ML17290A512

From kanterella
Jump to navigation Jump to search
Insp Rept 50-397/93-19 on 930524-28.Violations Noted.Major Areas Inspected:Inservice Insp Activities Conducted During Eighth Refueling Outage
ML17290A512
Person / Time
Site: Columbia 
Issue date: 06/24/1993
From: Ang W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML17290A510 List:
References
50-397-93-19, NUDOCS 9307140113
Download: ML17290A512 (11)


See also: IR 05000397/1993019

Text

Report

No.

Docket No.

License

No.

Licensee:

Faci 1 ity Name:

Inspection at:

Inspection

Conducted:

Inspectors:

U.S.

NUCLEAR REGULATORY COMMISSION

REGION

V

50-397/93-19

50-397

NPF-21

Washington Public Power Supply System

(WPPSS)

P.O.

Box 968

3000 George

Washington

Way

Richland,

Washington

99352

Washington

Nuclear Project No.

2

(WNP-2)

WNP-2 site near Richland,

Washington

May 24-28,

1993

C. Clark, Reactor Inspector,

Region

V

M. Payne,

Reactor Inspector,

Region

V

M. Tschi ltz, Project Inspector,

Region

V

Approved by:

m~8,

W. P. Ang, Chic

Engineering Section

Date Signed

Ins ection

Summar

Ins ection durin

the

eriod of Ha

24-28

1993

Re ort No. 50-397 93-19

Areas

Ins ected:

1

This routine announced

inspection

reviewed the Inservice Inspection (ISI)

activities conducted

during the eighth refueling outage

(R8).

Inspection

Procedures

73753,

"Inservice Inspection,"

and 92701,

"Followup," were used

as

- guidance

during the inspection.

Safet

Issues

Mana ement

S stem

SIMS

Item:

None

9307140113

930625

PDR

ADQCK 05000397

6

PDR

Results:

General

Conc1usions

and

S ecific Findin s:

~

ISI examinations

observed

were performed in accordance

with licensee

procedures.

Personnel

performing ISI examinations

and data evaluations

were

knowle'dgeable

and proficient in their activities.

~

A weakness

in controlling the introduction of foreign material

around the

open reactor vessel

and the refueling cavity area during refueling

operations

was identified.

Si nificant Safet

Hatters:

None

Summar

of Violation or Deviations:

One violation (with two examples)

was identified (paragraph

3 of the report):

~

Disassembly of a underwater

camera 'inside the refueling floor Foreign

Haterial Control

Boundary.

The camera parts were observed to be

uncontrolled

and unattended

on the floor.

Disassembly

outside

the

Foreign Haterial Control

Boundary was possible.

Failure to follow procedure

requirements

for logging of tools serial

numbers for accountability of tools brought into a Foreign Haterial

Control

Boundary.

0 en Items

Summar

No new open items were identified.

DETAILS

Persons

Contacted

Mashin ton Public Power

Su

1

S stem

  • C
  • L
  • R.
  • T
  • R.
  • J
  • D
  • G
  • R.
  • D

Baker, Plant Nanager

Fies,

Licensing Engineer

Gearhart,guali ty Assurance Director

Grumme,

Nuclear Safety Assurance

Nanager

Kyle, Chemistry Engineer

Nessersmith,

Haintenance

Support Nanager

Noen, Naterials

and Inspection

Nanager

Parrish,

Operations Assistant

Nanaging Director

Ramey,

Inservice Inspection

Engineer

Sorensen,Regulatory

Programs

Nanager

Webring, Technical Division Nanager

Welch, Nondestructive

Examinations

Supervisor

'Denotes

th'ose attending

the exit meeting

on Nay 28,

1993.

The inspectors

also held discussions

with other licensee

personnel

during

the inspection.

Inservice

Ins ection

Observation of Work Activities

73753

a.

~Pur ose

The purpose of this inspection

was to review a sample of completed

Inservice Inspectio'n (ISI) work and to observe

work activities in

progress

to determine if the inspection,

repair and replacement of Class

1,

2 and

3 pressure

retaining

components

were being performed in

accordance

with applicable requirements.

b.

~Back round

During this inspection

the licensee

was conducting the eighth refueling

outage

{R8) for WNP-2.

