ML17292A458

From kanterella
Jump to navigation Jump to search
Insp Rept 50-397/96-16 on 960731-0809.Violations Noted. Major Areas Inspected:Operations,Engineering & Effectiveness of Licensee Controls & Evaluations
ML17292A458
Person / Time
Site: Columbia 
Issue date: 09/12/1996
From: Johnston G, Mckernon T, Tracy G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML17292A454 List:
References
50-397-96-16, NUDOCS 9609190289
Download: ML17292A458 (23)


See also: IR 05000397/1996016

Text

ENCLOSURE 2

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket No.:

License No.:

Repoit No.:

Licensee:

Facility:

Location:

Dates:

Inspectors:

Approved By:

50-397

NPF-21

50-397/96-1 6

Washington Public Power Supply System

Washington Nuclear Project-2

3000 George Washington Way

Richland, Washington

July 31 through August 9, 1996

Thomas O. McKernon, Operator Licensing Examiner

Gary W. Johnston,

Senior Project Engineer

Glenn M. Tracy, Acting Deputy Director

Division of Reactor Safety

Attachment:

Partial List of Persons Contacted

List of Inspection Procedures

Used

List of Items Opened

List of Licensee Procedures

and documents Reviewed During This

Inspection

9609i90289

960912

PDR

ADOCK 05000397

8

PDR

-2-

EXECUTIVE SUMMARY

Washington Nuclear Project-2

NRC Inspection Report 50-397/96-16

From July 31 through August 9, 1996, a special inspection was conducted to review two

recent events, an early criticality occurring outside the estimated critical rod position

tolerance band during startup on June 27, 1996, and a power excursion on July 20,1996,

which resulted from the manipulation of the adjustable speed drive system by a

nonlicensed person.

The inspectors made the following conclusions.

~Oeretione

The operating crew failed to follow procedures when distracting activities were

conducted during the approach to criticality (Section 01.2).

Multiple procedural violations occurred due to an erroneous control room operator

log entry and a failure to use the correct strip chart paper on one of the source

range monitor recorders (Section 01.2).

The shift manager and the control room supervisor failed to use a conservative

decision making process,

did not exercise good command, control, and

communications,

and failed to elevate the estimated critical position problem to

upper operations management

(Section 01.2).

~En ineerin

The reluctance of the station nuclear engineers to bring forward to management

their initial concerns related to the accuracy of the estimated critical position

calculation demonstrated

a lack of conservative decision making (Section E1.2).

The continuing effort to verify the adequacy of the estimated critical position

calculations were thwarted by inadequate training in the use of the associated

software.

Therefore, combined with a lack of proceduralization for estimated

critical position calculations, the station nuclear engineers efforts merely continued

to reinforce the error in usage of the software (Section E1.2).

The lack of a reviewed and approved procedure for conducting an estimated critical

position calculation contributed to the early criticality event (Section E1.2).

The lack of an adequate

procedure with sufficient controls resulted in a nonlicensed

individual operating the reactor recirculation system and affecting reactivity

(Section 01.3).

-3-

Effectiveness of Licensee Controls and Evaluations

~

The licensee's investigations were too narrowly focused and did not identify all

facts involved in the events (Section 01.4).

4-

Re ort Details

On June 27, 1996, the reactor was restarted

and subsequently

shut down due to an error

in calculating the estimated critical rod position.

The reactor was restarted

on June 29,

and the licensee recommenced

power ascension

and testing of the digital feedwater and

adjustable speed drive modifications.

On July 20, while at 68 percent power, the plant

experienced

a short duration 15 percent power transient due to an error associated with

adjustable speed drive testing.

01

Conduct of Operations

01.1

General Comments

71707

Using Inspection Procedure 71707, the inspectors reviewed the operational aspects

of two recent events: an early criticality occurrence;

and Reactor Recirculation

Control Pump-1A speed transient during adjustable speed drive testing.

In the

former event, conduct of operations lacked the rigor of command and control

required by procedures during the approach to criticality and concerns related to

deviation from the estimated criticality band were not elevated to the appropriate

management

levels.

In the latter event,

a nonlicensed person inadvertently caused

a reactivit

transient b

erroneousl

im utin

data into the ad'ustable

speed drive

y

y

y

p

9

I

system.

01.2 Criticalit Achieved Prior to Minimum Estimated Critical Position

a.

