REGULAl Y INFORMATION DISTR IBUTIO SYSTEM (RIDS)
ACCESSION'BR: 8810260526 DOC. DATE: 88/10/19 NOTARIZED: NO,
'DOCKET 0
'FACIL:STN-50-528 Palo Verde Nuclear Stationi Unit 1> Arizona Pub li 05000528 STN-50-529 Palo Verde Nuclear Stationi Unit 2I Arizona, Pub li 05000529 STN-50-530 Palo Verde Nuclear Stationi Unit 3i Arizona Publi' 05000530 AUTH. NAME AUTHOR AFFILIATION KARNERI O'. B.
Arizona Nuclear Power Prospect (formerly Arizona;Public Ser.v REC IP. NAME RECIPIENT AFFILIATION Document Control Branch (Document Control Desk)
SUBJECT:
Informs that SSFI diesel generator h auxiliary.0eedeater sos reviee will be completed bg 890228.
.DISTRIBUTION CODE:
AOOID COPIES RECEIVED LTR Q ENCL Q SIZE:
TITLE:
OR Submittal:
General Distribution NOTES: Standardized'lant.
Standardized plant.
Standardized plant.
05000528 05000529 05000530 REC IP IENT ID CODE/NAME PD5 LA CHAN> T COPIES LTTR ENCL RECIPIENT ID CODE/NAME PD5 PD DAVIS' COPIES LTTR ENCL INTERNAL ACRS NRR/DEST/ADS 7E NRR/DEST/ESB 8D NRR/DEBT/RSB 8E NRR/PMAS/ILRB12
,OGC/HDS1 RES/DSIR/EIB EXTERNAL:
LPDR'SIC 6
1 1
1 ARM/DAF/LFMB NRR/DEST/CEB 8H NRR/DEST/MTB 9H NRR/DOEA/TSB 11 NUDOCS-ABSTRACT 01'RC PDR NOTES:
TOTAL'UMBER OF COPIES REQUIRED:
LTTR 27 ENCL
I t49 h ~
I u
uk F)941
~
IZ+C g9<<99 c
P P
'" Fu le c Iuun )+I III I]4 /
Vu.
9$ P I
1 1<9 4h,
- 0"a 4<<H. h a 14 J+
5 I
')'fu r
Cj( j Iu 9
-'I u
Arizona Nuclear Power Project P.O. BOX 52034
~
PHOENIX, ARIZONA85072-2034 161-01405-DBK/JMQ October 19, 1988 Docket Nos.
STN 50-528/529/530 Document Control Desk U.
S. Nuclear Regulatory Commission Mail Station Pl-137 Washington, D.C.
20555
References:
A)
NRC Inspection Report from J.
B.
- Martin, NRC to E.
E. Van Brunt, Jr.,
ANPP, dated March 30, 1988.
Subject:
Safety System Functional Inspection (SSFI)
B)
Letter from E.
E.
Van
- Brunt, Jr.,
ANPP to NRC Document Control Desk 102-00725, dated April 25, 1988.
Subject:
Response
to Notice of Violations from SSFI Inspection
Dear Sirs:
Subject:
Palo Verde Nuclear Generating Station (PVNGS)
Units 1, 2, and 3
SSFI Diesel Generator (DG) and Auxiliary Feedwater (AF)
Systems Review File:
88-056-026; 88-070-026 ANPP's initial response to the Notice of Violation from the SSFI Inspection was provided to the NRC by Reference (B).
In this initial
- response, ANPP committed to provide a detailed review of two selected safety-related
Since the submittal of Reference (B) on April 25,
- 1988, we have instituted a
major program within the Nuclear Engineering Department.
The Engineering Excellence Program is composed of fourteen (14) major.objectives.
One objective specifically addresses systems reviews and training for the Nuclear Engineering Department staff.- In preparation to commence the first system reviews, it was necessary to develop standards for the system reviews, calculations reviews, training packages, Design Basis Manual Writers Guides and
- formats, etc.
We plan to commence the system reviews immediately following this effort and anticipate a
four (4) month duration for these initial systems to be reviewed.
88i0260526 88iOi9 P
R ADOCK 05000528
'PDC 00'(Q
41
~Ah C 0>
U.
S. Nuclear Regulatory Commission Page 2
161-01405-DBK/JMQ October 19, 1988 We have combined the the AF and DG systems reviews with the training effort that is now scheduled to be completed by February 28, 1989.
Therefore, completion of the AF and DG systems review will be completed by February 28, 1989.
If you have any questions, please contact A. C. Rogers and T.
D. Shriver of my staff.
Very truly yours, D. B. Karner Executive Vice President DBK/JMQ/dim cc:
R.
W. Parkhill J.
B. Martin G.
W. Knighton M. J.
Davis T. J. Polich
Cl 4>
'9 l
l, Ji