.NAME RECIPIENT AFFILIATION R Document Control Branch (Document Control Desk)

SUBJECT:

Discusses NRC commitment change re procedure use 6 adherence.

0 0 DISTRIBUTION CODE: AOOID TITLE: OR COPIES RECEIVED:LTR Submittal: General Distribution 3 ENCL SIZE:

R NOTES:STANDARDIZED PLANT 05000528 Standardized plant. 05000529 Standardized plant. 05000530 RECIPIENT COPIES RECXPXENT COPIES ID CODE/NAME LTTR ENCL XD CODE/NAME LTTR ENCL Y

PD4-2 LA PD4-2 PD HOLIAN, B TRAN, L XNTERNAL: ACRS F LLE GENT.BR~0 NRR/DE/EELB NRR/DRCH/HICB NRR/DRPW NRR/DSSA/SPLB NRR/DSSA/SRXB NUDOCS-ABSTRACT OGC/HDS2 D EXTERNAL: NOAC NRC PDR NOTE TO ALL"RIDS" RECIPIENTS:

PLEASE HELP US TO REDUCE iVASTE! CONTACT I'HE DOCI:;"CLIENT CONTROL DESK, ROO!1! PI -37 (EXT. 504.2083 ) TO ELI i!INATE YOUR NAZI L F ROiI f

DIS RIBU'I'ION LISTS I'OR DOCI.'h!EN'I'S YOI: DON" I'l I'.D!

TOTAL NUMBER OF COPIES REQUIRED: LTTR 20 ENCL ~ 4

t Arizona Public Service Company PALO VERDE NUCLEAR GENERATING STATION P.O. BOX 52034 ~ PHOENIX, ARIZONA85072-2034 JAMES, M. LEVINE 102-03179-JML/AKK/RKR VICE PAESIDENT NUCLEAR PADDUCTIDN November 16, 1994 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Station P1-37 Washington, DC 20555

Dear Sirs:

Subject:

Palo Verde Nuclear Generating Station (PVNGS)

Units 1, 2, and 3 Docket Nos. STN 50-528/529/530 NRC Commitment Change, Procedure Use and Adherence File: 94-056-026 In a November 17, 1989 submittal (letter no. 102-01525), Arizona Public Service Company (APS) responded to NRC staff concerns regarding procedure use and adherence at PVNGS. As part of the response, APS committed to revise administrative procedure 40AC-9OP02, "Conduct of Shift Operations," to prescriptively identify when procedures shall be in the possession of and followed by the user, when procedures shall be out and referred to by the user, and when procedures shall be consulted. In addition to this procedure, there are several departmental procedures that provide guidance for procedure use and adherence.

A new procedure has been developed (procedure 01AC-OAP04, Procedure Use and

~

Adherence) that establishes a common set of ground rules for the use of procedures at PVNGS. The existing guidance procedures will either be cancelled or revised to the new procedure. The new procedure modifies current requirements (i.e., 'eference procedures shall be in the possession of and followed by the user for all safety related activities) to follow industry experience. In the new procedure, the decision on whether the procedure is in the user's hand or referenced by the user is based on the complexity of the task, the experience of the user, and the consequences of a possible error.

APS considers that the new requirements also resolve the NRC's concerns, since it is still managements'xpectation that the requirements of procedures be followed and it is Still the responsibility of the individual procedure user to correctly perform the activities directed by the procedure.

gr3(>0/5 9412010192 941116 II PDR P

ADOCK 05000528 PDR P$ )1

'. S. Nuclear Regulatory Commission ATTN: Document Control Desk

'NRC Commitment Change

. Page2 Based on the above discussion, APS has changed its policy for procedure use and adherence. Therefore, APS no longer considers the commitment in the 1989 submittal to be valid. This letter is provided for your information.

Should you have any questions, please contact Scott A. Bauer at (602) 393-5978.

Sincerely,

/

JML'/AKK/RKR/dpr cc: L. J. Callan B. E. Holian K. E. Perkins K. E. Johnston '.