ML17291B113

From kanterella
Jump to navigation Jump to search
Insp Rept 50-397/95-30 on 950925-28.Violations Noted.Major Areas Inspected:Radiation Protection Program Response to Events Re High High & Very High Radiation Area Doors
ML17291B113
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 11/14/1995
From: Murray B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML17291B111 List:
References
50-397-95-30, NUDOCS 9511210026
Download: ML17291B113 (24)


See also: IR 05000397/1995030

Text

ENCLOSURE 2

U.S.

NUCLEAR REGULATORY COMMISSION

REGION

'

V

Inspection Report:

50-397/95-30

License:

NPF-21

Licensee:

Washington Publ'ic Power Supply System

3000 George Washington

Way

P.O.

Box 968.

MD 1023

Richland,

Washington

Facility Name:

Washington

Nuclear

Project-2

Inspection At:

Richland,

Washington

Inspection

Conducted:

September

25-28 '995

Inspectors:

L. T. Ricketson,

P.E..

Senior

Radiation Specialist

Plant Support Branch

M.

P.

Shannon,

Radiation Specialist.

Plant Support Branch

Approved:

urray,

>e

,

ant

upper

rane

//-/4r f5

a e

Ins ection

Summar

AAI

A t d.'

ti

.

d i

p ti

f th

di ti

p t ti

program's

response

to events related to high high (greater

than

1000 mrem/hr)

and very high (greater

than 500 Rads/hr) radiation area doors,

including:

initial determination of event significance,

event investigation,

root cause

analysis,

resolution of problem evaluation

requests

(PER),

comprehensiveness

of corrective actions.

communications,

verification, procedural

adequacy,

and

potential for significant exposure.

Results:

Plant

Su

orb

~

The dispositioning

manager for PER 295-0492

was not sensitive to the

significance of the event.

This affected the comprehensiveness

and the

timeliness of the implementation of corrective actions.

Improvements in

the

PER process

have

been

made since the occurrence of the events

(Section 2.1).

95ii2i002h 951.ii4

PDR

ADOCK 05000397

8

PDR

-2-

~

The licensee's

investigation of events

described in PER 295-0492

and

PER 295-0955 were not thorough.

The events

were not viewed as

significant; therefore,

less eff'ort was devoted to determining the

causes.

Had more detailed investigations

been performed,

an adverse

trend involving personnel

performance

and

a poor verification program

may have been identified.

The investigation of PER 295-0927

was more

thorough.

However, the investigation determined only what happened

during the event.

not what caused

the event (Section 2.2).

~

The radiation protection manager did not follow the guidance in

Procedure

PPH 1.3. 12A, Revision 2, concerning the root-cause

analysis

and, therefore,

did not meet

management

expectations.

The licensee

missed

an opportunity to identify an adverse

trend and

a problem with

the verification program (Section 2.3).

Radiation protection personnel

did not meet management

expectations

for

resolving problem evaluation

requests

in a timely manner

(Section 2.4).

A violation of Technical Specification

6. 12.2 was identified involving

=

the failure to lock

a door controlling access

to an area with radiation

levels greater

than

1000 mRem/hr (Section 2.5).

Communication of information regarding the first event

was poor and

may

have contributed to the second

event (Section 2.6).

~

A Non-Cited Violation was identified involving the failure to follow a

procedure.

Radiation protection personnel

missed

two earlier

opportunities to identify the procedural

violation.

The oversight

program for high high and very high radiation areas

continued to be

weak, in part because,

management's

expectations

with regard to high

high and very high radiation area surveillances

did not include the

rigorous

and consistent

use of the guidance provided to ensure that

technical specification requi rements

were met (Section 2.7).

~

The procedure for the control of access

to high high and very high

radiation areas

did not address all regulatory requi rements

(Section 2.8).

~

The potential for personnel

radiation

exposure in excess of regulatory

limits occur ring as

a result of the events

was low (Section 2.9).

Summar

of Ins ection Findin s:

Violation 397/9530-01

was opened

(Section 2.5).

A Non-Cited Violation was identified (Section 2.7).

-3-

Attachments:

~

Attachment

1

- Persons

Contacted

and Exit Meeting

~

Attachment

2 - Chronology of Events

1

BACKGROUND

-4

DETAILS

From May 7 to August 17,

1995, three potential violations occurred involving

doors to areas controlled in accordance

to Technical Specification 6. 12.2.

A

special

NRC inspection

was performed to evaluate the potential for unplanned

personnel

radiation exposure

associated

with each event

and to review the

corrective actions taken by the licensee for each of the following three

events.

