Notification of Caseload Forecast Panel 801028-30 Meeting W/Util in Buckeye,Az & at Site.Agenda Encl
ML17296B037
Person / Time
Site: Palo Verde  
Issue date: 10/17/1980
From: Kerrigan J
Office of Nuclear Reactor Regulation
To: Miraglia F
Office of Nuclear Reactor Regulation
References
NUDOCS 8011060586
Download: ML17296B037 (14)


Text

Docket Nos.

STN 50-528/529/530 HEHORANDUN FOR:

Frank J. Hiraglia, Acting Chief, Licensing Branch 4'3, DL FRoja:

SUBJECT:

DATE & TINE:

LOCATION:

PURPOSE:

Janis Kerrigan, Project Hanager, Licensing Branch 83, DL PALO VERDE l. 2, AND 3 CASELOAD FORECAST HEETING October 28<<29-30, 1980 8:00 am - 5:00 pm 0

Buckeye Union High School, Board Room 902 Eason Street Buckeye, Arizona and Palo Verde site The NRC Caseload Forecast Panel meeting and site visit to the Palo Verde l, 2, and 3 plants.

PARTICIPANTS:

NRC M. Lovelace J. Kerrigan F. Hiraglia E

Arizona Public Service B. guinn, et al cc:

See next page Janis Ker'rigan, Project Hanager Licensing Branch 83 Division of Licensing 80 11.0egg'It@

LBIII3:DL 10

/80 OFFICE/

SURNAME DATE$

NRC FORM 318 (9 76) NRCM 0240

'0 U.S. GOVERNMENT PRINTING OFFICE: 1979 289 369

t, y

ging N,

v tf

= ~

III I

t-C 0

J r-II 59)

Docket Fi 1>>

NRC PDR Local PDR TIC NSIC Branch File

,H. Denton E.

Case D. Eisenhut R. Purple T.

Novak S. Vara T.

I pl>dl i to R.

A. Clark R.

Reid R. Tedesco B. Youngblood A. Schwencer F. Niraglia J.

R. Hiller G. Lainas D. Crutchfiold

'll. Russell J. Olshinki R. Vollmer R.

Rosnak F. Schauer R.

E. Jackson G. Lear V. Noonan S. Pawlicki V. Benaroya Z.

Ros toczy W.

Haass D. Nuller R. Ballard ll. Regan J.

D. Sal,tzman D.

Ross P.

Check R. Satterfield O. Parr F.

Rosa W. Butler W. Kregor R.

M. Houston T. Nurphy W. Gammill L. Rubenstein T. Spels W. Johnston B. Grim<.s H. Collins F.

Pagano S.

l4imos J.

Kraiuo>er liEETING NOT ICI; DISTPIl<ljTION

). Stole S.

l<anauer P. Collins D. Vassallo D.

Ziemann F. Schroeder K. Kniel D.,Skovholt G. 'Knighton N. Ernst R. Baer E.

Adensam A. Thadani ACRS (16)

Attorney, OELD OIE (3)

OSD (7)

Project Nanager J

Kerrigan Licensing Assistant~~

Recepti oni st TERA J."LeDoux, IEE V..'Noore I&E Headquarters I&E Region I I&E Region II I&F. Region III I&E Region IV I&E Region V

I NRC

Participants:

Lovelace J. Kerrigan F. Niraglia bcc:

Applicant

& Service List

A j

~y,g Afc(

Wp0 UNITEDSTATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555 OCT

] 7 1980 Docket Nos.

STN 50-528/529/530 MEMORANDUM FOR:

Frank J. Miraglia, Acting Chief, Licensing Branch ¹3, DL FROM:

SUBJECT:

DATE & TIME:

LOCATION:

PURPOSE:

Janis'errigan, Project Manager, Licensing Branch ¹3, DL PALO VERDE 1,',

AND 3 CASELOAD FORECAST MEETING October 28-29-30, 1980 8:00 am - 5:00 pm Buckeye Union" High School, Board Room 902 Eason Street Buckeye, Arizona and Palo Verde site The NRC Caseload Forecast Panel meeting and site visit to the Palo Verde 1, 2, and 3 plants.