Ins ection Sco

e 71707

On Thursday, June 27, 1996, reactor criticality was achieved prior to the minimum

expected point of criticality calculated by the station nuclear engineer.

The

inspectors reviewed control room logs, facility procedures,

data logs, and conducted

interviews with key licensee personnel.

The inspectors also reviewed the actions of

the control room shift operators to ascertain whether their actions contributed to

the estimated critical position event.

b.

Observations

and Findin s

0 erations Command

Control

and Communications

The inspectors observed that during the estimated critical position event,

a number

of barriers to effective command, control, and communications were either

breached

or circumvented:

(1)

Initial communications between the backshift shift manager and the onshift

station nuclear engineer indicated

a low confidence level in the estimated

critical position calculation.

While the shift manager questioned the results

-5-'f

the calculation, particularly with respect to its difference from the

estimated critical position calculated for the prior initial criticality of June 14,

1996, no compensatory

measures

of monitoring were deemed necessary.

Cautionary actions of Step 4.2.5 in Procedure

PPM 1.3.59, "Reactivity

Management," were discussed

between the station nuclear engineer and the

shift manager.

This step required that, "Ifcriticality occurs before the

Minimum Allowable Critical Position, stop control rod withdrawal, notify the

control room supervisor.

The control room supervisor should direct the

control room operator to drive control rods in the reverse order."

Additionally, the control room supervisor erroneously assumed,

by review of

the station nuclear engineer's estimated critical position memorandum which

was addressed

to the reactor/fuels engineering manager, that the

memorandum had been reviewed by the manager when, in fact, it had not.

The results of subsequent

discussions

between the onshift station nuclear

engineer and the estimated critical position calculation (PowerPlex) software

custodian, also a station nuclear engineer, at 0200 hours0.00231 days <br />0.0556 hours <br />3.306878e-4 weeks <br />7.61e-5 months <br />, indicated that the

offshift station nuclear engineer doubted the estimated critical position

calculation results.

However, the onshift station nuclear engineer did not

consider it necessary

to elevate the lack of confidence in the estimated

critical position calculation up to his management

nor did he share the

information with the shift manager or the control room supervisor.

At 0533 hours0.00617 days <br />0.148 hours <br />8.812831e-4 weeks <br />2.028065e-4 months <br />, Intermediate Range Monitor IRM-Det-1C appeared

to fail and

was declared inoperable by the operators.

At the direction of the shift

manager, the control room supervisor (also the reactivity manager) diverted

his attention to filling out the limited condition of operation log paperwork.

This activity and his following preparations for turnover to the oncoming

control room supervisor consumed the majority of his attention and focus

until the time of turnover.

These activities were in noncompliance with the

startup Procedure

PPM 3.1.2, Revision 31, Step 4.2.2 caution, which stated,

that, "During the approach to criticality, avoid activities that can distract the

operator at the controls and the control room supervisor."

This was an

apparent violation of Technical Specification 6.8.1a (50-397/9616-03).

At the time of turnover, the shift technical advisor advised both control room

supervisors that the plant was close to going critical. The shift technical

advisor returned to the front panel and the reactor operator and shift

technical advisor continued to withdraw control rods.

The control room

supervisors did not stop their turnover and focus on the approach to

criticality. This was another example of a failure to adhere to the Reactivity

Management Procedure.

Procedure

PPM 1.3.1, Revision 26, "Conduct of

Operation," Step 4.6.1, stated, "During periods when reactivity

manipulations are in progress or plant activities which could affect reactivity

occur, the control room supervisor shall assume the responsibility of

Reactivity Manager.

Responsibilities include ensuring

a conservative

-6-

approach to operations involving core reactivity changes."

Procedure

PPM

1.3.1, Revision 26, Step 4.6.2 (r) further stated, "Shift turnover of the

control room staff is inappropriate when criticality is imminent." This was

another example of apparent violation (50-397/9616-03).

(5)

During the control room supervisor turnover walkthrough of the control

board panels, the oncoming control room supervisor suddenly observed the

condition of the plant and the source range monitor neutron level. The

reactor operator stated that criticality was imminent. The control room

supervisor discussed

the condition with the station nuclear engineer and

was informed of the deviation from the expected estimated critical position

margin.

The control room supervisor briefly informed the shift foreman.

The shift foreman acknowledged the control room supervisor but did not

internalize the information and act upon it. Instead, the shift foreman

focused upon conducting the shift briefing while the control room supervisor

returned to the at-the-controls area to oversee control rod withdrawals.