Section 4.0.5 of the Mashington Public Power Supply System

(WPPSS)

Project

Number

2 Technical Specifications

requires that Inservice

Inspection (ISI) be performed in accordance

with Section

XI of the

American Society of Nechanical

Engineers

(ASNE) Boiler and Pressure

Vessel

Code

(Code)

and applicable

Addenda.

The Code inspection

requirements

are the basis for inservice examinations

and tests

conducted

during the initial 120-month of commercial operation inspection interval,

which began

on December

13,

1984.

The Washington Public Power Supply

System Project

Number

2

(WNP-2) inservice inspection

program is in its

first ten year interval; ending December

13,

1994.

The licensee's

ISI

program is based

on the

1980 Edition of the

ASHE Code,

Section XI, with

Addenda through Minter 1980

{80M80), except that paragraph

IWA-2300 (a)

(1) and code category

C-F welds have

been

updated to the

1983 Edition,

Minter 1983 Addenda

(83W83).

In addition Paragraph

IFW-3400 has

been

2

updated

to the

1980 Edition, Minter 1981 Addenda

{BOM81).

c.

Scheduli n

of Work

The inspectors

reviewed licensee

ISI plans

and schedules

for the'urrent,

ISI interval to determine if changes

to the inspection

plan had

been

properly documented

and approved.

The inspectors

found that all changes

to the ISI plan had

been properly

documented

and approved.

d.

Review of Personnel

ualifications

and Certifications

The inspectors

reviewed the qualifications

and certifications of the

personnel

who were observed

conducting ISI examinations

during this

inspection.

These

personnel

were certified for LevelI and II

examination activities under American Society for Nondestructive

Testing

Standard

SNT-TC-lA.

The inspectors

also reviewed

a sample of the

qualifications

and certifications of licensee

and contractor

Level III

examiners.

The inspectors verified that the records

contained

the

required information,

such as:

employer's

name,

person certified and the

activity that they were qualified to perform.

e.

Observation of Work

The inspectors

observed

portions of the following examinations:

~

Volumetric examination of main steam piping welds

[numbers

26MS(l)D-

8, D-BLDI, D-8LDO, D-9, D-9LUI, and

D-9LUO] by ultrasonic testing

(UT) using procedure

No. gCI 6-13,

Rev.

5, "Ultrasonic Examination

of Ferritic Steel

Piping Welds."

~

Surface

examination of main steam piping welds

[numbers

26NS(1)D-8,

D-8LDI, D-BLDO, D-9, D-9LUI, D-9LUO], attachment

welds for eight

welded lugs installed

on reactor core isolation cooling

(RCIC)

system piping [weld No. RCIC-IC-2{M)] and reactor pressure

vessel

(RPV) head studs

[numbers

35-1-7A and 35-1-14A] by magnetic particle

testing

(NT) using procedure

No.

QCI 4-3,

Rev.

5, "Magnetic Particle

Examination

WNP-2."

~

Surface

examination of process

instrument line welds

[numbers XI-3

and XI-5] by liquid penetrant testing

(PT) using procedure

No. (CI

3-1,

Rev.

7, "Liquid Penetrant

Examination Instructions."

Visual examination of flange and valve bolting for reactor water

cleanup

(RWCU) system [item part numbers

4RMCU(3)-10BD, RWCU-V-100-

BLT and

RWCU-101-2]

and

RCIC system [item part No. 6RCIC{l)-28BD]

using procedure,

No.

QCI 7-1, Rev.5,

"Visual

Examination."'or

each of the examination

methods

observed,

the inspectors verified the

following:

~

Approved procedures

were available

and followed.

Nondestructive

examination

(NDE) equipment specified in the procedures

was used.

~

Personnel

were knowledgeable of the examination

methods

and proper

operation of the test equipment.

~

Personnel

were qualified and certified for the examination

activities which they performed.

These activities included

designation of examination

method, calibration of equipment,

examination,

and evaluation

and acceptance

of test results.

~

Required

documentation

was complete.

Examination results,

evaluations,

and any corrective actions,

repairs or replacements

were recorded

as specified in the ISI program

and

NDE procedures.

f.

