ML17292B372

From kanterella
Jump to navigation Jump to search
Insp Rept 50-397/98-01 on 980209-0422.One Apparent Violation Noted & Being Considered for Ea.Major Areas Inspected: Engineering
ML17292B372
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 05/08/1998
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML17292B371 List:
References
50-397-98-01, 50-397-98-1, NUDOCS 9805140317
Download: ML17292B372 (22)


See also: IR 05000397/1998001

Text

ENCLOSU

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket No.:

License No.:

Report No.:

Licensee:

Facility:

Location:

Dates:

Inspector:

Accompanying

Personnel:

50-397

NPF-21

50-397/98-01

Washington Public Power Supply System

Washington Nuclear Project-2

3000 George Washington Way

Richland, Washington

February 9 through April22, 1998

John E. Whittemore, Senior Reactor Inspector

Maintenance Branch

Tai L. Huang, Nuclear Engineer, Reactor Systems Branch

Office of Nuclear Reactor Regulation

Jose March-Leuba, Nuclear Engineering Consultant

Oak Ridge National Laboratory

Approved By:

Dr. Dale A. Powers, Chief, Maintenance Branch

Division of Reactor Safety

ATTACHMENT:

Supplemental Information

980M40317 980508

PDR

ADOCK 05000397

6

PDR

-2-

XE

TV

A Y

Washington Nuclear Project-2

NRC Inspection Report 50-397/98-01

During the performance of an NRC inspection reported in NRC Inspection Report 50-397/97-11

to determine the adequacy of certain WNP-2 facility license power distribution and fuel thermal

limits, the inspectors identified three unresolved items. This current special inspection was

conducted to review the licensee's response to the unresolved items using inspection personnel

from Region IV, the Office of Nuclear Reactor Regulation, and Oak Ridge National Laboratory.

gggini~rin

~

The licensee operated the Siemens Power Corporation's fuel in Core Cycles 7-12 in

excess of a revised operating limit minimum critical power ratio based on revised and

conservative ANFB-1125 correlation constant uncertainty (Section E1.2).

On the basis of the November 25, 1997, licensee response,

the safety limit minimum

critical power ratio was not exceeded during the actual events and transients

experienced

by the plant during Core Cycles 8-12. The licensee's analysis to determine

ifthe limitcould have been exceeded during Core Cycles 8-12 did not use licensing

bases assumptions,

bounds, and parameters

(Section E1.2).

Administrative controls and operating limits in place during Core Cycles 7-12 would not

have ensured operation within the envelope of the licensing basis.

Therefore, had the

limiting transient occurred with design basis operating conditions, the revised safety limit

could have been reached or exceeded (Section E1.3).

~

The vendor development and implementation of the minimum critical power ratio

operating and safety limits for WNP-2 fuel were not adequate to assure that the limits

were accurate and conservative.

Licensee oversight of the fuel vendors'esign

processes

and controls for the nuclear fuel supplied to WNP-2 failed to detect that an

inadequate Technical Specification limitwas developed.

The failure to establish

measures

to assure that the design bases were correctly translated into technical

specifications was identified as an apparent violation of Criterion III,Appendix B to

10 CFR Part 50 (Section E1.4).

0

-3-

e

D

il

au

The unit operated at or near full power during the onsite inspection period.

E1

Conduct of Engineering

E1.1

~B~r~nI

This inspection consisted of engineering followup review of the licensee's response to

the three unresolved items identified during NRC Inspection Report 50-397/97-011.

During that inspection, it was determined that the licensee had operated Core

Cycles 7-12 with nonconservative values for the operating limitminimum critical power

ratio (OLMCPR) for the Siemens Power Corporation's (SPC) fuel. These limits are

specified in the Core Operating LimitReport. These limits, according to 10 CFR Part 50,

Appendix A, Criterion 10, are specified acceptable fuel design limits (SAFDLs). The

licensee's reactor core, associated

coolant, control, and protection systems are to be

designed such that there is appropriate margins to assure that SAFDLs are not

exceeded during any condition of normal operation, including anticipated operational

occurrences.