Procedure

PPM 1.3.1, Revision 26, Step 4.6.2b stated, "The Reactor

Operator at H13-P603 shall not be distracted by control room activities such

as shift turnover, shift brief, or surveillances."

The conduct of the shift brief

during the approach to criticality was another example of failure to follow

procedures

and apparent violation of Technical Specification 6.8.1a

(50-397/961 6-03).

(6)

In followup interviews, it was determined that the shift technical advisor

who had previously reviewed the estimated critical position calculation did

not internalize the information and, as such, did not serve as a barrier to

identify and inform the control room supervisor of the out-of-tolerance

estimated critical position/criticality conditions.

Actions:

(1)

While the shift manager questioned the estimated critical position calculation

results when presented

the estimated critical position memorandum,

cautionary action statements

in the startup procedure gave the shift manager

confidence in continuing with control rod withdrawal. As discussed

above,

this action resulted in a failure to follow procedures.

(2)

The shift manager directed the control room supervisor to attend to other

duties which detracted from his reactivity manager duties and

responsibilities.

This was an apparent failure to comply with

Procedure

PPM 3.1.2.

(3)

The offgoing/oncoming control room supervisor turnover detracted from the

focus on the approach to criticality and an apparent failure to comply with

Procedure

PPM 1.3.1.

-7-

(4)

The offgoing/oncoming control room supervisors failed to discontinue their

turnover when informed that the reactor was close to criticality.

(5)

The shift manager failed to advise his upper operations management that the

early criticality was approaching

and the minimum estimated critical position

criteria would not be met.

(6)

The shift manager made

a cognizant decision to conduct

a shift briefing

while the control room supervisor and the reactor operator/shift technical

advisor continued to pull control rods.

This action was an apparent

noncompliance with procedures

as discussed

above in item (5) of the

command, control, and communication section.

(7)

The control room supervisor directed the reactor operator to pull control rod 18-47 from step 16 to 26 while the crew monitored the increasing

source range monitor count rate.

The reactor was then declared critical at

0705 hours0.00816 days <br />0.196 hours <br />0.00117 weeks <br />2.682525e-4 months <br />, June 27, 1996, with a source range monitor Channel A

detector reading 7x10'ps,

a reactor period of 345 seconds,

and a reactor

coolant system temperature of 211 degrees f.

In followup reviews of the

control room operator logs, the inspectors determined this data was not

accurately entered into the control room operator log as required by Startup

Procedure

PPM 3.1.2, Revision 31, Step 4.2.7 which stated, "Enter the

following here and in the control room operator log at the time of criticality .

.. Time, Neutron Level, Period, Control Rod Number, Control Rod Position,

Coolant Temperature."

The control room operator log was annotated

as

having a neutron level of 5000 cps.

This erroneous entry represented

a

failure to follow procedures

and a violation of Technical Specification 6.8.1a

(50-397/961 6-01 ).

(8)

Additionally, the inspectors identified that the control room operators had

erroneously installed and not identified one of the source range monitor

recorder's strip chart paper which was of the wrong type.

The strip chart

paper had a linear scale when the appropriate type was one with a

logarithmic scale.

Procedure

PPM 3.1.10, "Operating Data Logs,"

Revision 11, stated, "The purpose of recorder charts is to provide operations

and management

personnel with a permanent record of trends exhibited by

specific plant parameters."

The source range monitor recorder with the

incorrect strip chart paper would not serve the purpose of an accurate

historical permanent record.

This was a failure to follow procedures

and a

violation of Technical Specification 6.8.1a (50-397/9616-02).

c.

Conclusions

The inspectors concluded that apparent violations of regulatory requirements

existed in the operations area of responsibility.

The operating crew failed to follow

procedures when distracting activities were conducted during the approach to

-8-'riticality.

The shift manager and the control room supervisor failed to use a

conservative decision making process,

did not exercise good command, control, and

communications,

and failed to elevate the estimated critical position problem to

upper operations management.

Additionally, procedural violations occurred due to

an erroneous control room operator log entry and a failure to use the correct strip

chart paper on one of the source range monitor recorders.

