Advises That Util Scheduled Independent Maint Vertical Slice Insp to Begin in Jul 1989.Util Will Be Assisted by Environ & Energy Svcs,Co.Nrc Invited to Participate in Insp
ML17304B296
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 06/27/1989
From: Conway W
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Martin J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
001-00186-WFC, 1-186-WFC, NUDOCS 8907070016
Download: ML17304B296 (6)


Text

)J(

REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)

ACCESSION NBR:8907070016 DOC.DATE: 89/06/27 NOTARIZED: NO DOCKET FACIL:STN-50-528 Palo Verde Nuclear Station, Unit 1, Arizona Publi 05000528 STN-50-529 Palo Verde Nuclear Station, Unit 2, Arizona Publi 05000529 STN-50-530 Palo Verde Nuclear Station, Unit 3, Arizona Publi 05000530 AUTH.NAME AUTHOR AFFILIATION CONWAY,W:F.

Arizona Public Service Co.

(formerly Arizona'Nuclear Power R

RECIP.NAME RECIPIENT AFFILIATION MARTIN,J.B.

Region 5, Ofc of the Director

SUBJECT:

Advises that util scheduled maint vertical slice insp to begin in Jul 1989.

DISTRIBUTION CODE: IEOID COPIES RECEIVED:LTR r

ENCL Q SIZE:

TITLE: General (50 Dkt)-Insp Rept/Notice of Violation Response NOTES:Standardized plant.

Standardized'plant.

Standardized plant.

8 05000528 05000529 05000530 RECIPIENT ID CODE/NAME PD5 PD DAVIS,M INTERNAL: ACRS AEOD/DEIIB DEDRO NRR/DEST DIR NRR/DOEA DIR 11

'NRR/DREP/RPB 10 NUDOCS-ABSTRACT OGC/HDS 1 RES MORICSEAU,D EXTERNAL: LPDR NSIC NOTES COPIES LTTR ENCL 2

1 1

1 1

2 1

1

.1 RECIPIENT ID CODE/NAME CHAN,T DAVIS,M.

AEOD AEOD/TPAD NRR SHANKMAN,S NRR/DLPQ/PEB NRR/DREP/EPB 10 NRR/PMAS/ILRB12 0

T J'EG FILE 02 G

FILE 01 NRC PDR COPIES LTTR ENCL 1

1 1

1 1

1 1

1 1

D S

I 9

NOXK 'IO ALL 'KIDS" KXXPEÃIS

/'y PLZASE HELP US IO REDOCE %RITE!'GKChCT 'IHE DOCUMEÃZ CONTI')L DESK, RXH P1-37 (EXT. 20079)

KO ELXMINAXBKRR NMB FKH DZPI%tZBQTICN LISTS XQR DOCUMENXS YOU DCRPT NEEDI TOTAL NUMBER OF COPIES REQUIRED:

LTTR 28 ENCL D

D S

Q~

Arizona Public Service Company P.O. EIOX 53999

~

PHOENIX. ARIZONA85072-3999 WILLIAMF. CONWAY EXECUTIVEVICEPRESIDENT NUCLEAR 001-00186-WFC June 27, 1989 Mr. John B. Martin Regional Administrator United States Nuclear Regulatory Commission Region V

1450 Maria Lane, Suite 210 Walnut Creek, California 94596-5368

Dear Mr. Martin:

Subject:

MAINTENANCE INSPECTION File:

89-045-419 Palo Verde Nuclear Generating Station (PVNGS)

Management has scheduled an independent Maintenance Vertical Slice Inspection to begin in

July, 1989.

This inspection will be conducted under the cognizance of our QA organization.

The inspection team will be led by the independent contractor who has specific experience performing NRC vertical slice activities.

Our decision to perform this inspection is based on our need to better assess the maintenance area in light of "lessons learned" from the Units 1

and 3

incidents and our desire to take strong management initiatives relative to critical self-assessment.

It is our understanding that the NRC.encourages utilities to take the initiative in the area of self-assessments.

Our plan to perform a

self-initiated. independent maintenance inspection

-is in concert with this understanding.

We have contracted with Environmental and Energy Services Company (ERCE) to assist us in performing this assessment.

Mr.

Gary Overbeck of ERCE will be the team leader.

Mr.

Overbeck has participated with numerous NRC inspection teams including maintenance inspections.

ERCE will furnish two additional team members with maintenance experience.

PVNGS will have at least three personnel functioning as team members.

n9070700iC~

S90627 PDR ADOCK 05000S2S PDC

(~

i

Page 2

June 27, 1989 Staffing the self-assessment team with our people provides an opportunity for them to gain a

better understanding. of the overall process by which Palo Verde is maintained.

An added advantage is that the team members will gain experience in this special inspection technique, whicn can be carried forth into future self-initiated assessments.

Palo Verde also recognizes that participation by experienced consultants in self-assessments can provide added objectivity and. thoroughness.

ERCE will provide training on self-assessment methodology to approximately 50 PVNGS personnel in early July.

The actual inspection will begin in late.

July and will be performed on Unit 1, with lessons learned from Unit 1 being applied to Units,2 and 3.

We would like to take, this opportunity to extend an.

invitation to the NRC to participate with us or to overview this inspection.

In any event, the results of this self-assessment will be made available to the NRC for review.

If you require additional details, please feel free to contact Blaine Ballard, Director of QA, at PVNGS.

William Conw WFC/lbs