Comments on Re NRC Review of Environ Qualification of Equipment,Documenting Agreements Reached During 831031 Telcon
ML17298A636
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 11/08/1983
From: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Knighton G
Office of Nuclear Reactor Regulation
References
ANPP-28186-WFQ, NUDOCS 8311110054
Download: ML17298A636 (6)


Text

SUBJECT; Comments on 831011 ltr re NRC review of environ qualification of equipmentrdocumenting agreements

-reached dur ing 831031.tel con ~

DISTRIBUTION CODE:

A008S

.COPIES RECEIVED:LTR:3 ENCL TITLE: OR/Licensing Submi!ttal: Equipment Qualification SIZE:.

NOTES:Standardized plant ~

Standardized plant ~

Standardized plant ~

REGULATORY FORMATION DISTRIBUTION S EM (RIDS)

ACCESS/ON NBR 831 1 1 1 0050 DOC DATE ~ 83/1 1/08 NOTARIZED NO FACIL:STN-50<<528';Palo Verde Nuclear Station<

Uni t ig Ar izona Publ i

'STN 50 529 Palo Verde Nuclear Stationi Unit 2i Arizona Publi STN 50 530 Palo Verde Nuclear Stationi Unit 3i Arizona Publi AUTH~ NAME

'UTHOR AFFILIATION VAN BRUNT<E,E ~

Ar'izona Pub'I ic Ser vice Co, RECIP s NAME RECIPIENT AFFILIATION KN?GHTONr G s Licensing Branch 3

DOCKET 05000528 05000529 05000530 05000528 05000529 05000530 RECIPIENT ID CODE/NAME NRR LB3 BC 12 INTERNAL:,ELD/HDS3 12 IE F ILE.

09 NRR/DE/EQB 07 AB

-06 REG:

FIL.=

04 RECOPIES LTTR ENCL 1

1 2

1 1.

RECIPIENT ID CODE/NAME L'ICITRAr E ~

GC 13 NRR -CALVOiJ NRR/DL DIR 1'RR/DS I/AEB RGN5 COPIES LTTR ENCL EXTERNALs AC9S 15

,NRC PDR 02,.

NTIS 31 LPDR NSIC 03 05 0

,'TOTAL NUMBER OF COPIES REQUIRED e LTTR 25 ENCL

rollll 1

H tl t<<

) )

~

1 fl

) )>>a

),'uT )I 6 ') W>>i)<<1 IW u>II)>

)

.W>>'uo lf li

>> 'u I <<f

)

")I'f)

) P, W>> fur IO W

op

~

) ~

W o

T

)f/ lf)

'" ')Pal>

-> )

P 'l) aw)ah') w'(,

W~

<<rVW)~

)<o

~O a)) ll>> t>>;'>>

) ")f) ) 1)) )ff~~r>I')f[JIK'"t) l>>'

Wpf )r. ~ 1)'

f f>h<<

,()~g f,WN

~ I

~

1 oomoe~wcet u>>,~ +

<<T ):. 'V T>>:).I>>f 'J <>>J

)f" f llf <<h

') !'>>

<<.a.f).I)'~ 'f)4) f t'$ f l,f", f pfrll t I')

~ 'f r>>l

~ f)>>i lt) '>% Vr

~ )

7 jl')l I',f)

Ii li h

l I) 1<>.I, I

T h>>

)

~

~

7 Arizona Public Service Company P.O. SOX 2I666

~

PHOENIX, ARIZONA 65036 November 8, 1983 ANPP-28186 WFQ/RJP Director of Nuclear Reactor Regulation Attention:

Mr. George Knighton, Chief Licensing Branch No.

3 Division of Licensing U.S. Nuclear Regulatory Commission Washington, D.C.

20555

Subject:

Palo Verde Nuclear Generating Station (PVNGS)

Units 1, 2 and 3

Docket Nos.

STN-50-528/529/530 File:

83-056-026'.1.01.10

Reference:

Letter from G.

W.

Knighton (NRC) to E.

E.

Van Brunt, Jr.

(APS),

dated October ll,

1983,

Subject:

Staff Review of Environmental Qualification of Equipment for Palo Verde.

Dear Mr. Knighton:

Our comments regarding the referenced letter were discussed in a

telephone conversation with E. A. Licitra, B. LaGrange and H. Garg of the NRC staff on October 31, 1983.

The following agreements were reached:

1.

Page B 16, items 3:

states PVNGS is required to provide interim operation justification for any safety related mechanical equipment which is not qualified prior to fuel load.

After describing the APS mechanical equipment qualification program and explaining that it is expected to be completed by June,

1984, NRC suggested that if our program were complete prior to full power operation, it would be acceptable to not provide interim operation justifications.

Ho~ever, any equipment not qualified prior to full power operation, would still require interim operation justification.

APS agreed to include completion schedules for all safety related mechanical equipment, along with the additional information requested in the

letter, in the PVNGS mechanical equipment qualification program submittal.

This submittal is scheduled to be provided to NRC by November 21, 1983.

2.

Page B-16, item 2:

Three items are listed as selection for audit from our mechanical equipment program.

It was agreed by NRC and APS that these packages would be sent to NRC on the PVNGS docket for NRC review.

We expect to have these packages ready for audit by January 1, 1984, at which time they will be provided for NRC review.

PDR PDO 5+ 83f i08 83ifii00" 0~000Sa8 PDR

,(o

~(

4

~lg I

t

Mr. G.

W. Knighton Page 2

3.

Pages B-18 through B-20:

Qualification work which was shown to be incomplete in our Environmental

+alification

Report, is listed.

APS will provide an updated status of this equipment along with interim operation justifications for any equipment not qualified prior to fuel load.

4.

Pages B-21 and B-22:

Equipment which is qualified but for which no surveillance program has been implemented, to NRC's knowledge, is listed.

APS understands that when the surveillance program has been accepted by NRC, that these items will be deleted from this list.

5.

Page B-9, item 5:

Three items are listed for whicn NRC requested a

detailed surveillance program be submitted.

APS asked for additional clarification as to which Reliance Motor (sub-item 2) the NRC would like information on.

NRC suggested that APS select the specific motor application to submit.

If you have any comments, please contact me.

l!

Very truly ours E. E.

Van Brunt, Jr.

,APS Vice President

-*'uclear Projects Management ANPP Project 'Director EEVB/RJP/sp cc: