Confirmatory Order Modifying License Effective Immediately. Order Confirms WPPSS Commitment to Complete Inplementation of Thermo-Lag 330-1 Fire Barriers C/As in Spring 1999 & Overall Work Package Closeout by Dec 1999
ML17292B307
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 03/25/1998
From: Collins S
NRC (Affiliation Not Assigned)
To:
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
Shared Package
ML17292B308 List:
References
NUDOCS 9804030377
Download: ML17292B307 (10)


Text

7590-01 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of

)

)

WASHINGTON PUBLIC POWER SUPPLY SYSTEM )

)

(Nuclear Project No. 2)

)

Docket No. 50-397 CONFIRMATORYORDER MODIFYINGLICENSE EFFECTIVE IMMEDIATELY Washington Public Power Supply System, WPPSS, ( WPPSS or the Licensee) is the holder of Facility Operating License No. NPF-21, which authorizes operation of Nuclear Project No. 2 (WNP-2) located in Richland, Washington, at steady state reactor core power levels not in excess of 3485 megawatts thermal (rated power).

The staff of the U.S. Nuclear Regulatory Commission (NRC) has been concerned that Thermo-Lag 330-1 fire barrier systems installed by licensees may not provide the level of fire endurance intended and that licensees that use Thermo-Lag 330-1 fire barriers may not be meeting regulatory requirements.

During the 1992 to 1994 time frame, the NRC staff issued Generic Letter (GL) 92-08, "Thermo-Lag 330-1 Fire Barriers" and subsequent requests for additional information that requested licensees to submit plans and schedules for resolving the Thermo-Lag issue.

The NRC staff has obtained and reviewed ail licensees'orrective plans and schedules.

The staff is concerned that some licensees may not be making adequate progress toward resolving ihe plant-specific issues, and that some implementation schedules may be either too tenuous or too protracted.

For example, several licensees informed the NRC staff that their completion dates had slippedby 6 months to as much as 3 years.

For plants that have 9804030377 980325 PDR ADQCK 05000397 F

PDR

completion action scheduled beyond 1997, the NRC staff has met with these licensees to Ch discuss the progress of the licensees'orrective actions and the extent of licensee management attention regarding completion of Thermo-Lag corrective actions.

In addition, the NRC staff discussed with licensees the possibility of accelerating their completion schedules.

WPPSS was one of the licensees with which the NRC staff held meetings.

At these meetings, the NRC staff reviewed with WPPSS the schedule of Thermo-Lag corrective actions described in the WPPSS submittals to the NRC dated April 13, 1993, February 11, 1994, November 9, 1994, April27, 1995, and September 26, 1997.

Based on the information submitted by WPPSS and provided during the meetings, the NRC staff has concluded that the schedules presented by WPPSS are reasonable.

This conclusion is based on the (1) amount of installed Thermo-Lag; (2) the complexity of the plant-specific fire barrier configurations and issues; (3) the need to perform certain plant modifications during outages as opposed to those that can be performed white the plant is at power, and (4) integration with other significant, but unrelated issues that WPPSS is addressing at its plant.

In order to remove compensatory measures such as fire watches, it has been determined that resolution of the Thermo-Lag corrective actions by WPPSS must be completed in accordance with current WPPSS schedules.

By letter dated February 27, 1998, the NRC staff notified WPPSS of its plan to incorporate WPPSS's schedular commitment into a requirement by issuance of an order and requested consent from the Licensee.

By letter dated March 12, 1998, the Licensee provided its consent to issuance of a Confirmatory Order.

1 r,

(

f

III.

0 The Licensee's commitment as set forth in its letter of March 12, 1998, is acceptable and is necessary for the NRC to conclude that the public health and safety are reasonably assured.

To preclude any schedule slippage and to assure public health and safety, the NRC staff has determined that the Licensee's commitment in its March 12, 1998, letter be confirmed by this Order. The Licensee has agreed to this action. Based on the above, and the Licensee's consent, this Order is immediately effective upon issuance.

IV.

Accordingly, pursuant to sections 103, 161b, 161i, 161o, 182, and 186 of the Atomic Energy Act of 1954, as amended, and the Commission's regulations in 10 CFR 2.202 and 10 CFR Part 50, IT IS HEREBY ORDERED, effective immediately, that:

WPPSS shall complete final implementation of Thermo-Lag 330-1 fire barrier corrective actions at Washington Public Power Supply System, Nuclear Project No. 2, described in the WPPSS submittals to the NRC dated April 13, 1993, February 11, 1994, November 9, 1994, April27, 1995, and September 26, 1997, during the R-14 Maintenance and Refueling Outage (Spnng 1999). Overall work package close-out willbe completed by December 1999.

The Director, Office of Nuclear Reactor Regulation, may relax or rescind, in writing, any provisions of this Confirmatory Order upon a showing by the Licensee of good cause.

I',

l li

V.

Any person adversely affected by this Confirmatory Order, other than the Licensee, may request a hearing within 20 days of its issuance.

Where good cause is shown, consideration will be given to extending the time to request a hearing. A request for extension of time must be made in writing to the Director, Office of Nuclear Reactor Regulation; U.S. Nuclear Regulatory Commission, Washington, D.C. 20555, and include a statement of good cause for the extension.

Any request for a hearing shall be submitted to the Secretary, U.S. Nuclear Regulatory Commission, Attention: Docketing and Services Section, Washington, D.C. 20555.

Copies of the hearing request shall also be sent to the Director, Office of Nuclear Reactor Regulation, U. S.

Nuclear Regulatory Commission, Washington, D. C. 20555, to the Assistant General Counsel for Hearings and Enforcement at the same address, to the Regional Administrator, NRC Region IV at 611 Ryan Plaza Drive, Suite 400, Artington, Texas 76011, and to the Licensee.

Ifsuch a person requests a hearing, that person shall set forth with particularity the manner in which his/her interest is adversely affected by this Order and shall address criteria set forth in 10 CFR 2.714(d).

Ifa hearing is requested by a person whose interest is adversely affected, the Commission willissue an Order designating the time and place of any such hearing.

Ifa hearing is held, the issue to be considered at such hearing shall be whether this Confirmatory Order should be sustained.

ln the absence of any request for hearing, or written approval of an extension of time in which to request a hearing, the provisions specified in Section IVabove shall be final 20 days from the date of this Order without further order or proceedings.

Ifan extension of time for requesting a hearing has been approved, the provisions specified in Section IVshall be final

~ i

4

~

e Ji I

/t I

i II fl il I

I

5 when the extension expires ifa hearing request has not been received.

An answer or a request 4

I for hearing shall not stay the immediate effectiveness of this Order.

FOR THE NUCLEAR REGULATORYCOMMISSION Dated at Rockville, Maryland this 25thday of March 1998 a

ue

. C i s, Director Office of Nuclear Reactor Regulation