01.3

Ad ustable

S eed Drive Power Excursion Event

Ins ection Sco

e 71707

On July 20, 1996, while performing tests on the adjustable speed drive system to

ascertain whether or not electronic resonance

of control circuitry might occur at

different pump speeds,

a contract engineer in the adjustable speed drive room

inadvertently caused

a 15 percent change in power from 68 to 53 percent and a

return to the initial 68 percent power level.

The event occurred while efforts were

being taken to serve as compensatory

measures

should an electronic resonance

condition appear during adjustment of the reactor recirculation pumps.

The inspectors reviewed the adjustable speed drive event and conducted interviews

with key facility personnel.

Test procedures

and other control processes

were also

reviewed.

b.

Observations

and Findin s

The inspectors interviewed key operations personnel involved with validation and

verification of Procedure

PPM 8.3.339, "Test Instructions

- Reactor Recirculation

(RRC) Adjustable Speed Drive (ASD) and Reactor Digital Feedwater

(DFW) Control

Power Ascension Test Program," Revision 1. The inspectors noted that the test

procedure had been validated for those areas which could be modeled on the plant-

specific simulator, but was not validated for test areas related to in-plant local

actions such as the input of adjustable speed drive runback values at local panels

inside the adjustable speed drive room.

Further, discussions with operations

personnel indicated that directions for local actions inside the adjustable speed drive

room were discussed

during the pretest brief in the control room.

The procedure

did not contain specific steps by which compensatory measures

were to be taken

should electronic resonance

appear.

The only written guidance that existed was as

an embedded

action statement to a caution in Step 8.9 of the procedure.

As such,

the procedure was inadequate

in that it did not contain measures sufficient to

preclude manipulation of facility controls as expressly prohibited by

10 CFR 50.54(i), in that, a nonlicensed individual operated the reactor recirculation

control system and affected reactivity.

This was considered

an apparent violation

of Criterion V of 10 CFR 50, Appendix B (50-397/9616-05).

-9-

In addition, the plant operations committee review of the test procedure had

identified a potential problem with the procedure

in this area, but had not followed

through with sufficient actions to preclude the event from occurring.

As such, the

licensee had prior knowledge of the potential for the event but did not take

sufficient measures

to preclude its occurrence.

Further, the work control process

did not identify the test evolution as a potential problem because

it did not have

procedural steps to review and, therefore, did not review the task to a level of

depth which would have identified a problem with the procedure.

c.

Conclusions

The inspectors concluded that the procedure controlling adjustable speed drive

testing for local actions in the adjustable speed drive room was inadequate

and an

apparent violation. The inspectors

also concluded that controls and barriers which

would have precluded

a nonlicensed individual from manipulating reactivity were not

established.

As a result, a nonlicensed individual was placed in a position in which

he alone could, and did, cause

an effect on core reactivity.

01.4 Effectiveness of Licensee Controls and Evaluations

71707

a.

Ins ection Sco

e

The inspectors reviewed the licensee incident review board investigations, followup

problem evaluation requests,

and conducted discussions with key personnel

involved in the events and in the investigation of the events.

Observations

and Findin s

The inspectors noted that the licensee's incident review board findings did not

include a number of the discrepancies

identified by the inspectors.

For example:

(1) the erroneous control room operator log entry related to the initial criticality

count rate (5000 cps versus 70,000 cps); and (2) the fact that one of the source

range monitor recorders had the incorrect strip chart paper installed.

Additionally, the incident review boards did not identify some root causes which the

inspectors believed were very relevant.

For example, the estimated critical position

incident review board focused on the reactor engineering aspects

and did not

address operations command and control during the events and what barriers were

breached or circumvented.

The adjustable speed drive incident review board

investigation focused solely upon the contract engineer's

actions and did not

address what barriers in the procedural review process were circumvented.

For

example, why did the operations review process

and work control process not

function properly and preclude

a nonlicensed individual from even being in a position

in which he could affect the manipulation of reactivity?

-10-

c.

Conclusions

The inspectors concluded that the licensee's investigations were too narrowly

focused and did not identify all facts involved in the events.

05 Operator Training and Qualification (41500)

a.

Ins ection Sco

e

The inspectors reviewed licensed operator training related to the approach to

criticality. The review included both the initial licensed operator certification

program and the licensed operator requalification program, as well as interviews

with key training department personnel.

b.

Observations

and Findin

s

The inspectors noted that the initial licensed operator certification training included

the appropriate knowledge and abilities competencies

and these were linked to

simulator and classroom training sessions.

The licensed operator requalification

program was procedurally linked to lesson plans and learning objectives.