1.1

Event

1

On May 7,

1995,

a door (C-115) to a high high radiation area

on the 437-foot

elevation of the radwaste building was discovered

by licensee

personnel

to be

. unlocked.

Radiation 'levels within the area

were greater than

1000 milli rems

per hour.

Technical Specification

6. 12.2 requires

such areas to be locked to

control inadvertent

personnel

entry.

A planned entry into the area

was

conducted

ear lier in the day by a mechanical

maintenance

worker under the

observation of a radiation protection technician.

The door was normally

controlled by a padlock

and

a chain.

The chain was usually passed

through the

hand wheel in a manner that prevented

the wheel

from being turned, thus,

locking the door.

On this day, the padlock

was locked;

however,

the chain

was

not routed

so that it restricted the movement of the wheel,

and the door could

have

been

opened.

A radiation protection supervisor

discovered

the unlocked

door and licensee

personnel

initiated

PER 95-0492 to document the problem and

track corrective actions.

1.2

Event 2

On August 9

~

1995.

licensee

personnel

discovered

the

same door (C115)

on the

437-foot elevation of the radwaste building was not locked.

This time the

chain

and the lock were on the floor nearby.

An entry into the

room was

completed the previous afternoon

by an equipment operator

under the

observation of a radiation protection technician.

The licensee initiated

PER 295-0927 to document the event.

1.3

Event

3

On August 16.

1995, the licensee identif'ied that the door to the traversing

incore probe

room,

an area that was posted

and controlled as

a very high

radiation area.

had only one lock i nstead of the two locks required

by

Procedure

PPM 11.2.7.3.

PER 295-0955

was initiated to document the event.

2

NRC REVIEW

The

NRC inspectors

reviewed the problem evaluation

requests

associated

with

the events.

investigation reports,

proposed corrective actions,

correspondence

by the quality assurance

organization related to the corrective actions,

applicable

implementing procedures,

radiation protection log book entries,

key

-5-

control log entries,

survey information, training materials,

and applicable

night orders

from radiation protection

management.

In addition to per forming

document reviews, the inspectors

conducted interviews and performed

independent

radiation surveys.

2. 1

Initial Determination of Event Si nificance

When the events occurred,

the licensee's

corrective action program was

implemented using the following procedures:

~

PPM 1.3. 12.

"Problem Evaluation Request

(PER)," Revision

20

~

PPM 1.3. 12A, "Processing

Problem Evaluation Requests,"

Revision

2

Both procedures

were revised again

on September

18,

1995 'fter the events

occurred.

.At the time of the events. it was the dispositioning manager's

(in this case

the radiation protection manager'). responsibility to determine the

significance of. the events.

Section 6.3 of Procedure

PPM 1.3. 12A stated that

the dispositioning

manager

is to "Review the

PER to verify whether or not a

Root Cause Analysis is required.

Attachment 8.8 should

be used for guidance."

Attachment 8.8

~

"Root Cause Analysis Screening

Guide," included guidance in

the areas of reactor operations

(Section

1. 1). health physics

(Section 1.2).

radwaste transportation

(Section 1.3),

and miscellaneous

matters

(Section 1.4).

Event

1

Even though the event described

in PER 295-0492

was identified as being

contrary to the requirements

of Technical Specification

6. 12.2 and might have

presented

the potential for significant personnel

radiation exposure, it was

not determined

by the licensee to war rant

a root-cause

anal'ysis.

Because it

was not considered significant, the search for all possible

causes

was not

rigorous

and the timely implementation of corrective actions

was not

emphasized.

See Section 2.5 for

a discussion of the corrective actions.

Event

2

PER 295-0927

was considered significant because

the event represented

a

significant adverse

trend or failure affecting

a quality program or plant

safety,

according to the note in Block 19 of the problem evaluation request

form.

Event 3

PER 295-0955

was not considered

by the licensee to be significant.

The event

was seen merely

as

a procedural violation.

A root-cause

analysis

was not

determined to be necessary.

No adverse

trend in the verification program.

as

discussed

in Section 2.7

~ was identified.

-6-

Event

3

PER 295-0955

was not considered

by the licensee to be significant.

The event

was seen merely as

a procedural violation.

A root-cause

analysis

was not

determined to be necessary.

No adverse trend in the verification program,

as

discussed

in Section 2.7,

was identified.

The inspectors

noted that major changes

were made in the way problem

evaluation

requests

were dispositioned with the issuance of Revision

3 of

Procedure

PPM 1.3. 12A on September

18.

1995.