The nonconservative and inappropriate limits occurred because the SPC

(previous fuel vendor) critical heat flux data base did not contain a sufficient number of

data points to statistically support the advanced nuclear fuel-boiling (ANFB-1125)

correlation that was used to provide the uncertainty measurement

for measuring the

performance of the SPC fuel for operation in Cycles 7-12. Performance measuring of the

other fuel in the core was not affected by the ANFB-1125 correlation. The net result was

that the OLMCPR for the SPC fuel was nonconservative because the uncertainty applied

to the calculation was not statistically supported by the available data.

The limits for fuel

supplied by current vendor, Asea Brown Boveri/Combustion Engineering (ABB/CE) were

adequate.

Pertaining to Cycle 12 only, the OLMCPR was not calculated in accordance with NRC-

approved topical reports referenced in Technical Specification 5.6.5.b, by the current

fuel vendor (ABB/CE). Specifically, a condition set forth in the NRC-approved generic

Topical Report CENPD-300-PA, "Reference Safety Report for Boiling Water Reload

Fuel," July 1996, had not been satisfied.

Restriction 7 of the report stated that an

independent evaluation of the current fuel vendor's US96A7 correlation should be

performed and compared against test data.

Had this condition been met, the

inadequacy of the ANFB-1125 correlation would have been identified. As a result, the

inspectors determined that the ABB/CE US96A7 correlation used by ABB/CE to describe

-4-

the performance of SPC fuel for Core Cycle 12, was deficient because absolute errors

were propagated by application of the SPC correlation. At the end of that inspection, the

inspectors could not determine if a revised operating limitdeveloped from a statistically

valid correlation, was exceeded,

during Core Cycles 7-12. This was an unresolved item.

The safety limitminimum critical power ratio (SLMCPR) was also affected because

it was

determined by analyzing to obtain delta (6,) MCPR, starting from the OLMCPR for limiting

transients.

Therefore, using the nonconservative OLMCPR as a starting point to

determine ifthe defined limiting condition for SLMCPR would be reached or exceeded,

also yielded an incorrect value for the safety limit. The inspectors were not sure ifa

revised SLMCPR was exceeded or could have been exceeded any time during Core

Cycles 7-12. This was an unresolved item.

As a result of the above unresolved items, the inspectors also questioned the adequacy

of the design control process to assure that the nuclear fuel design bases were

successfully translated into facility license limits. This was a third and final unresolved

item.

Because of the determination by the NRC inspectors that the OLMCPR and SLMCPR

were nonconservative, the licensee submitted a technical specification amendment

request for Cycle 13 (the current cycle of operation) to set the SLMCPR at 1.13 for the

SPC fuel in Cycle 13. This represented

a significant change from the previous limits of

1.07 for Core Cycles 7-12. The new limitwas deteimined by the application of a

conservative multiplier applied to the methodology and the Cycle 13 benchmark

calculations.

The OLMCPRs were changed accordingly and the amendment was

approved, allowing startup of the unit.

The licensee chose to respond to the unresolved items by performing investigation and

analysis to justify a SLMCPR limitof 1.10 and an appropriately adjusted OLMCPR. This

was thought to be an accurate and conservative estimate based on the conditions that

would exist when the SPC database

issue was finally statistically resolved.

Concurrent

with the effort by the licensee, the NRC was reviewing the SPC development of a

method to estimate the additional uncertainty in the ANFB-1125 correlation by

application of an additive constant.

Again, this was necessary because of the limited

experimental critical heat flux data available. At the time'of the inspection, the NRC

review of the SPC submittal was not complete, so the use of 1.10 as a valid limitcould

not be recognized.

4

'

The licensee's response letter to the unresolved items, dated November 25, 1997, stated

that the revised OLMCPR had been exceeded numerous times during Core Cycles 7-12,

but that the revised safety limithad never been exceeded,

nor could it have been

exceeded given the analyzed conditions. The response,

however, did not address the

adequacy of the design control process to assure the design and implementation of

appropriate facility license limits for operation of the nuclear fuel.

-5-

E1.2 Assessment for Potential to Exceed Technical Specification Safety and Operating Limits

a.