In the

requalification training, the training associated

with reactivity focused upon lessons

learned from industry events and simulator sessions

related to startup of the plant.

In the simulator requalification training, operators discussed

plant indications during

the approach to criticality and then continued with plant heatup operations.

As

such, not all reactor operators had the opportunity to pull control rods to criticality.

However, all operators were involved in training discussions.

Conclusions

The inspectors concluded that the operators had the prerequisite knowledge and

abilities related to approach-to-criticality operations.

However, the inspectors also

concluded that because

of decreased

opportunities for plant startups and because

of a greater number of licensed operators

in the program, the experience level of

operators may not have been as high as it had been in the past.

III. En ineerin

E1

Conduct of Engineering

E1.1

General Comments

37551

Using Inspection Procedure 37551, the inspectors reviewed the involvement of

station nuclear engineers

in the early criticality and the Reactor Recirculation Control

Pump-1A speed transient during adjustable speed drive testing.

In the former event,

concerns of the station nuclear engineers regarding the results of calculations of the

estimated critical rod position and the deviation from the estimated criticality band

-11-

were not elevated to the appropriate management

levels.

In the latter event,

a

nonlicensed person,

a contractor engineer, inadvertently caused

a reactivity

transient by erroneously imputing data into the adjustable speed drive system.

The

inspectors summarized other observations

related to these events in Sections 01.2

and 01.3 of this report.

E1.2 Criticalit

Achieved Prior to Minimum Estimated Critical Position

a.

Ins ection Sco

e

On Thursday, June 27, 1996, reactor criticality was achieved prior to the minimum

expected point of criticality calculated by the station nuclear engineer.

The

inspectors reviewed control room logs, facility procedures,

data logs, and conducted

interviews with key licensee personnel.

b.

Observations

and Findin s

The estimated critical position calculated for the June 27, 1996, reactor criticality

was performed utilizing the incorrect software flag for the plant condition.

The

PowerPlex software required that a specific set of conditions be input to solve for

the desired parameters.

The software accomplished this with a series of flags that

were set by the user.

The flag setting that caused the estimated critical position

calculation to be incorrect was for Xenon dependence.

Normally the flag default

is -1, which covers most cases for online use.

For the case of a plant that had been

shutdown for a short period of time, where the Xenon concentration had not

decayed fully the flag should have been set to 0.

Discussions with the software custodian, who also conducted the station nuclear

engineers training on the PowerPlex software, indicated to the inspectors that he

had questioned the vendor about the use of the -1 option.

However, the use of the

option for the case of a post-trip return to criticality was not a topic discussed

and

the custodian was left with the impression that the default value of -1 would be

used in almost all possible situations.

Therefore, when the estimated critical

position calculation was done the option of 0 was not selected.

When subsequent

calculations were conducted, the other station nuclear engineers performed the

calculation in the same method.

On June 12, 1996, the first estimated critical position following the refueling outage

was performed.

This estimated critical position was done using charts provided by

the fuel vendor, and no anomalies were found.

The estimated critical position was

validated using the PowerPlex software, which agreed with the manual calculation.

The wrong Xenon dependence

flag was set for this calculation, however, the

software automatically depletes Xenon for the first run after a refueling.

As a

result, the station nuclear engineers

did not receive prior indication of the error in

use of the software.

-1 2-

The reactor scrammed on June 24, 1996, at around 0800 hours0.00926 days <br />0.222 hours <br />0.00132 weeks <br />3.044e-4 months <br />.

On the following

day, June 25, 1996, an initial estimated critical position was calculated estimating

0000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> that night.

The station nuclear engineer recalculated

an estimated

critical position that night for a 0600 critical time on June 26, 1996.

The station

nuclear engineer that performed the calculation noted that the result was the same

as the previous calculation, which was unexpected.

The station nuclear engineer

was concerned about the calculation and expressed

his concerns to the oncoming

station nuclear engineer for the day shift. Additional runs of the software were

done, which resulted in the same results.

A manual calculation was done which

came up with a different result, that later turned out to be more accurate.

The

manual calculation, however, was discounted because

it did not include factors that

the PowerPlex software included, particularly the fact that. one rod was inoperable

and would stay in the core.

Runs on the software of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> after the trip and 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> gave the same results.

The station nuclear engineers

ascribed that the reason for this conclusion was that

the Xenon had decayed out of the core by 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> after the scram.