Some of the changes

included:

The introduction of the concept of a "Significant PER," [Section 4. 19j; the

determination of the significance of problem evaluation

requests

during

morning meetings of site management

[Section 6.2j; and the requirement that

all significant problem evaluation

requests

have

a formal root-cause

analysis

performed [Section 6.4.6j.

An attachment entitled, "Significant PER Screening

Guide." replaced the "Root Cause Analysis Screening

Guide."

The new screening

guide in'eluded

as significant

"Any operation or condition prohibited by the

plant's Technical Specifications."

Such guidance, if followed, would have

served to raise the level of attention received

by PER 295-0492;

however, the

events'hich

are the subject of this inspection,

occurred before the

implementation of Revision

3 of the Procedure

PPM 1.3. 12A.

Conclusion

The

PER dispositioning

manager

was not sensitive to the significance of the

first event.

This affected the comprehensiveness

and the timeliness of'he

implementation of corrective actions.

Improvements in the

PER process

have

been

made since the occurrence of the events.

2.2

Event Investi ation

The inspectors

interviewed licensee

personnel

and performed record reviews

and

determined the following concerning the licensee's

investigation process:

Event

1

According to the mechanical

maintenance

worker involved in the event described

in PER 295-0492.

licensee

representatives

never interviewed him regarding

details of the event.

The radiation protection supervisor

who validated

PER 295-0492 confi rmed this.

The radiation protection technician involved in

the event stated that

he was interviewed

a few days after the event.

Event

2

The event described

in PER 295-0927

was recognized

by the licensee

as being

significant and

an incident review board was established

on August

9

~ 1995, to

review the ci rcumstances

surrounding the event.

The incident review board

interviewed the individuals involved and reviewed records related to the

event.

According to the incident review board report dated August 16,

1995.

the incident review board concluded that the root cause of the incident was

,Ql

-7-

unknown.

Also according to the report.

".

.

. it was decided to deviate

from

the normal

IRB process

and,

instead,

have

an independent

investigator

investigate the incident in hopes of resolving what occurred."

The

independent

investigator interviewed personnel

with known or potential

knowledge of the event

and concluded that the individuals involved "failed to

lock the door."

Event

3

Although it was identified on August 17,

1995, that the traversing incore

probe

room door did not have two locks. the licensee did not determine. until

prompted

by the inspectors,

that. the second

lock was

removed

from the door on

-August 1,

1995.

Records

were available to confirm that one lock was re-cored

on that date

and the other lock removed;

h'owever,

the licensee

had not taken

action to determine the length of time the violation existed.

The

investigation also did not identify that radiation protection personnel

performing weekly verifications of high high radiation area

and very high

radiation area controls

(as discussed

in Section 2.7) failed to identify the

violation on August

7 and

14 '995.

Conclusion

The licensee's

investigation of events

described

in PER 295-0492

and

PER 295-

0955 were not thorough.

The events

were not viewed's significant; therefore,

less effort was devoted to determining the causes.

Had more detailed

investigations

been performed,

an adverse trend involving personnel

performance

and

a poor verification program

may have

been identified.

The

investigation of PER 295-0927

was more thorough.

However, the investigation

determined only what happened

during the event.

not what caused

the event.

2.3

Root-Cause

Anal sis

Procedure

PPM 1.3.48,

"Root Cause

Analysis'

" Revision 5, Section 1.0 states,

"Root cause analysis is required

when there is

a 'Significant Condition

Adverse To'uality.'s described

in 10 CFR 50, Appendix B, Criterion XVI."

Procedure

PPM 1.3. 12A, Section 6.3,

requi res the dispositioning

manager

to

"Review the

PER to verify whether

or not

a Root Cause Analysis is required.

Attachment 8.8 should

be used for guidance."

Attachment 8.8, Section 1.2

includes guidance that

a root cause analysis is to be performed

when

a

breakdown in the radiation safety program involving a number of violations

that are related (or if isolated, that are recurring) that collectively

represent

a potentially significant lack of attention

or carelessness

toward

licensed responsibilities.

Procedure

PPM 1.3. 12A. Section 6.3, also states,

"PPM 1.3.48 should

be used in

the preparation of a root cause analysis determination

and documented

in a

Root Cause Analysis report."

Procedure

PPM 1.3.48 included discussions

on

root-cause

analysis

techniques

such as:

change analysis,

barrier analysis,

event

and causal

factor charting, fault-tree analysis,

human performance

evaluation

system,

and management

oversight

and risk-tree ana'lysis.

A

root-cause

analysis report format was provided with instruction to attach the

reports to the associated

problem evaluation request.

Event

1

Since the event was not recognized

as significant,

no formal root cause

analysis

was performed.