In

i n

o

2

3

The inspectors reviewed the licensee's November 25, 1997, response to the unresolved

items with respect to adherence to the: (1) OLMCPR and SLMCPR for the SPC fuel

during Core Cycles 7-12, and (2) graphs depicting MCPR for Core Cycles 8-12. The

inspectors also reviewed licensee initial and followup submittals requesting a license

amendment and the amendment

to change the cycle specific MCPR for Core Cycle 7.

b.

In the November 25, 1997, response,

the licensee evaluated the impact of a revised

additive uncertainty constant and a chosen SLMCPR of 1.10, and concluded that:

~

The OLMCPR associated with an SLMCPR of 1.10 was exceeded numerous

times for each of the previous Core Cycles 7-12.

~

The SLMCPR was not exceeded for any of the actual operating events or

transients experienced during Cycles 7-12.

~

The SLMCPR could not have been exceeded during Cycles 7-12 for any

postulated anticipated operatio'nal occuriences (AOOs) ifthe actual plant

operating conditions during those cycles were used instead of the design basis

assumptions

used for reload transient analyses.

The inspectors agreed with the licensee's first two above conclusions, but disagreed

with the derivation of the third conclusion.

The licensee's position was that the limiting

transient should be analyzed assuming actual conditions that existed during Core

Cycles 7-12. Therefore, because the turbine bypass system was not declared

inoperable during high power operation for any of the previous cycles, the limitingAOO,

turbine trip without bypass, need not be analyzed.

Consequently,

in the response,

the

analysis was performed assuming that automatic operation of the turbine bypass was

available.

The inspectors'osition was that the design basis assumptions prescribed for the reload

transient analyses define the limitingAOO during high power conditions in the Final

Safety Analysis Report (FSAR). Therefore, analysis without bypass capability should be

performed to validate the analysis.

However, the licensee determined that it was

acceptable to analyze a turbine trip with the turbine bypass available and a'ssume it

would operate during the postulated event.

This approach was different from,

and'xplicitly

contrary to, the design basis assumptions for the analysis in Chapter 15 of the

FSAR.

0

-6-

r

in

Limi Viol 'o

The inspectors reviewed WNP-2 operational data graphs for Cycles 8-12 (July 1992-

March 1997) to identify the operating conditions with lowest margin to critical power

during these five operating cycles.

Table

1 below shows the most limiting conditions for

each of these cycles using the old additive constant uncertainty values, which resulted in

an SLMCPR value of 1.07.

Table 1:

Most Limiting Operating Conditions Using Original Additive Constants

Uncertainty

Date

7/29/92

" 1/12/94

4/15/95

1 2/1/95

11/21/96

Cycle

10

12

Power %

99.7

99.9

99.9

100.0

100.1

Flow%

96.0

93.2

92.8

96.4

95.8

  • FLCPR

0.996

0.987

0.980

0.979

0.955

MCPR

1.26

1.31

1.30

1.27

"Fraction of Limiting Critical Power Ratio

In the November 25, 1997, response, the licensee evaluated the impact of a revised

correlation uncertainty on the SLMCPR and concluded that the SLMCPR value should

be at least 0.03 higher than assumed.

This conclusion was based on a revised

ANFB-1125 correlation uncertainty value of 0.0195, which was the least conservative

value under review by the NRC at the time of the inspection.

The application of the

0.0195 correlation uncertainty constant

resulted in the derivation of the 1.10 SLMCPR.

The response

also indicated that other uncertainties associated with transient hMCPR

and less certainty of the database

could result in a difference between corrected and

uncorrected SLMCPR of 0.06.

From discussion with NRC review personnel, the

inspectors determined that the correlation uncertainty value could be as high as 0.026,

which would result in larger MCPR penalty. Therefore the final approved safety and

operating limits were likelyto be more restrictive (higher), but the least restrictive (lowest)

expected value for SLMCPR was 1.10.

The licensee stated that their study to develop the response concluded that the

OLMCPR would have been exceeded

on numerous occasions during each of the

evaluated cycles (7-12) ifthe revised correlation uncertainty constant and resultant

additive MCPR constant uncertainty had been used to develop the limitfor the SPC

fuel. Also according to the licensee, the most significant departure from the revised

OLMCPR occurred during Core Cycle 8 where it was exceeded

by about 5 percent.