This was not

the case,

as subsequent

analysis showed that the amount of Xenon would have

been nearly equal to equilibrium at the time of the scram, and the 36-hour figure

was around half of the equilibrium value.

The engineers continued to analyze the

differences, requesting assistance

from the fuels engineering group to do other

calculations.

The differences between the calculations of the two groups amounted

to about 6 mK, but was discounted.

The difference between the June 12, 1996,

estimated critical position and the last estimated critical position that was calculated

was 16 mK. The engineers became convinced that Samarium poisoning accounted

for the difference.

This would explain some changes

in the expected estimated

critical position, however, not to the magnitude that occurred.

On June 27, 1996, the station nuclear engineer gave the estimated critical position

to the shift manager.

The shift manager questioned the difference between the

estimated critical position of June 12 and the new estimated critical position.

The

station nuclear engineer convinced the shift manager that sufficient independent

work was done to justify the estimated critical position.

The onshift control room

supervisor was not informed of this disparity.

The rest of the event process

is

described in Section 01.2 of this report.

The inspectors reviewed Procedure

PPM 1.3.59, "Reactivity Management Program,"

Revision,1, and noted that step 2.6.3a of the procedure stated that, "An estimated

ECP calculation should be performed by the SNE... and an acceptable

band of

delta K/K for criticality should be applied."

Procedure

PPVI 3.1.2, "Reactor

Startup," Revision 31, step 4.2.3 further required that the station nuclear engineer,

"...verify criticality occurs between the Minimum Allowable ECP Limit and the

Maximum Allowable ECP Limit." However, no approved plant procedure existed on

June 27, 1996, to perform a calculation for an estimated critical position and

applied tolerance band, nor were instructions provided within Procedure

PPM 3.1.2,

"Reactor Startup."

The inspectors noted that a draft procedure had existed for

-13-

some time but did not include sufficient instructions to preclude the miscalculation

of the estimated criticality point.

As a result, on June 27, 1996, the reactor was

taken critical approximately 4 mK earlier than the minimum allowable estimated

critical point limit. The lack of specified procedural guidance was considered

an

apparent violation of Technical Specification 6.8.1a (50-397/9616-04).

c.

Conclusions

The inspectors noted the apparent reluctance of the station nuclear engineers to

bring forward to management

their initial concerns related to the accuracy of the

estimated critical position calculation.

Further, their assurance

that sufficient

independent verification was done led the shift manager to believe the estimated

critical position was correct.

The continuing effort to verify the adequacy of the

estimated critical position calculations were thwarted by inadequate training in the

use of the PowerPlex software.

Therefore, combined with a lack of

proceduralization for estimated critical position calculations, the station nuclear

engineers efforts merely continued to reinforce the error in usage of the software.

E5

En ineer Trainin

and Qualification 41500

a.

Ins ection Sco

e

The inspectors reviewed station nuclear engineer training related to the approach to

criticality and the use of the PowerPlex software to calculate the estimated critical

position.

The review included initial training and subsequent

refresher training, as

well as interviews with the PowerPlex software custodian responsible for providing

the training on the use of the software.

Observations

and Findin

s

The inspectors noted that, for the initial training, the station nuclear engineers were

presented with all the functional attributes of the PowerPlex program.

The review

of the training indicated that the original training was sufficient and addressed

the

necessary

knowledge and ability factors.

However, subsequent

training on the

software did not include sufficient detail to ensure that changes

made to the

software by the vendor were addressed.

The vendor had recently provided new

software with changes to the flag settings related to time dependent

Xenon

concentration.

The effect of the setting of the flag for the case of a cold

time-dependent

post-trip calculation for a critical rod position was not discussed

during training of the station nuclear engineers.

As a result, when the calculation

for the reactor startup of June 27, 1996, was performed, the error in selecting the

flag was repeated consistently.

This resulted in each confirmatory calculation being

performed with the same conditions set in the program.

-1 4-

c.

Conclusions

The inspectors concluded that the station nuclear engineers training on the use of

the PowerPlex software was flawed such that the personnel consistently performed

the estimated critical position calculations incorrectly.

V. Mana ement Meetin s

X1

Exit Meeting Summary

The inspectors presented

the inspection results to members of licensee management

at the

conclusion of the inspection on August 8, 1996.

The licensee acknowledged the findings

presented.