The cause of the event described

in PER 295-0492

was

determined

by the radiation protection organization to be failure to

self-check

(Root-Cause

Code PE0205).

Event

2

According to the note in Block 19 of the problem evaluation

request

form, the

event described

in PER 295-0927

represented

a significant adverse trend or

failure affecting

a quality program or plant safety.

The licensee

recognized

that the event

was significant and planned to perform

a formal root-cause

analysis.

However, it was decided that the independent

investigation would

suffice for the root cause analysis

because,

"nothing further can be. gained or

investigated."

The guidance of Procedures

PPM 1.3. 12A and

PPM 1.3.48

was not

followed.

None of the root-cause

analysis

techniques

described in Procedure

PPM 1.3.48 were used.

Had licensee

personnel

performed barrier analysis

as

part of a root-cause

analysis,

they would have identified that one of the

barriers,

which did not work was the verification program.

The verification

program is discussed

in Section 2.7.

The inspectors

reviewed the results of the independent

investigation

and noted

that the independent

investigator.

from the licensee's

Nuclear

Safety

Issues

Program.

concluded that the individuals "failed to lock the door."

The

investigator

made

no conclusion concerning the cause of the event.

The

inspectors

interviewed the investigator

and determined that he was not aware

that the investigation

was substituted for a formal root cause analysis,

and

he stated that he had not conducted the investigation

as

he would a root cause

analysis.

The cause of the event was listed on the problem evaluation request

resolution form as less than adequate

human performance.

Specifically,

root-cause

codes

were listed as,

"system alignment. tagout, restoration

not

verified" (PE0201),

and

"Oocuments not followed correctly" (PE0209).

Event 3

No formal root cause analysis

was performed after the third event.

The cause

of the event described in PER 295-0955

was determined

by the radiation

protection organization to be. procedural

noncompliance

(Root-Cause

Code PE0209).

Even though this event shared

one of the

same root-cause

codes

as the previous event. it was not seen

as part of an adverse trend.

Licensee

personnel

did not identify a problem with the verification program,

as

discussed

in Section 2.7

~

and the event

was seen

as

an isolated

example.

-9-

'onclusion

The radiation protection manager did not follow procedural

guidance outlined

in the root-cause

analysis

implementing procedure

and. therefore,

did not meet

management

expectations.

The licensee

missed

an opportunity to identify an

adverse trend

and

a problem with the verification program.

2.4

Resolution of Problem Evaluation

Re uests

Procedure

PPH 1.3. 12A, "Processing

Problem Evaluation Requests,"

Revision 2.

Section 5.3, stated that the dispositioning manager

"should disposition

PERs

within 30 days after initiation of the PER."

The inspectors

constructed

the time lines in Attachment

2 from document

reviews

and personnel

interviews.

This information demonstrates

that

a significant amount of time was expended

before the

PERs were dispositioned

through the submission of appropriate

and comprehensive

corrective actions.

Conclusion

Radiation protection personnel

did not meet management

expectations

of

resolving the

PERs in a timely manner.

2.5

Corrective Actions

The inspectors

interviewed licensee

personnel

and performed record reviews in

order to evaluation the licensee's

corrective actions related to the three

events.

Procedure

PPH 1.3. 12A. "Processing

Problem Evaluation Requests,"

Revision 2,

Section 6.4.4 states.

"The corrective action should

be completed within 60

days of PER disposition.

Event

1

The cause of the event described

in PER 295-0492

was determined

by the

radiation protection organization to be failure to self check.

The proposed

corrective action was to replace the chains

used to secure

high high radiation

area doorswith padeyes

(hasps).

The corrective action,

although appropriate

for the specific problem, did not directly address

the identified cause.

This

was first identified in a memorandum

dated July 26,

1995,

by quality assurance

personnel

reviewing the initial. proposed corrective actions.

The insoectors

agreed with this conclusion

and noted that the padeyes

were not instaljed

unti 1 September

14,

1995. too late to prevent the second event.

The licensee

missed

an opportunity to identify and correct problems

caused

by workers

who

did not understand

management.'s

expectations

related to the verification

process,

as discussed

in Section 2.7.

The response

from radiation protection

personnel

to the July 26 memorandum,

on August 15,

1995,

was,

"The corrective

-10-

action for failure to self-check is addressed

by

PER 295-0201 that is

addressing

Human Performance

Issue for WNP-2 plant wide basis."

The August

15

response

also stated

PER 295-0927 would thoroughly address

corrective actions

related to the self-checking issue.

Event 2

The cause of the event described

in PER 295-0927

was listed on the problem

evaluation request

resolution

form as less than adequate

human performance.