Conclusions

The inspectors

concluded that the licensee

was adequately

implementing their approved

ISI program.

Licensee

personnel

were

knowledgeable

and proficient in their examination activities.

No violations or deviations

from NRC requirements

were identified in the

areas

reviewed.

Identification of Uncontrolled Material Inside

a Forei

n Material Control

Area

On May 26,

1993

a tour of the refueling floor was conducted.

During the

tour, while inside the foreign material control boundary area in the

northeast

section adjacent

to the reactor cavity, dryer separator pit,

and open reactor vessel,

the inspectors

noted loose hardware

which did

not appear

to be properly controlled.

The hardware consisted

of several

small

cap screws

and

a cover plate which were later identified as parts

of the underwater "fire fly" submarine

camera unit that was being

temporary stored within the area

by contractor personnel.

The submarine

unit was being used for inspections

inside the reactor vessel.

Repairs

to the submarine unit were ongoing but had temporarily been

suspended.

The inspectors

did not see

anyone working on the repair of the fire-fly.

Review of the foreign material accountabi,lity log sheets

for that day did

not reveal entries for each of the loose hardware.

The situation

was

brought to the attention of nearby personnel

and the cover plate

and cap

screws

were removed

from the foreign material control boundary area.

The

NRC inspectors notified the refueling floor supervisor for the

foreign material control boundary area that they had found uncontrolled

foreign material

(loose hardware) within the area,

which had

been

removed,

and requested

that

he identify the source of this foreign

material.

The licensee

investigation identified that the loose hardware

had

been

generated

by contractor personnel

performing repair work on the

fire fly camera.

This camera

had been properly logged into the foreign

material control

boundary

area

as

one piece of equipment.

The licensee

acknowledged that any foreign material/loose

hardware

generated

during

4

disassembly

of the submarine

camera within the foreign material control

boundary

area

should

have

been captured

or controlled, or the material

logged out of the area.

The licensee identified that contractor

disassembly

personnel

had requested

bags for capture of the loose parts,

but left the uncontrolled

loose parts in the area while they left to

obtain repair parts.

Plant Procedures

Manual

(PPM) Administrative Procedure

number 1.3. 18,

revision 8, "Foreign Haterial Control around the Spent

Fuel Pool, 'the

Reactor Cavity and the Dryer Separator Pit" provided the requirements

for

control of foreign material

in the Foreign Material Control

Boundary.

PPH 1.3. 18 Section 6.2. l.d required that,

"When possible,

move

an item

out of the Foreign Material Control

Boundary prior to any required

disassembly."

The inspectors

concluded that disassembly

of the "Fire Fly" submarine

camera

outside

the foreign material

control

boundary

was possible

because

the camera

was

a relatively small unit that could have

been readily

transported

outside

the boundary for disassembly.

Disassembly of the

"Fire Fly" submarine

camera inside the foreign material

control boundary,

is

a violation of PPH 1.3. 18 and Section 6.8. 1 of the

WNP-2 Technical

Specifications

(Violation 50-397/93-19-01).

The inspectors

noted that the licensee

had experienced

similar past

problems

with control of material accountability

around the reactor

vessel

cavi ty during the last refueling outage in 1992.

A similar

violation (50-397/92-14-03)

was issued

June

30,

1992, in NRC inspection

report 50-397/92-14.

Similarly, Problem Evaluation

Request

(PER)

numbers

293-487,

293-497

and 293-679,

issued during this refueling outage,

identified problems with foreign material control.

PPH 1.3. 18, Sections

3.8, 6.2 and Attachment-8.2

provided the following

requirements

for logging tools into

a foreign material control boundary:

~

Section 3.8, states

in part that,

" ...

The tools will also

be

marked,

using vibro etching or other suitable

permanent

markings,

with a number.

This number will be used to maintain the inventory

of the tools

and to aid in providing positive identification in

logging the tools into the Foreign Material Control Accountability

Log. ...

NOTE: The use of these tools does

NOT prevent other tools

that meet the ... logging requirements

from being brought into the

Foreign Material Control

Boundary.

Section 6.2. 1 c. states

in part that,

"The Foreign Material Control

Watch will log each

separate

item into the Foreign Material Control

Accountability Log...

