ML17309A469

From kanterella
Jump to navigation Jump to search
Notice of Violation from Insp on 911216-20.Violation Noted: Adequate Methods for on-shift Assessment of Offsite Consequences of Radiological Emergency Condition Not in Use at Plant
ML17309A469
Person / Time
Site: Ginna Constellation icon.png
Issue date: 01/31/1992
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML17309A468 List:
References
50-244-91-28, NUDOCS 9202110189
Download: ML17309A469 (2)


Text

APPENDIX A NOTICE OF VIOLATION Rochester Gas and Electric Corporation R. 'E. Ginna Nuclear Power Plant

~

Docket:

50-244 License:

DPR-18'uring NRC inspection, on December 16-20; 1991, an apparent violation of NRC requirements was identified.

In accordance with the "General Statement of Policy and Procedure for NRC Enforcement Actions," 10 CFR Part 2, Appendix C (1991 Enforcement Policy),'that violation is listed below:

10 CFR 50.47(b)(9) requires that adequate

methods, systems, and equipment for assessing and monitoring actual or potential off-site consequences of,a radiological emergency condition be in use.

Contrary to the above, on December 18, 1991, adequate methods for on-shift assessment of the off-site consequences of a radiological emergency condition were not in use at. the Ginna Nuclear Power Plant.

Specifically, due to"lack of procedures and/or training, the Emergency Coordinator and Health Physics Technician in the Control Room, were not able to perform dose assessment for radiological releases which may result froin a steam generator tube rupture.

This is a Severity Level IV Violation (Supplement I).

Because acceptable interim procedures for declaring an appropriate emergency condition based, on associated radioactive emissions have been implemented and acceptable training in dose assessment was planned, no written reply to this violation is required.