Six corrective actions

were originally proposed.

In a memorandum

dated

September

18,

1995, the radiation protection manager

was informed that the

disposition of PER 295-0927

was incomplete.

The memorandum stated,

"Although

the corrective actions that are already proposed

may add improvement to the

current Health Physics

program,

they do not identify a method by which future

personnel

errors of the same type can be minimized.

The

CAP [corrective

action plan] ¹6, which is to 'Evaluate the need for improved training for

personnel

.

.

. .'oes

not adequately

implement such

La] process

at this

time."

The reviewers stated further. that an evaluation is

a precursor .to

determining effective corrective action

and does not ensure training will be

performed.-

The inspectors

agreed with the assessment~.

Also, the inspectors

determined

through interviews that there

was

no attempt

made to notify the

general

working population of such problems in a timely manner,

such

as

through safety meetings or site newsletters.

Event

3

The cause of the event described

in PER 295-0955

was determined

by the

radiation protection organization to be procedural

noncompliance.

In a

memorandum

dated

September

15,

1995, the radiation protection

manager

was

notified of the return of PER 295-0955

because it did not contain cor rectiv'e

action.

Radiation protection personnel

indicated that appropriate corrective

action would be addressed

by

PER 295-0927,

CAP ¹6.

As stated

above,

PER 295-0927.

CAP ¹6 was found to be unacceptable.

For each of the

PERs

~ the initial corrective actions

were found to be

unacceptable,

when reviewed

by quality assur ance personnel,

or nonexistent.

The causes

for all events

were determined to fall under the general

heading of

"work practices,"

according to Procedure

PPH 1.3.48,

Attachment 8.6,

indicating an adverse trend.

Technical Specification

6. 12.2 requi res, in part, that in addition to the

requirements

of Technical Specification

6. 12. 1, areas

accessible

to personnel

with radiation levels

such that

a major portion of the body could receive in

1

hour

a dose greater

than

1000 mrems shall

be provided with locked doors to

prevent unauthorized entry.

The inspectors

determined that Events

1 and

2

were

a violation of Technical Specification 6. 12.2.

Further.

because

the

second

example of this violation could have reasonably

been expected to have

been prevented

by corrective actions for the first example

had they been

implemented in a timely manner.

the inspectors

determined this licensee-

identified violation did not meet criteria for exercise of discretion,

as

outlined in Section VII of the

NRC Enforcement Policy (397/9530-01).

Conclusion

A violation of Technical Specification

6. 12.2 was identified involving the

fai lure to maintain

a lock door for an area in which the radiation levels

exceeded

1000 mrems/hr.

2.6

Communications

Based

on information gathered

through personnel

interviews

and records

reviews, the inspectors

evaluated

the quality of the licensee's

communications

regarding these

events.

  • Event

1

According to a statement

to the inspectors

made by the mechanical

maintenance

worker involved in the event described

in PER 295-0492 'he mechanical

maintenance

worker was not aware that he was involved with a high high

radiation area control issue until informed by the inspectors

on September

26,

1995.

The incident evidently had not been discussed

at safety meetings

held

within the maintenance

department.

During another

interview with NRC

inspectors,

the radiation protection technician involved in the event stated

that he was not aware that

a problem evaluation request

was written and was

not aware of corrective actions that were taken to prevent recurrence.

The

licensee

could produce

no record of discussions,

safety meetings,

or general

communications

in which the plant workers were made aware of'

Technical

Specification violation and of corrective actions taken to prevent its

recurrence.

Event

2

According to a statement

made to inspectors

by the radiation protection

technician involved in the event described

in PER 295-0927,

he was not aware

of the previous event (described in PER 295-0492).

The inspector determined

that verification.

as it relates to high high radiation area

and very high

radiation area

locks was not addressed

in the licensee's

general

employee or

radiation worker training.

Conclusion

Communication of information regarding the first event

was poor

and

may have

contributed to the second

event.

-12-

2.7

Verification Pro

ram

The licensee relied on two forms of verification to ensure that Technical

Specification required locks were in place.

The first was the independent

verification by a second

person that doors to high high radiation areas

and

very high radiation areas

were locked after entries to the areas

were

completed.

The independent verifier did not have to be

a radiation protection

technician.

Any worker could perform the verification.

The second

form of

verification was performed

by radiation protection technicians

during weekly

routine assignments.

Radiation protection technicians

were required to verify

that high high radiation

areas

and very high radiation areas

were properly

locked.

The licensee

experienced

problems with both forms of verifications.

In the events, described

in PER 295-0492

and

PER 295-0927 'orkers

signed the

key log book verifying that the door (C115) to the high high radiation area

was properly locked.