The inspectors determined through the review of graphs depicting MCPR for Core

Cycles 8-12, and applying licensing bases analysis values,

that the limitof 1.10

may have been exceeded

by as much as 10 percent, ifthe higher correlation

-7-

uncertainty of 0.026 had been applied.

The inspectors noted that operating in excess

of the OLMCPR in the core operating limit report would have violated Technical Specification 3.2.2 ifthe appropriate OLMCPR value had been included in the core

operating limit report.

f

Limi Durin

c al0 era in

Ev n

In the November 25, 1997, response,

the licensee determined that, from 1991 to 1997,

WNP-2 was subject to five transients that could have potentially challenged the

SLMCPR. However, upon comparing relative severity, none of these transients

resembled the limiting transient described in Chapter 15 of the FSAR. The conditions for

these transients are summarized in Table 2, and, based on review of the data, the

inspectors determined that the SLMCPR was not exceeded

in any of these transient

events.

Table 2:.

Operational Events and Their Impact on SLMCPR

Date

11/19/91

8/15/92

8/3/93

Event

FW Controller

Failure

Instability

Event

MSIV Closure

Initial

  • FLCPR

0.864

0.860

Initial

CPR

1.435

1.940

1.442

hCPR

0.05

0.37

0.04

Transient

CPR

1.385

1.570

1.402

2/18/95

4/4/95

Turbine Trip with

Bypass Available

Turbine Trip with

Bypass Available

0.842

0.952

1.473

1.303

-0

0.01

1.473

1.293

  • Fraction of Limiting Critical Power Ratio
    • Unknown, Unstable

Po

n i

I

fe

Limi Violation

The most limitingAOO for WNP-2 was identified as a turbine trip without bypass (TTNB).

According to the Cycle 11 transient analysis report, the TTNB AOO resulted in a 8 CPR

of 0.21 for SPC Atrium-9 fuel, when the uncorrected ANFB-1125 correlation was used.

As previously stated, the licensee had evaluated the effect of the revised correlation

constant for Atrium-9 fuel and concluded that a b,CPR correction of 0.03 was required for

the new limit (1.10). Thus, the TTNB AOO was estimated to result in a BCPR of 0.24

when the revised constant was used.

-8-

Table 3 shows the most limiting CPR for SPC fuel that could have been reached or

exceeded during a TTNB AOO using the above assumptions

at the worst point in each of

the previous five cycles.

This table indicates that, had a limiting TTNBAOO occurred,

the safety limitwould have been reached or exceeded regardless of whether the safety

limit MCPR value was 1.10 or 1.13.

Table 3:

Projected CPR During Design Basis Turbine Trip Without Bypass Starting

From Actual Conditions on Indicated Date

Date

7/29/92

1/1 2/94

4/1 5/95

12/1/95

11/21/96

Cycle

10

12

Transient MCPR

1.02

1.07

1.06

1.03

1.10

Licensee representatives

did not agree that the revised SLMCPR of 1.10 could have

been reached or exceeded under the conditions existing on the dates above, and stated

that additional information would be provided to substantiate their position.

In addition,

the inspectors and licensee representatives

disagreed on other issues related to the

assumptions

used in the analysis.

These disagreements

are listed below.

The licensee's analysis used a control rod scram insertion time that was based

on historical surveillance results and not the maximum insertion time for which

operation is allowed by the technical specifications.

The licensee's analysis assumed

a predicted actual axial power shape that was

based on previous end-of-cycle conditions, instead of the axial offset assumed

in

the FSAR licensing analysis.

The licensee's analysis assumed

an all-control-rods-out condition instead of the

limiting rod patterns used in the FSAR licensing analysis.

During the inspection, the licensee was unable to supply the same data for Core Cycle 7,

as that supplied for Cycles 8-12, without significant added effort. The inspectors

determined that they had sufficient data.

However, as shown above, during each of the

evaluated cycles, the potential existed to reach or exceed the revised SLMCPR during a

turbine trip event with the bypass system unavailable.

This transient described in the

-9-

licensing basis as the limiting event that is analyzed

from full power operation in

Chapter 15 of the FSAR. The inspectors believed that the potential existed to reach or

exceed the revised SLMCPR during all five of these cycles.

However, the licensee's

representatives

indicated they would be able to provide additional information to refute

the inspectors'osition.

