Forwards Insp Rept 50-397/95-31 on 951015-1125 & Notice of Violation.Violation of Concern Due to Indication of Continuing Weakness in Radiation Protection Practices at WNP-2
ML17291B179
Person / Time
Site: Columbia 
Issue date: 12/26/1995
From: Dyer J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Parrish J
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
Shared Package
ML17291B180 List:
References
NUDOCS 9512290331
Download: ML17291B179 (11)


See also: IR 05000397/1995031

Text

CATEGORY 2

REGUL'ATOINFORMATION

DISTRIBUTION 'TEM

(RIDE)

ACCESSIOM NBR:9512290331

DOC.DATE: 95/12/26

NOTARIZED: NO

DOCKET I

FACIL:50-397 WPPSS Nuclear Project, Unit 2, Washington Public

Powe

05000397

UTH.NAME

AUTHOR AFFILIATION

ER,J.E.

Region

4 (Post

820201)

RECIP.NAME

RECIPIENT AFFILIATION

PARRISH,J.V.

Washington Public Power Supply System

SUBJECT:

Forwards insp rept 50-397/95-31

on 951015-1125

& notice of

violation.Violation of NRC concern

due because it indicates

~

continuing weakness

in radiation protection practices

at

WNP-2.

DISTRIBUTION CODE:

IEOZD

COPIES

RECEIVED:LTR Q ENCL I

SIZE: 5 +

TITLE: General

(50 Dkt)-Insp Rept/Notice of Violation Response

NOTES:

RECIPIENT

ID CODE/NAME

PD4-2

PD

INTERNAL: ACRS

AEOD/SPD/RAB

DEDRO

NRR/DISP/PIPB

NRR/DRPM/PECB

NUDOCS-ABSTRACT

OGC/HDS3

RNAL: LITCO BRYCE,J

H

NRC PDR

COPIES

LTTR ENCL

1

1

2

2

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

RECIPIENT

ID CODE/NAME

CLIFFORD,J

AEOD/DEIB

AEOD

P'NTER

ARRI'URGE'f

B

NRR/DRPM/PERB

OE DIR

RGN4

FILE

01

NOAC

COPIES

LTTR ENCL

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

NOTE TO ALL "RIDS" RECIPIENTS:

PLEASE HELP US

TO REDUCE WASTE)

CONTACT THE DOCUMENT CONTROL DESK,

ROOM OWFN 5D-5(EXT. 415-2083)

TO ELIMINATE YOUR NAME FROM

DISTRIBUTION LISTS FOR

DOCUMENTS YOU DON'T NEEDl

TOTAL NUMBER OF COPIES

REQUIRED:

LTTR

20

ENCL

20

UNIT E O STAT ES

C LEAR R EG ULATORY COMMISSI

, REGION IV

611 RYAN PLAZA DRIVE, SUITE 400

ARLINGTON. TEXAS 76011 8064

ore 26 895

Washington Public Power Supply System

ATTN:

J.

V. Parrish,

Vice President

Nuclear Operations

3000 George

Washington

Way

P.O.

Box 968,

MD 1023

Richland,

Washington

99352

SUBJECT:

NRC

INSPECTION

REPORT 50-397/95-31

AND NOTICE OF VIOLATION

This refers to the inspection

conducted

by Messrs.

R.

C. Barr,

G.

W. Johnston,

and

Ms. J.

L. Dixon-Herrity of this office on October

15 through

November

25,

1995, at the Washington Nuclear Project-2 facility.

The purpose of the

inspection

was to determine

whether activities authorized

by the license

were

conducted

safely

and in accordance

with NRC requirements.

At the conclusion

of the inspection,

the findings were discussed

with you and those

members of

your staff identified in the enclosed

report.

Areas

examined during the inspection

are identified in the report.

Within

these

areas,

the inspection consisted

of selective

examinations

of procedures

and representative

records,

interviews with personnel,

and observation of

activities in progress.

Based

on the results of this inspection,

the

NRC has determined that one

violation of NRC requirements

occurred.

The violation is cited in the

enclosed

Notice of Violation (Notice)

and the circumstances

surrounding it are

described

in detail

in the subject inspection report.

The violation is of

concern

because it indicates

continuing weakness

in radiation protection

practices

at WNP-2.

You are required to respond to this letter

and should follow the instructions

specified

in the enclosed

Notice when preparing your response.

In your

response,

you should

document

the specific actions

taken

and

any additional

actions

you plan to prevent recurrence.

Your response

may reference

or

include previous docketed

correspondence, if the correspondence

adequately

addresses

the required response.