In the first event.

the individuals did not physically

test the lock and chain to verify that the particular configuration kept the

door from being opened.

In the second

event, the workers obviously did not

communicate well and

no observations

or physical

checks

were performed.

The

inspectors identified no evidence of willful wrongdoing by the individuals

responsible f'r locking the doors

and performing the verification.

There was

no logical reason for the individuals to subject themselves

to possible

disciplinary action.

However, the inspectors

noted that there were variations

in the worker's understanding

of what was meant

by the requirement to verify

that the areas

were properly locked.

To some workers. verification meant

physically checking the locks and chains: to others it was simply an

observation or perhaps

a verbal confi rmation.

As discussed

in Section 2.6,

management's

expectations

for the verification program

as it relates to high

high and very radiation area

door locks were not included in the licensee's

general

employee or radiation worker training.

The radiation protection technicians

that performed weekly verification checks

on August

7 and 14.

1995, did not identify that there

was only one lock on the

door of the traversing incore probe

room,

an area controlled as

a very high

radiation area.

This condition existed

from August

1 until it was identified

by licensee

personnel

on August

17 '995.

Event 3 was

a violation of

Procedure

PPM 11.2.7.3 which stated,

"Accessible very high radiation areas

shall

be maintained double-locked."

The procedural

requirements

exceeded

the

requirements

of Technical Specification 6. 12.2 and

10 CFR 20. 1602.

The

inspectors

determined that this failure constitutes

a violation of minor

significance

and is being treated

as

a Non-Cited Violation, consistent with

Section

IV of the

NRC Enforcement Policy.

Also. the weekly verifications did not identify unti 1 the week of the

inspection

(on September

27.

1995) that the lock at the wet well had not been

re-cored at the

same tike as the other high high radiation area

locks.

Cores

were changed in the other

locks

on approximately August 1.

1995.

Re-cored

-13-

high high radiation area

padlocks were wrapped with a bright green

band to

distinguish them from other

locks and were highly visible.

The inspectors

were informed at the start of the inspection that all high high radiation area

locks had been re-cored.

In NRC Inspection

Report 50-397/95-21.

the inspectors

concluded that the

oversight program for high radiation areas

was weak.

This was based

on

finding that radiation protection technicians

were not aware of the number of

areas,

which were requi red to be verified.

A checklist including each

door to

be verified as locked was not used for guidance.

The licensee's

record of

weekly verification included

a single verification signature

and only stated

that high high radiation areas

and very high radiation areas

were checked.

The licensee

took action to address this concern

and during the current

inspection,

the inspectors

were shown

a checklist with 16 high high and/or

very high radiation areas.

Licensee representatives

stated that the checklist

was used for guidance but was not expected

by management

to be taken into the

field or kept as

an official record.

Conclusion

A Non-Cited Violation was identified involving the failure to follow a

procedure.

Radiation protection personnel

missed

two earlier opportunities to

identify the procedural violation.

The oversight program for high high and

very high radiation areas

continued to be weak, in part because,

management's

expectations

with regard to high high and very high radiation area

survei llances did not include the rigorous

and consistent

use of the guidance

provided to ensure that technical specification

requirements

were met.

2.8

Procedures

Procedure

PPN 1.2.2,

"Plant Procedure

Preparation,"

Revision 20,

Attachment 20. defines the following terms:

Shall

- Used to denote regulatory requirements,

external

commitments

and

selective specific management

direction.

Should

- Used to denote

recommendations

but not enforceable

regulatory

requirements

and management

expectations.

(Hanagement

expects

each

employee using plant expectations

to carry out "should" statements

unless

circumstances

prevent or necessitate

deviation.

Departures

from

recommendations

should be done after supervisory concurrence.)

The inspectors

reviewed Procedure

PPH 11.2.7.3,

"High and Very High Radiation

Area Controls," Revision

10, to determine if the procedure

conformed to the

above guidance

and noted,

as

an example,

that Section 5.2.6.e stated,

"When

exiting

a high high radiation area.

health physics

personnel

should lock the

door.

-14-

This was inconsistent with Section 5.2.2,

which stated,

"Accessible high high

radiation areas

shall

be maintained

locked whenever

reasonably possible."

Not only was Section 5.2.6.e inconsistent with Section 5.2.2,

but it was

inconsistent with the regulatory requirement of Technical Specification

6. 12.2

which states,

in part. "In addition to the requi rements of Specification

6. 12. 1, areas

accessible

to personnel

with radiation levels such that

a major

portion of the body could receive in

1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />

a dose greater than

1000 mrems

shall

be provided with locked doors to prevent unauthorized entry

.