The review of the additional information is discussed later in

Section E1.3.

In a letter from the licensee to the NRC dated February 28, 1991,

and supplemented

by

letters dated March 21, 1991, and April26, 1991, the licensee requested to amend the

facility license.

The amendment sought was to modify the facilitySLMCPR and the

associated

bases to reflect cycle specific analysis resulting from use of a new reload

methodology.

The new methodology was necessary to account for the loading of fuel

from a new vendor (SPC).

The inspectors noted that the amendment was granted to change the safety limitfor the

SPC fuel to 1.07.

The 1.07 limitwas in effect for Core Cycles 7-12. As noted above, it

was necessary for the licensee to change the limit in a more conservative direction once

the NRC identiflied the undesirable conditions at the vendor facility.

~nisi

The inspectors concluded that the licensee had operated the SPC fuel in Core

Cycles 7-12 in excess of a revised OLMCPR based on revised correlation constants and

additive uncertainties applied to the SLMCPR of 1.07.

On the basis of the November 25,

1997, response, the SLMCPR was not exceeded during the actual events and transients

experienced by the plant during Core Cycles 8-12.

Data was not provided by the

licensee to assess

whether the limitwas exceeded during Core Cycle 7. The licensee's

analysis to determine ifthe limitcould have been exceeded during Core Cycles 8-12 did

not use licensing bases assumptions,

bounds, and parameters.

vi

f

d ii

f

In

i

0

The licensee provided additional information on March 9, 1998, to refute the NRC

position that the potential existed to reach or exceed the revised SLMCPR during Core

Cycles 8-12. The inspectors reviewed this information in order to make the

determination ifthe potential still existed.

Findin

and Obs

rva io s

At the end of the on-site portion of the inspection, licensee representatives

and the

inspectors agreed on the selection of a specific time in Core Cycle 8 for analysis to

provide the additional information. The March 9, 1998, additional information submittal

documented two licensee calculations using the NRC-approved models WNP-2

-10-

RETRAN and VIPRE calculational codes.

The conditions selected for analysis by the

licensee were the actual conditions that occurred near the end of Cycle 8. The simulated

transient used for the analysis was the AOO of TTNB because

it was'he most limiting

transient for the analyzed baseline conditions according to Chapter 15 of the FSAR. The

inspectors determined that the conditions and transient selected for analyses were

appropriate.

One calculation simulated a load rejection without bypass using the actual plant

conditions (as opposed to licensing bases initial conditions).

For this calculation, the

licensee used a condition near the end of cycle with a minimum fraction of limiting CPR

(MFLCPR) value of 0.993, which was considered limitingfor Cycle 8. The actual core

power, coolant flow, vessel pressure,

and rod pattern were used instead of the licensing

bases initial conditions. The results of the licensee's calculation indicated that, by using

the actual initial.operating conditions for this event, the loss of CPR margin (b,CPR) was

as much as 0.125. This reduction was accomplished through a combination of the lower

initial power, flow, and pressure and because some rods were partially inserted in the

core, which provided for a faster negative reactivity insertion during the scram.

The

licensee concluded that this additional margin compensated

amply for the erroneous

safety limitvalue assumed during operation; thus, a load rejection without bypass would

not have caused a safety limitviolation should it have occurred during the Cycle 8 most

limiting conditions.

The other calculation reproduced the licensing-bases

event of load rejection without

bypass event for Cycle 8. This calculation indicated that the hCPR during a licensing-

bases load rejection without bypass was 0.259. This reduction in margin was

significantly higher than the reduction assumed for actual conditions (0.125).

During

actual operation, the licensee was not aware of the potential safety limitviolation and did

not take action to minimize its impact. Therefore, administrative controls and operating

limits would not have precluded facilityoperation within the licensing basis envelope.

L

As observed

in Table

1 of this report, WNP-2 was operated with MCPR values as low

as 1.26 during Cycle 8.

Therefore, margin was insufficient to preclude reaching or

exceeding a revised safety limitof 1.10 for the limiting transient initiated just within the

envelope of licensing basis.

This calculation confirmed the inspection finding that, by

operating with the erroneous. operating and safety limitvalues, the facilitywas operated

in a mode that potentially could have resulted in exceeding a revised safety limit based

on a conservative application of the ANFB-1125 correlation.

