Interim Deficiency Rept DER 84-33 Re Incorrectly Installed Hanger Support Assembly.Initially Reported on 840504.Second Walkdown of Pipe Support Assembly 1-SI-070-H011 Revealed Missing Weld.Complete Rept Expected by 840810
ML17298B040
Person / Time
Site: Palo Verde Arizona Public Service icon.png
Issue date: 06/04/1984
From: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Bishop T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
ANPP-29642-TDS, DER-84-33, NUDOCS 8406120317
Download: ML17298B040 (5)


Text

Pi""CBVEQ gs pn LsrwV Arizona Public Service Company IMta JlJH-5 hHIO: l5 June 4,'984 BEG@>it A<K" ANPP-29642-TDS/TRB U. S. Nuclear Regulatory Commission lE. FlLE COPYit Region V Creekside Oaks Office Park 1450 Maria Lane Suite 210 Walnut Creek, CA 94596-5368 Attention: Mr. T. W. Bishop, Director Division of Resident Reactor Projects and Engineering Programs

Subject:

Interim Report DER 84-33 A 50.55(e) Potentially Reportable Deficiency Relating to Incorrectly Installed Hanger Support Assembly Rile: 84-019-026; D.4.33.2

Reference:

Telephone Conversation between P. Narbut and T. Bradish on May 4, 1984

Dear Sir:

The NRC was notified of a potentially reportable deficiency in the referenced telephone conversation. At that time, it was estimated that a determination of reportability would be made within thirty (30) days.

Due to the extensive investigation and evaluation required, an Interim Report is attached. It is now expected that this information will be finalized by August 10, 1984, at which time a complete report will be submitted.

Very truly yours, EE 0a ~~~

E. E. Van Brunt, APS Vice President Jr.

Nuclear Production ANPP Project Director EEVB/TRB:ru Attachment cc: See Page Two 84061Z03i7 840604 PDR ADOCK 050005Z8 8 PDR ZL--~l'. (

C Mr. T. W. Bishop DER 84-33 Page Two cc~ Richard DeYoung, Director Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, D. C.'0555 T. G. Woods, Jr.

D. B. Earner W. E. Ide D. B. Fasnacht A. C. Rogers L. A. Souza B. S. Kaplan D. E. Fowler T. D. Shriver J. Vorees J. R. Bynum J. M. Allen J. A. Brand A. C. Gehr W. J. Stubblefield W. G. Bingham R. L. Patterson R. W. Welcher H. D. Foster D. R. Hawkinson L. E. Vorderbrueggen G. A. Fiorelli S. R. Frost J. Self D. Canady Records Center Institute of Nuclear Power Operations 1100 Circle 75 Parkway, Suite 1500 Atlanta, GA 30339

Ag f

I

INTERIM REPORT DER 84-33 POTENTIAL REPORTABLE DEFICIENCY ARIZONA PUBLIC SERVICE COMPANY (APS)

PVNGS UNIT 1 I. Potential Problem Pipe support assembly, 1-SI-070-HOll, was installed and approved by Field Engineering and Quality Control. An individual walkdown was also made on this system. This hanger was installed to Rev. 2 of the drawing, 13-SI-070-H-Oll and FCR 51,022-PI. This design drawing shows a weld between Item C of the hanger (south) and the insert plate. This weld was never made and the condition was not detected until a second walkdown was made on the system.

II. Approach To and Status of Proposed Resolution Bechtel field engineering is currently studying this problem to determine reportability and technical justification for corrective action.

III. Projected Completion of Corrective Action and Submittal of the Final Report Evaluation of this condition and submittal of the Final Report is forecast to be completed by August 10, 1984.