Responds to 851219 Ltr Re Violations & Deviation Noted in Insp Rept 50-528/85-31 on 851028-1108.Corrective Actions: Outage Maint Personnel Retrained to Rev 3 to 73AC-9ZZ05 & Procedures IP-4.12,IP-4.14 & IP-5.15 Changed
ML17299A979
Person / Time
Site: Palo Verde Arizona Public Service icon.png
Issue date: 01/17/1986
From: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Kirsch D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
ANPP-34681-EEVB, NUDOCS 8602040277
Download: ML17299A979 (4)


Text

8~020P0277 86000i0528t pDR I5IDOCK 0500pDR 9

Arizona Nuclear Power Project P.O. BOX 52034 4 PHOENIX, ARIZONA85072-2034 J8 P I Qf t J ~

January 17, 1986 ANPP-34681-HF98/~ggg8.05 U. S. Nuclear Regulatory Commission Region V 1450 Maria Lane, Suite 210 Walnut Creek, CA 94596-5368 Attention: Mr. D. F. Kirsch, Deputy Director Division of Reactor Safety and Projects

Subject:

Palo Verde Nuclear Generating Station (PVNGS)

Unit 1 Docket No. STN 50-528 (License NPF&1)

Response to Notice of Violations: 50-528/85-31-09, 50-528/85-31-06; and Response to Notice of Deviation: 50-528/85-31-04.

File: 86&7026 D.4.33.2 Re ference: NRC Inspection Report 50-528/85-31, letter from D. F. Kirsch to E. E. Van Brunt, dated 12/19/85

Dear Sir:

This letter is provided in response to the inspection conducted by Mr. S. Richards and other members of the NRC staff on October 28 through November 8, 1985 of activities authorized by NRC, License No. NPF&1. Based on the results of the inspection, two violations of NRC requirements (administration of temporary modifications) and one deviation (design verification) were identified. The two violations were discussed in Items A and B in Appendix A of the referenced letter. The deviation was discussed in Appendix B of the referenced letter. The Arizona Nuclear Power Project (ANPP) responses to these items are submitted herewith in Attachments A and B to this letter.

With respect to the general areas of perceived weakness identified by the NRC in the referenced Inspection Report, ANPP will address these areas and response include its responses to these areas along with the this letter. transmittal of the final to Item B which is discussed in Attachment A to

t U

J ~ ~

iy 4 Pl 11

Mr. D. F. Kirsch PVNGS Unit 1 Notice of Violations and Deviation 50-528/85-31&9, 50-528/85-31-06 and 50-528/85-31-04 Page 2 ANPP- 34681 Should there be any further concerns, ANPP will be pleased to discuss them with you.

Very truly yours, EQ/~8~~v Jnpg E. E. Van Brunt, Jr.

Executive Vice President Project Director EEVB/TAP/dim Attachments cc: A. C. Gehr R. P. Zimmerman E. A LLcitra L. F. Miller