~nisi

Administrative controls and operating limits in place during Cycles 7-12 would not have

ensured operation within the envelope of the licensing basis.

Therefore, had the limiting

transient occurred with design basis operating conditions, the revised safety limitcould

have been exceeded.

-11-

vl in fLi

n

'

'n

n

IP

an Vn

r

Ins e

'o

The inspectors reviewed procedures and documentation that licensee personnel

depicted as representing the integrated process for the determination of technical

specification core power distribution limits. Discussions were also held with fuel design

engineering and fuel management

personnel involved in the fuel and core thermal limits

determination process.

The inspectors conducted a review of the licensee's process for core reload design

control to identify and evaluate features and elements that would challenge the adequacy

of the vendor supplied core operating and safety limits. This effort necessitated

additional review of fuel management

and procurement processes.

b.,

fv

I

According to licensee personnel, the process of core reload was processed

as a design

modification. The inspectors reviewed Procedure PPM 1.4.1, "Plant Modifications,"

Revision 23. This upper-tier site document provided the administrative guidance for

planning, implementing, and tracking modifications, but did not reach to the level of

providing requirements for detailed review of vendor-provided limits. The inspectors also

reviewed Procedure El 2.8, "Generating Facility Design Change Process," Revision 14.

This lower-tier engineering document was the engineering instruction for processing

design modifications. The inspectors were unable to identify any attribute in this

procedure that would result in an evaluation of the adequacy of vendor-provided

cycle-specific operating and safety limits to meet the licensing basis.

Licensee representatives

stated that the supplier's quality surveillance program was

instrumental in the process for core reload design control. The inspectors reviewed

Procedure SQI 7.4, "Source Surveillance Activities," Revision 11. This procedure

describe'd the methods for the quality assurance

organization to perform surveillance

activities of vendors who were a source of services, material, and hardware.

This

procedure provided the administrative guidance needed to schedule, plan, perform, and

report source surveillance activities. The inspectors determined that this procedure did

not cause the WNP-2 staff to perform activities associated with validating the adequacy

of vendor-supplied license limits.

Licensee representatives

also stated that design review of fuel vendor analysis was

performed in accordance with Fuel Management Instruction FMI 4-3, "Reload and Fuel

Design Reviews," Revision 5, for every new core, prior to startup.

This instruction

described requirements and responsibilities for conducting design reviews of reload

nuclear fuel, including review of the methods and procedures used by vendors in making

fuel design decisions.

The procedure required the development of a review checklist and

suggested

topics to be included. According to the procedure, the checklist was expected

-12-

to consist of a series of questions to be answered during the core design review. The

inspectors reviewed the design review packages,

including the completed design review

checklists, for Core Cycles 10 and 11. None of the questions in the checklists required

evaluating the validity of the vendor-proposed

fuel operating and safety MCPR limits.

In summary, licensee oversight of the previous and current fuel vendors did not assure

that the core power distribution and fuel thermal limits submitted by letters dated

August 2, 1990, February 28, 1991, and May 20, 1991, were accurate and conservative.

10 CFR Part 50, Appendix B, Criterion III requires that established measures

assure that

applicable regulations and the design basis are correctly translated into specifications,

drawings, procedures,

and instructions.

The inspectors determined that established

measures

did not assure the translation of regulatory requirements and the design basis

for the reactor core into the facility license Technical Specifications.

Consequently, the

licensee failed to ensure that sufficient margin was available in its SLMCPR SAFDL.

This was an apparent violation of Criterion III of Appendix B to 10 CFR Part 50

(50-397/9801-01).

The inspectors concluded that vendor development and implementation of MCPR

operating and safety limits for WNP-2 fuel were not adequate to assure that the limits

were accurate and conservative.

Licensee oversight of the fuel vendors'esign

processes

and controls for the nuclear fuel supplie'd to WNP-2, failed to detect tliat

an'nadequate

technical specification limitwas developed.

