REGULATOR INFORMATION DISTRIBUTION STEM (RIBS)
ACCESSION NBR: 8008130590 DOC ~ DATE: 80/08/04 NOTARIZED:
NO DOCKET ¹ FACIL:STN-50-528 Palo Verde Nuclear Statjonr Unjt ii Arizona Publ j 05000528 STN-50-529 Palo Verde Nuclear StatjonE Unjt 2i Arjzona Publj 05000529 STN-50-530 Palo Verde Nuclear Stationi Unit 3i Arizona Publi 05000530 AUTH ~ NAME, AUTHOR AFFILIATION VAN BRUNTRE.E.
Arizona Public Service Co.
REC IP ~ NAME RECIP IENT AFFILIATION
SUBJECT:
Interim,dej'iciency.rept re Class 1Ei600 voltipower cable aualification testing due to difficulties in implementation
~
Final rept will forwarded by 801115.
DISTRIBUTION CODE:
B019S COPIES RECEIVED!LTR ENCL'IZE!g" TITLE: Construction Deficiency Reoor t (10CFR50
~ 55E)
NOTES!Standardized Plant.
Standardjzed Plant.
Standardized Plant
~
05000528 05000529 05000530 RECIPIENT ID CODE/NAME ACTION:
A/D LICENSNG 21 LEEgJ ~
20 INTERNAL! AD/RCI/IE D/DIR HUM FAC S
EDO 8
STAFF 07 ILE 05 MPA 08 OELD 23 QA BR 10 RUTHERFORDgH ~ IE COPIES LTTR ENCL 1
1 1
1 1
1 1
1 1
1 2
2 1
1 1=
1, 1
1 1
1 RECIPIENT ID CODE/NAME"'CHHENCERgA
~
15 KERRIGANE J ~
14 AEOD DIRiHUM FAC SFY EQUIP QUAL BR16 LIC QUAL'R NRC PDR 02
.PRO REV BR 01 STANDRDS DEV'1 COPIES LTTR ENCL 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 EXTERNAL! ACRS NSIC 24 04 16 16 1
1 LPDR 03 1
1
<"6 15 1980 TOTAL NUMBER OF COPIES REQUIRED:
LTTR 39 ENCL 39
~
rr rt W
1' 8
1 rt Ir I
~F rrl',
rh
~ I fi I
tt A
f tr"~ r W
0
,0 Wlfr,t
(
f 1 lr
'll, f fNI Wr I I rr II 1lr)tl
"+W fr r I 1
I I
I 'IW f t'f W"
7 fr
~
'I I
g 7
~,
r 1
II 7
1
'I r
I l
,7 I
f 0
k rr t
1 l
,lt
WEIRD IIS3 lX (QCSEQPRZKZP P. O. BOX 2I666
'HOENIX'RIZONA65036 August 4, 1980 ANPP-16084-BSK/JAR U. S. Nuclear Regulatory Commission Region V Walnut Creek Plaza. Suite 202 1990 North California Boulevard Walnut Creek, California 94596 Attention:
Mr. G.
S. Spencer, Chief Reactor Construction and Engineering Support Branch
Subject:
A 50.55(e)
Reportable Condition Relating to Class IE, 600V, Power Cable File:
80-019-026
Reference:
(1)
ANPP-15090-JAR, dated March 24, 1980 (2)
ANPP-15507-BSK/JAR, dated May 23, 1980
Dear Sir:
A preliminary written report and an interim report of a reportable deficiency under 10CFR50.55(e) was transmitted by References (1) and (2), respectively.
Reference (2) estimated that information from qualification testing would be available by August 1, 1980.
This information is summarized on the enclosed interim report.
The qualification testing is not complete due to difficulties encountered during its implementation.
It is now expected that this information will be finalized by November 15, 1980 at which time a complete report will be submitted.
The Stop Work order", issued. March 5, 1980, on installation of the Rockbestos Class IE cables has been partially lifted for out-of-containment installations as explained in the interim report.
A decision will be made by September 1,
1980 on the disposition of the remainder of the quarantined cable and the cable previously pulled.
Very truly yours, EEVBJr/BSK:skc Enclosure soosqae &9C)
E.
E. Van Brunt, Jr.
APS Vice President Nuclear Projects ANPP Project Director.
/oft 5
j((
L l
I
U. S. Nuclear Regulatory Commission Attention:
Mr. G.
S. Spencer,
.Chief ANPP-16084-BSK/JAR August 4, 1980 Page 2
~ cc': ~,Victor Stello, Jr., Director Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, D.
C.
20555 A. C. Gehr '-.
Snell
& Wilmer R. L.
D. B.
W. E.
B. S.
J.
A.
A. C.
J.
M.
W. H.
W. G.
W. J.
J.
E.
R.
W.
D. R.
J. A.
Robb Fasnacht Ide Kaplan Roedel Rogers Allen Wilson Bingham Stubblefield Bashore Welcher Hawkinson Brand
a; I f
ili I
I
REPORTABLE DEFICIENCY 50.55(e)
ARIZONA PUBLIC SERVICE COMPANY (APS)
PVNGS UNIT //1 INTERIH REPORT August 1, 1980 Problem 'and'Previous Notification The purpose of this report is to provide additional interim information required by 10CFR50.55(e) con-cerning apparent deficiencies relating to 600V copper power cable, delivered and partially installed in Unit 81 of the PVNGS.
A preliminary written report of this deficiency was transmitted by Reference (1).
An interim report was forwarded by Reference (2).
Reference (2) stated that qualification testing and evaluation would be complete by August 1,
1980.
A roach to Resolution of the Problem Please refer to Reference (1) which documents our approach,to the resolution of this problem.
XII Status of Pro osed Resolution Class IE multiconductor cable with insulation repairs manufactured after October 1, 1979'is'ualified per IEEE-323-1974 and is released:for installation out-of-containment.
Steam line break/loss of coolant accident (SLB/LOCA) tests are being conducted.
Sufficient in-formation should be available by mid-October, 1980 to determine if this cable can be installed inside con-"
tainment.
Class IE multiconductor cable with insulation repairs manufactured before October 1,
1979 and all single conductor Class IE cable with insulation repairs has been undergoing aging analysis to 'establish at least a 40-year qualified life for out-of-c'ontainment use per IEEE-323-1974.
The scheduled completion date for this phase of testing is August 18, 1980.-
SLB/LOCA tests are scheduled to be completed in mid-September, 1980 for in-containment qualification.
' )
Wp' 1
I
Reportable Deficiency 50.55(e)
Interim Report August 1, 1980 Page 2
IV Reasons for Dela of Final Re ort The final report is delayed in order to await the completion and evaluation of qualification testing.
The final report is delayed because of the time involved to develop Arrhenius plots for the insu-lation repair material as noted in Section III above.
V Pro'ected Com letion of Corrective Action and Submittal Date of the Final Re ort Class IE multiconductor cable with insulation repairs has successfully completed out-of-containment quali-fication.
Qualification for out-of-containment installation of single conductor cable with insulation repairs is scheduled for completion by August 18, 1980.
Disposi-tion for all out-of-containment cable installation is expected by September 1, 1980.
SLB/LOCA testing for all cable should be completed by late October, 1980.
A final report will be submitted by November 15, 1980.