.

. Doors

shall

remain locked except during periods of access

.

Radiation protection personnel

responded to inspectors'omments

by initiating

a procedure

change

form which changed

the "should" in this section to the word

"shall."

The inspectors

noted other examples of instructions that did not convey that

regulatory requirements

were the basis for the particular procedural

step.

Procedure

PPH 11.2.7.3,

Section 4.3, stated,

"Provisions should be made for

timely surveys to identify and post with precautionary notices.

the areas

and

systems that

may become high or very high radiation areas."

Contrast this to

10 CFR 20.1501(a),

which states.

that each licensee

shall

make or cause to be

made,

surveys that

may be necessary

for the licensee to comply with the

regulations in this part and are reasonable

under the circumstances

to

evaluate the potential radiological

hazards that could be present,

and

10 CFR 20. 1902, which states,

that each licensee

shall post each high and very

high radiation area.

Procedure

PPM 1.2.2 did not define the terms "will" and "must."

However,

Procedure

PPH 11.2.7.3,

Section 5. 1.8, stated.

"Personnel will receive,

at

a

minimum,

a briefing of the radiological conditions in the area prior to

entry."

The regulatory requi rement.

10 CFR 19. 12. states,

that all

individuals working in or frequenting

any portion of a restricted

area shall

be kept informed of radiation in such portions of the restricted

area

and in

precautions to minimize exposure.

Procedure

PPH 11.2.7.3,

Section 5.2.4 states,

"Entry into high high radiation

areas

greater

than or equal to 1000 mrem/hr will be controlled by the issuance

of an approved

RWP

.

.

. ."

Technical Specification

6. 12. 1 requi res,

in part,

that entrance into high radi ation areas

be controlled by requi ring issuance of

a radiation work permit.

Procedure

PPH 11.2.7.3,

Section 3.2, states.

"Personnel

must have received the

required radiological training before being allowed to high or very high

radiation areas."

Technical Specification 6. 12. 1 requi res,

in part, that

entry into such areas

.

.

.

may be made after the dose rate levels in the area

have

been established

and personnel

have

been

made knowledgeable of them.

Licensee representatives

stated that

~ even though the terms "will" and "must"

were not currently defined by procedures

they were interpreted

as meaning

"shall."

Licensee

representatives

indicated that they would be considering

ways to address

the presence of such terms in their procedures.

-15-

The inspectors

acknowledged that the licensee

could implement

management

expectations

with statements

containing the word "should," and that the

licensee

could allow flexibility with respect to management

expectations.

However, the examples listed wer e instructions that were necessary

to

implement regulatory requirements.

Therefore,

using the licensee's

definitions from Procedure

PPN 1.2.2, "shall" was the proper term to ensure

that licensee

personnel

understood

the regulatory significance.

In order to

evaluate the action to be taken by the licensee with respect to undefined

terms,

such

as will and.must.

and to evaluate

more fully whether the wording

contained in other radiation protection procedures

correctly implements

regulatory requirements,

the inspectors identified an inspection followup item

(397/9530-02).

Conclusion

The procedure for the control of access

to high and very high radiation areas

did not appropriately

convey all regulatory requirements.

2.9

Potential

For Si nificant Ex osure

In order to determine whether there existed

a substantial

potential

for

personnel

exposure to radiation in excess of regulatory limits, the inspectors

toured the 437-foot elevation of the radioactive waste building,

and on

September

27.

1995,

one of the inspectors.

accompanied

by a radiation

protection technician,

performed

independent

radiation measurements.

The radiation measurements

made

by the inspector

were in good agreement with

the licensee's

measurements.

General

area radiation levels were approximately

1.6 rems per hour.

The inspector identified one area that measured

approximately

15 rems per hour at 30 centimeter s and 500

rems

per

hour

on

contact.

The inspector determined that it would be difficult to place

a major

portion of the whole body within 30 centimeters of this area

and that it would

be unlikely that personnel

would be in such

a position long enough to receive

a radiation exposure in excess of regulatory limits.

Should

an individual be

in the area

long enough to receive

an overexposure, it would be likely that

the alarming dosimeter.

requi red for entry into the radiological controlled

area,

would alert the individual before the exposure

could occur.

During

NRC Inspection 50-397/95-16,

the inspectors

noted that there

had been

14 examples of individuals entering the radiological controlled area without

alarming dosimeters.

During this inspection,

the inspectors

found that the

licensee

had identified one additional

example since the end of the refueling

outage.