PARTICIPANTS:

NRC W. Lovelace J. Kerrigan F. Miraglia Arizona Public Service B. guinn, et al cc:

See next page

~~)

nis Kerrigan, Proje icensing Branch ¹3 Division of Licensing h

Manager

e I

li I<

iJ I

r'

Yr. E.

E'.

Van Brunt, Jr.

Vice President

- Construction Projects Arizona Public Service Company P. 0.

Box 21666

Phoenix, Arizona 85036 CC:

Arthur C. Gehr, Esq.

Snell 8 Wilmer 3100 Valley Center

Phoenix, Arizona 85073 Charles S. Pierson Assistant Attorney General 200 State Capitol 1700 West Washington

. Phoenix, Arizona 85007 David N. Barry, Esq.,

Senior Counsel Charles R. Kocher, Esq., Assistant Counsel Southern California Edison Company P. 0.

Box 800

Rosemead, California '1770 Dr. Stanley L. Dolins Assistant Director Energy Programs (OEPAD)

Office of the Governor 1700 West Washington Executive Tower - Room 50/

'hoenix, Arizona 85007 Wi 1 liam Primm Assistant Attorney General Bataan Memorial Building Santa Fe, New Mexico 87503 Resident Inspector Palo Verde/NPS U.S. Nuclear Regulatory Commi.,sion c/o TTL/LGX Luke Air Force Base, Arizoria 85309 Ms. Patricia Lee Ilourihan 309 E. 14th Street

Phoenix, Arizona 85008 '

I J

i I

1

PALO VERDE 1

CA ELOAD FORECAST PANEL SITE VISIT MEETING AGENDA 2.

3.

Overview of project construction schedule including progress and major milestones completed since Caseload Pane) visit of April, 1979, current problems and any anticipated problem areas that may impact the current projected fuel load date.

Detailed'eview and current status of design and engineering effort (by major discipline) includin'g any potential problems that may arise from necessary rework.

I Detailed review and current status of procurement activities including valves, pipe, instruments, cable, major components, etc.

4.

Actual and proposed craft. work force (by major craft), craft availability, pr'oductivity, potential labor negotiations and problems.

5.

Detailed review and current status of all large and small bore pipe hangers, restraints,

snubbers, etc., including design, rework, procurement, fabrication, delivery and installation.

6.

Detailed review of project schedule identifying critical path

items, near critical items, amount of float for vqrious activities, the current critical path to fuel loading, methods of implementation" of correctiye action for any activities with negative float, and provisions for contingencies.

The estimated project percent complete as of September 30,

'1980.

7.

Detailed review and current status of bulk quantities including current estimated quantities, quantities installed to date, quantjties scheduled to date, current percent complete for

each, actual versus forecast installation rates, and basis for figures.

(a)

-Concrete (CY)

(b)

Process Pipe (L'F)

Large Bore Pipe (2 1/2" and larqer)

Small Bore Pipe (2" and smaller)

.(c)

Yard Pipe (LF)

(d)

Large Bore Pipe Hanqers, Restraints, Snubbers (ea)

0 P

'(r

(e)

Small Bore Pipe Hangers, Restraints (ea)

(f)

Cable Tray (LF)

(g)

Total Conduit (LF')

(h}

Total Exposed Metal Conduit (LF)

(i)

Cable (LF)

Power Control Security Instrumentation Plant Lighting

{j) Terminations (ea)

Power Control Security Instrumentation Plant Lighting (k)

Electrical Circuits (ea)

Power Control

-.Security (1}

Instrumentation

{ea) 8.

Detailed review and current status of preparation of preop test procedures, integration of preop test activities with construction

schedule, system turnover
schedule, preop test
schedule, current and proposed preop test program manpower.

(a)

Total number of procedures required for fuel load.

(b)

Number of draft procedures not started.

(c)

Number of draft procedures being written.

(d)

Number of procedures approved.

(e}

Number of procedures in review.

f)

Total number of preop tests required for fuel load.

g)

Number of preop tests completed.

(h)

Number of preop tests currently in progress.

(i)

Number of systems turned over to start-up.

ji Ij

e,

~ 9.

Detailed discussion of potential schedular influence due to changes attributed to HUREG-0660, NUREG-0694 and other recent licensing requirements.

10.

Site tour and observation of construction activities.

ll.

Discussion of schedular impact, if any, regarding corrective action relating to Class IE, 600V, power cable.

~

~

{

1 ~