The inspectors asked the licensee whether any materials examined during the inspection

should be considered propriety.

No proprietary information was identified.

ATTACHMENT

PARTIAL LIST OF PERSONS CONTACTED

Licensee

P. Bemis, Vice President for Nuclear Operations

L. Fernandez,

Licensing Manager

G. Smith, Plant General Manager

A. Langdon, Acting Operations Manager

J. Swailes, Engineering Director

D. Swank, Regulatory and Industrial Affairs Manager

R. Webring, Vice President Operations Support

M. Monopoli, Maintenance Manager

NRC

G. Tracy, Acting Deputy Director, Division of Reactor Safety

LIST OF INSPECTION PROCEDURES USED

IP 37551:

Onsite Engineering

IP 41500:

Training and Qualification

IP 71707:

Plant Operations

LIST OF ITEMS OPENED

~Oened

50-397/961 6-01

VI0

50-397/961 6-02

VIO

50-397/961 6-03

50-397/961 6-04

VIO

VIO

50-397/961 6-05

VIO

Failure to adhere to procedures

related to control room

operator log entries

Failure to adhere to procedures

related to retention of

permanent plant records

Failure to adhere to procedures

related to reactor startup

Failure to have a procedure for calculation of an estimated

critical position

Failure to have procedure appropriate to circumstances

resulting in a nonlicensed person operating the controls of the

reactor

LIST OF LICENSEE PROCEDURES AND DOCUMENTS

REVIEWED DURING THIS INSPECTION

PPM 3.1.2, Revision 31, "Reactor Startup"

PPM 3.1.10, Revision 11, "Operating Data Logs"

-2-

PPM 1.3.59, Revision 1, "Reactivity Management"

PPM 8.3.339, Revision 1, "Test Instructions - Reactor Recirculation Adjustable Speed Drive

and Reactor Digital Feedwater Control Power Ascension Test Program"

PPM 1.3.1 Revision

26, "Conduct of Operations"

Incident Review Board Report for PER 296-0576, "RRC-PUMP-1A Speed transient during

ASD testing," dated July 25, 1996

Incident Review Board Report for PER 296-0522, "CriticalityAchieved Prior to Minimum

Estimated Critical Position (ECP)," dated July 2, 1996

Interoffice Memorandum, Subject:

Estimated Critical Position (ECP) for BOC-12, dated

June 26, 1996

ENCLOSURE 3

Enforcement Policy: Section V,

"Predecisional Enforcement Conferences"

Erd'orccmcn( Policy S~~~g

Y.

PREOECISIOHAL

EHFORCEHEHT CONFERENCES

Whenever the

NRC has learned of the existence of a potential violation for

which

escalated

enforcement

action

appears

to

be

warranted,

or

recurring

nonconformance

on the part of a vendor,

the

HRC may provide

an opportunity for

a predecisional

enforcement conference with the licensee,

vendor, or other person

before taking enforcement

action.

The purpose of the conference

is to obtain

information that will assist

the

HRC in determining the appropriate

enforcement

action,

such

as:

(I)

a

common

understanding

of facts,

root causes

and missed

opportunities associated with the apparent violations, (2)

a common understanding

of corrective

action

taken or planned,

and

(3)

a

common understanding

of the

significance of issues

and the need for lasting comprehensive

corrective action.

If the

HRC concludes that it has sufficient information to make

an informed

enforcement decision,

a conference will not normally be held unless

the licensee

requests it.

However,

an opportunity for a conference will normally be provided

before issuing

an order based

on a violation of the rule on Deliberate Hisconduct

or

a civil penalty to

an unlicensed

person.

If a conference

is not held,

the

licensee

will normally

be

requested

to

provide

a written

response

to

an

inspection

report, if issued,

as

to

the

licensee's

views

on

the

apparent

violations

and their root causes

and

a description of planned

or

implemented

corrective action.

During the predecisional

enforcement

conference,

the licensee,

vendor, or

other persons will be given an opportunity to provide information consistent with

the

purpose

of the

conference,

including

an

explanation

to

the

HRC of the

immediate corrective actions (if any) that were taken following identification

of the potential

violation or nonconformance

and the long-term comprehensive

actions

that

were

taken

or will be

taken

to prevent

recurrence.

Licensees,

vendors,

or other

persons

will be told

when

a

meeting

is

a

predecisional

enforcement

conferences

A predecisiona1

enforcement conference is a meeting between the

NRC and the

licensee.