After reviewing your response

to this

Notice, including your proposed corrective actions

and the results of future

inspections,

the

NRC will determine

whether further .NRC enforcement

action is

necessary

to ensure

compliance with NRC regulatory requirements.

In accordance

with 10 CFR 2.790 of the

NRC's "Rules of Practice,"

a copy of

this letter, its enclosure(s),

and your response will be placed

in the

NRC

Public Document

Room

(PDR).

To the extent possible,

your response

should not

include

any personal

privacy, proprietary,

or safeguards

information so that

it can

be placed in the

PDR without redaction.

ciI5i229033i 95i226

PDR

ADOCK 0500039'7

8

PDR

Washington Public

Power Supply

System

The responses

directed

by this letter

and the enclosed

Notice are not subject

to the clearance

procedures

of the Office of Management

and Budget

as required

by the Paperwork Reduction Act of 1980,

Pub.

L. No. 96.511.

Should you have

any questions

concerning this inspection,

we will be pleased

to discuss

them with you.

Sincerely,

Docket:

50-397

License:

NPF-21

Enclosures:

1.

Notice of Violation

2.

NRC Inspection

Report

50-397/95-31

J.

E. Dyer, Director

Division of Reactor Projects

cc w/enclosures:

Washington Public Power Supply System

ATTN:

J.

H. Swailes,

WNP-2 Plant Manager

P.O.

Box 968,

MD 927M

Richland,

Washington

99352-0968

Washington Public Power Supply System

ATTN:

Chief Counsel

3000 George

Washington

Way

P.O.

Box 968,

MD 396

Richland,

Washington

99352-0968

Energy Facility Site Evaluation Council

ATTN:

Frederick

S. Adair, Chairman

P.O.

Box 43172

Olympia, Washington

98504-3172

Washington Public Power Supply System

ATTN:

D. A. Swank,

WNP-2 Licensing Manager

P.O.

Box 968 (Mail Drop PE20)

Richland,

Washington

99352-0968

Washington Public

Power Supply

System

Washington Public

Power Supply System

ATTN:

P.

R.

Bemis, Direct'or

Regulatory

and Industry Affairs

P.O.

Box 968 (Mail Drop PE20)

Richland,

Washington

99352-0968

Benton County Board of Commissioners

ATTN:

Chairman

P.O.

Box 190

Prosser,

Washington

99350-0190

Winston

8 Strawn

ATTN:

M. H. Philips,

Esq.

1400

L Street,

N.W.

Washington,

D.C.

20005-3502

Washington Public Power Supply

System

DEC 26 $95

E-Mail report to D. Nelson

(DJN)

E-Mail report to

NRR Event Tracking System

(IPAS)

" bcc to

DMB (IE01) i

bcc distrib.

by RIV:

L. J. Callan

DRS-PSB

Branch Chief (DRP/E,

WCFO)

Senior Project

Inspector

(DRP/E,

WCFO)

Leah Tremper

(OC/LFDCB,

MS:

TWFN 9E10)

Resident

Inspector

MIS System

RIV File

Branch Chief (DRP/TSS)

M.

Hammond

(PAO,

WCFO)

DOCUMENT NAME:

To receive copy of document, indicete in boxt "C

e Copy without enclosures

"E

~ Copy with enclosures "N" = No copy

RI V:SRI: DRP/E

RCBarr

12// 5795

C:DRP/E

HJWong

12&) /95

D:DRP

JEDyer

12/Q /95

0

C A

CO

Co

12/

/95

12/

/95

Washington Public Power Supply

System

DEC 2B $95

E-Mail report to D. Nelson

(DJN)

E-Mail report to

NRR Event Tracking System

( IPAS)

bcc to

DMB (IE01)

bcc distrib.

by RIV:

L. J. Callan

DRS-PSB

Branch Chief (DRP/E,

WCFO)

Senior Project Inspector"(DRP/E,

WCFO)

Leah Tremper

(OC/LFDCB,

MS:

TWFN 9E10)

Resident

Inspector

MIS System

RIV Fi1 e

Branch Chief (DRP/TSS)

M.

Hammond

(PAO,

WCFO)

DOCUMENT NAME:

To receive copy of document, indicate in box: "C" ~ Copy without enclosures

"E" ~ Copy with enclosures "N" ~ No copy

RIV:SRI: DRP/E

RCBarr

12//095

C:DRP/E

HJWong 0

12P5"/95

D:DRP

JEDyer

12/gCp/95

CO

0

12/

/95

12/

/95