Text
BEDEWED MRS Arizona Nuclear Popover Project P.O. BOX 52034 4
PHOENIX, ARIZONA85072-2034 885 JAN Q
QJ 8 Q Q REGIGNltNF ANPP-31634-EEVBJr January 6,
1985 Mr. John B. Martin Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission, Region V
1450 Maria Lane, Suite 210 Walnut Creek, CA 94596 lE Hg FILE COP5l-
Subject:
Certification of the Operability of All Required Systems for Initial Fuel
- Load, Palo Verde Unit 1
File: 85-055-026 Re:
PVNGS Unit 1 Operating License NPF-34
Dear Mr. Martin:
As required by Item l,b of Attachment 1 to the Palo Verde Nuclear Generating Unit 1 Operating License, NPF-34, I am hereby certifying that Item l.a of Attachment 1 to the license has been completed for the initial fuel load of Unit l.
The operability of all systems required, for the initial fuel load has been demonstrated by successfully meeting the acceptance criteria in the PVNGS Technical Specifications.,
This has be'en accomplished by the completion of'he applicable surveillance tests or by preoperational testing which verifies the meeting requirements of the Technical Specifications and which were performed within the required surveillance interval.
Very truly yours, lb cc:
D. Eisenhut T. Novak M. Licitra E.
E.
Van Brunt, Jr.
APS Vice President Nuclear Production ANPP Project Director 850iihOi34 850i06 PDR ADOCK 05000528 A