The item shall

be logged in sufficient detai l

so that

someone

else bringing it back out can positively identify

II

tO

~

~ ~

~

~

Guideline

3 of Attachment 8.2,

"Foreign Material Control

Accountability Log Sheet

Maintenance

Instructions", stated in part

under tool or equipment description that,

"a good description of the

item is required

so that it can

be uniquely identified by someone

else at

a later time.

Clearly

a six inch screwdriver is not

- sufficient.

You would have

no way of knowing that the six inch

screwdriver being brought out is the

same

one taken in."

The Refueling Floor Foreign Material Control Accountability

Log sheets

'or Hay 25 through 27,

1993 were reviewed to determine

compliance with

the tool control, requirements

noted above.

Several

tool or equipment

descriptions

entered

in the logs were "utilityknife", "knife", "need'le

nose pliers", "safety wire plier", etc.

These descriptions

did not

contain

a unique

number to provide positive identification in logging

these tools in and out of a foreign material control boundary.

Examples

of tools logged into the foreign material control boundary were, as

follows:

(1)

A utility knife at 2355 hours0.0273 days <br />0.654 hours <br />0.00389 weeks <br />8.960775e-4 months <br />

on Hay 25,

1993.

{2)

A knife at 0945 hours0.0109 days <br />0.263 hours <br />0.00156 weeks <br />3.595725e-4 months <br />

on Hay 26, 1993.

(3)

A'nife at

1130 hours0.0131 days <br />0.314 hours <br />0.00187 weeks <br />4.29965e-4 months <br />

on May 26,

1993.

(4)

Needle

nose pliers at

1305 hours0.0151 days <br />0.363 hours <br />0.00216 weeks <br />4.965525e-4 months <br />

on

May 26,

1993.

(5)

A utility knife at 0137 hours0.00159 days <br />0.0381 hours <br />2.265212e-4 weeks <br />5.21285e-5 months <br />

on Hay 27,

1993.

(6)

Safety wire pliers at 0950 hours0.011 days <br />0.264 hours <br />0.00157 weeks <br />3.61475e-4 months <br />

on Hay 27,1993.

The above identified tools were not logged in with a unique serial

number

{and a sufficient description)

as required

by

PPH 1.3.18 Sections

3.8 and

6.2.1.c.

Further review of the accountability log and applicable

requirements,

subsequent

to the on-site inspection identified the failure

to record tool serial

numbers in the accountability log as another

example of a failure to follow procedure,

and the second

example for

Violation (50-397/93-19-01).

This is

a repeat of a Violation 50-397/93-

14-03 issued

on June

30,

1992.

The inspectors

discussed

the above identified violation examples with the

licensee,

and the licensee

acknowledged

the inspectors

concerns.

The

licensee identified that as

a result of violation 92-14-03 they had

revised

PPH 1.3. 18 and provided training to their personnel,

to provide

additional

guidance

on foreign material control

around the reactor vessel

cavity prior to this refueling outage.

The licensee

noted that as

a

result of the

PERs issued in this area during this refueling outage,

they

were already reviewing what additional actions

they could implement to

strengthen

the controls against

the introduction of foreign material

over

or around the

open reactor vessel

and refueling cavity area during

refueling operations.

The licensee

stated

they would factor these latest

NRC inspection results into their corrective actions to strengthen

the

controls against

the introduction of foreign material

over or around the

open reactor vessel

and refueling cavity area during refueling

operations.

0

An exit meeting

was conducted

on Hay 28,

1993, with the licensee

representatives

identified in paragraph

1 of this report.

'The inspectors

summarized

the scope

and findings of the inspection at that time.

The

licensee

representatives

acknowledged

the inspectors

findings.

The

licensee

did not identify 'as proprietary

any of the materials

reviewed

by

or discussed

with the inspector during this inspection.

Further review of information obtained during the inspection resulted in

the identification, subsequent

to the on-site inspection, of an

additional

example of procedural

compliance violation.

The additional

example involved fai,lure to log tool serial

numbers in the Foreign

Haterial Control accountability

log.

The licensee

was notified of this

additional

procedural

compliance violation example during

a followup

telephone

call

on June

18,

1993.

The licensee

acknowledged

the

additional violation example.