Conferences

are normally held in the regional offices

and are not

normally open to public observation.

However,

a trial program is being conducted

to

open

approximately

25

percent

of all eligible

conferences

for public

observation,

i.e.,

every

fourth eligible

conference

involving one of three

categories

of licensees

(reactor, hospital,

and other materials licensees) will

be open to the public.

Conferences will not normally be open to the public if

the enforcement

action being contemplated:

(I) Would

be

taken

against

an individual, or if the action,

though not

taken

against

an

individual,

turns

on

whether

an

individual

has

committed

wrongdoing;

i;oforccmcnt I'olicy SLttcmcnt

(2)

Involves significant personnel

failures

where

the

HRC has

requested

that the individual(s)

involved be present

at the conference;

(3) Is based

on the findings of an

HRC Office of Investigations

report;

or

(4)

Involves

safeguards

information,

Privacy

Act

information,

or

information which could be considered

proprietary;

In addition,

conferences will not normally be open to the public if:

(5) The conference involves medical misadministrations or overexposures

and

the conference

cannot

be conducted without disclosing the exposed individual's

name;

or

(6) The conference will be conducted

by telephone

or the conference will

be conducted

at

a relatively small licensee's facility.

Notwithstanding meeting

any of these criteria,

a conference

may still be

open if the

conference

involves

issues

related

to

an

ongoing

adjudicatory

proceeding with one or more intervenors

or where the evidentiary basis for the

conference

is

a matter of public record,

such

as

an adjudicatory decision by the

Department of Labor.

In addition, with the approval of the Executive Director

for Operations,

conferences will not be open to the public where good cause

has

been

shown after balancing

the benefit of the public observation

against

the

potential

impact

on the agency's

enforcement

action in

a particular case.

As

soon

as it is determined

that

a conference

will be

open

to public

observation,

the

NRC will notify the licensee that the conference will be open

to public observation

as part of the agency's trial program.

Consistent with the

agency's

policy on

open

meetings,

"Staff Meetings

Open

to Public," published

September

20,

1994

(59 FR 48340),

the

NRC intends

to announce

open conferences

normally at least

10 working days in advance of conferences

through (I) notices

posted

in the Public Document

Room,

(2)

a toll-free telephone

recording at 800-

952-9674,

and

(3)

a toll-free electronic bulletin board

at 800-952-9676.

In

addition,

the

NRC will also

issue

a press

release

and notify appropriate

State

liaison officers that

a predecisional

enforcement

conference

has

been scheduled

and that it is open to public observation.

The public attending

open conferences

under the trial program may observe

but

not participate

in

the

conference.

It is

noted

that

the

purpose

of

conducting

open

conferences

under the trial program is not to maximize public

attendance,

but

rather

to

determine

whether

providing

the

public

with

opportunities

to

be

informed of

HRC activities is compatible with the

NRC's

ability to exercise

its regulatory

and safety responsibilities.

Therefore,

members

of the public will be

allowed

access

to the

NRC regional

offices to

attend

open enforcement

conferences

in accordance

with the "Standard

Operating

Procedures

For

Providing

Security

Support

For

NRC

Hearings

And Meetings,"

published

Hovember

1,

1991

(56 FR 56251).

These procedures

provide that visitot s

may

be subject

to personnel

screening,

that signs,

banners,

posters,

etc.,

not

larger than

18"

be permitted,

and that disruptive persons

may be removed.

md%/BR41 95

Enforcement Policy Statcmcnt

Members of the public attending

open conferences will be reminded that (I)

the apparent

violations discussed

at predecisional

enforcement

conferences

are

subject

to further review and

may

be subject to change prior to any resulting

enforcement action and {2) the statements

of views or expressions

of opinion made

by HRC employees

at predecisional

enforcement

conferences,

or the lack thereof,

are not intended to represent final determinations or beliefs.

Persons attending

open

conferences

will be provided

an opportunity to

submit written

comments

concerning

the trial program anonymously to the regional office.

These

comments

will be subsequently

forwarded to the Director of the Office of Enforcement for

review and consideration.

When needed

to protect the public health

and safety or common defense

and

security,

escalated

enforcement action,

such

as the issuance

of an immediately

effective

order,

will

be

taken

before

the

conference..

In

these

cases,

a

conference

may be held after the escalated

enforcement

action is taken.

NJREG/BR%195

EP-13