The inspectors

determined that the rate of personnel

entry into the

radiological controlled area without an alarming dosimeter

was low. and the

rate was decreasing

as workers

became

more familiar with the use of the

dosimeters.

-16-

The inspectors

also noted that Door C115 was massive

and opening the door was

a laborious task,

requiring that the hand wheel

be turned

many times.

Thus

the likelihood of an inadvertent entry to the .high high radiation area

was

low.

Had there

been

an inadvertent

entry, it was unlikely that an individual

would have received exposure in excess of regulatory limits.

Event

3 was unlikely to result in personnel

radiation exposure

because

personnel

entry was controlled by

a second lock.

Conclusion

The potential for personnel

radiation exposure in excess of regulatory limits

occurring as

a result of the events

was low.

0

1

PERSONS

CONTACTED

1. 1

Licensee

Personnel

ATTACHMENT 1

  • P. Bemis, Director Regulatory

and Industrial Affairs

  • V. Parrish,

Vice President

Nuclear Operations

T. Alton'echnical Specialist

D. Dinger. Health Physics Operations

Supervisor

  • C. Foley, Licensing Engineer

J.- Hunter, Health Physics Craft Supervisor

C.

Leon, Technical Specialist

~J.

Muth, Manager Quality Support

  • W. Rigby, Health Physics

Supervisor

V. Shockley, Assistant to the Radiation Protection

Manager

~J.

Swai les,

Plant General

Manager

  • D. Swank,

Manager Licensing

J. Tate,

Equipment Operator

  • J. Wiles. Qual.ity Assurance

Engineer

1.2

NRC Personnel

.

  • R. Barr, Senior Resident

Inspector

  • Denotes personnel

that attended

the exit meeting.

In addition to the

personnel

listed, the inspector contacted

other personnel

during this

inspection period.

2

EXIT MEETING

An exit meeting

was conducted

on September

28,

1995.

Ouring this meeting.

the

inspector

reviewed the scope

and findings of the report.

The licensee

expressed

the position that the wording used in its procedures,

as discussed

in Section 2.8

~ did not result in non-compliance with regulatory requi rements.

The licensee did not identify as proprietary,

any information provided to, or

reviewed

by the inspector.

0

-2-

ATTACHMENT 2

CHRONOLOGY OF EVENTS

Event

1

May 7,

1995

June

6

(30 Days)

June

8

(32 Days)

July 14

(68 Days)

July 26

(80 Days)

August

15

(100 Days)

September

27

(143 Days)

Door C115 was discovered

unlocked.

PER 295-0492

was

initiated.

Proposed corrective actions were due in 30 days.

A request

was

made by radiation protecti,on personnel

to

extend the deadline to June 30.

1995

A work order to install hasps

on all high high radiation

area

doors

was initiated.

The radiation protection organization submitted

a proposed

corrective action that required the replacement of chains

with padeyes, or hasps.

In a memorandum to the radiation protection manager

from

the'egulatory

support

manager,

the proposed corrective actions

were returned

and deficiencies in the actions

were

identified.

The radiation protection organization

was asked

to respond

on or before August 12.

1995.

The radiation protection organization

responded

and stated

that

PER 295-0201

and

PER 295-0927 would thoroughly address

corrective actions related to the self-checking issue.

PER 295-0492

was

reopened to include additional corrective

actions.

'

-3-

Event

2

August

8

August 9

(1 Day)

August 11

(3 Days)

August

16

(8 Days)

August 21

(13 Days)

September

18

(41 Days)

September

25

(48 Days)

Planned entry into a high high. radiation through Door C115.

Door C115 was discovered

unlocked.

PER 295-0927

was

initiated.

A nuclear safety issues

program lead investigator

was asked

to independently investigate the incident.

Memorandum containing the results of the independent

investigation

was sent

fr'om the incident review board

chairman to the plant manager.

Radiation protection manager

approves

proposed corrective

action.

In a memorandum to the radiation protection manager

from the

regulatory support manager,

the proposed corrective actions

were returned

and deficiencies in the actions were

identified.

The radiation protection organization

was asked

to respond

on or before October 8,

1995.

The radiation protection organization submitted additional

corrective actions.

Event 3

August

17

September

5

(19 Days)

September

15

(29 Days)

The door to the traversing incore probe

room was identified

as not having two locks are required

by procedure.

PER 295-

0955 was initiated.

The radiation protection organization

responded with

proposed corrective action.

In a memorandum to the radiation protection

manager

from the

regulatory support manager,

the proposed corrective actions

were returned

and deficiencies in the actions were

identified.

The radiation protection organization

was asked

to respond

on or before October 5,

1995.

P