The failure to establish

measures to assure that the design bases were correctly translated into technical

specifications was identified as an apparent violation of Criterion III,Appendix B to

10 CFR Part 50.

ES

Miscellaneous Engineering Issues

E8.1

Iv

I

-

7 -: failure to establish measures to assure that

design bases are translated into technical specification limits in accordance with

Criterion III of Appendix B to 10 CFR Part 50, for Core Cycles 7-12. This item was

evaluated in Section E1.2.

E8.2

Iv

I

- 9

7 1-0: failure to operate the reactor core in

accordance with a revised OLMCPR for Technical Specification 3.2.2, for Core

Cycles 7-12. This item is evaluated in Section E1.3.

E8.3

I

d

nr

Iv d I

5 -

7/9711-: failure to assure that a revised SLMCPR

could not be exceeded during AOOs for Core Cycles 7-12. This item is evaluated in

Section E1.3.

-13-

X1

Exit Meeting Summary

V

The inspectors met with licensee personnel on February 12, 1998, for a briefing of

preliminary findings. Licensee representatives

disagreed with the inspectors conclusion

that the potential existed to exceed the revised safety limitfor Core Cycles 8-12.

Consequently, the licensee's representatives

indicated their intent to provide additional

information for NRC review. The licensee's additional information was submitted in its

March 9, 1998 letter. Subsequently,

a supplemental telephonic exit meeting was held on

April22, 1998. At that time, the licensee was informed of the apparent violation

discussed

in this inspection report and the NRC's intent to hold a predecisional

enforcement conference.

Qs

tl

SUPPLEMENTAL INFORMATION

PARTIALLIST OF PERSONS CONTACTED

MLi K5lK

D. Atkinson, Manager, Quality Assurance

P. Bemis, Vice President, Nuclear Operations

S. Bian, Supervisor, Reactor/Fuels Engineering

R. Casarant, Engineer, Supplier Quality

D. Coleman, Acting Manager, Regulatory and Industry Affairs

T. Cong Hoang, Engineer, Fuel Design

J. Fisher, Engineer, Fuels Design

P. Inserra, Manager, Licensing

W. Kiel, Regulatory Programs Specialist

W. Moore, Consulting, Engineer, Fuel Design

D. Richey, Engineer, Fuels Design

G. Smith, Plant General Manager

J. Teachman, Principal Engineer, Fuel Design

R. Torres, Manager, Reactor Fuels Engineering

R. Webring, Vice President, Operations Support

QX~~ZS

W. Harris, Asea Brown Boveri/Combustion Engineering

J. Ingham, Siemens Power Corporation

S. Boyinton, Senior Resident Inspector

H. Wong, Chief, Projects Branch E

C. Poslusny, Jr., Project Manager,.Office of Nuclear Reactor Regulation

INSPECTION PROCEDURES USED

IP 92903

Followup - Engineering

~Oned

50-397/98-01

ITEMS OPENED, CLOSED, AND DISCUSSED

EEI

Failure to Control Design of Facility Technical Specification

Limit(Section E1.4)

t

e

-2-

GLzzd

50-397/9711-01

50-397/9711-02

50-397/9711-03

URI

Adequacy of Design Control of Facility License Limits

(Section E8.3)

URI

Potentially Exceeding OLMCPR During Core Cycles 7-12

(Section E8.3)

URI

Determination of Potential to Exceed SLMCPR During

Anticipated Operational Transients (Section E8.4)

El 2.8

FMI 4-3

PPM 1.4.1

SQI 7.4

LIST OF PROCEDURES REVIEWED

Generating Facility Design Process,

Revision 14

Reload and Fuel Design Reviews, Revision 5

Plant Modifications, Revision 23

Supplier Quality Instruction, Revision 11

LIST OF DOCUMENTS REVIEWED

Nuclear UtilityProcurement Issues Committee Audit of Siemens Power Corporation,

July 24, 1997

Procurement Quality Assurance Vendor File, Siemens Power Corporation

Updated Final Safety Analysis Report, Chapter 15

Critical Power Ratio Graphs, WNP-2 Core Cycles 8-12

Core Reload Design Review Reports, WNP-2 Core Cycles 9-11

License Response to Unresolved Items, November 25, 1997

Cycle 13 Core Operating Limit Report

WNP-2 Technical Specifications

License Response to Unresolved Item 50-397/9711-03, March 9, 1998