ML17289B082

From kanterella
Jump to navigation Jump to search
Insp Rept 50-397/92-35 on Stated Date.Violations Noted.Major Areas Inspected:Followup Items & Radwaste Mgt Program, Including Gases Radwaste Mgt,Liquid Radwaste Mgt & Radiological Environ Monitoring Program
ML17289B082
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 11/23/1992
From: Louis Carson, Coblentz L, Reese J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML17289B079 List:
References
50-397-92-35, NUDOCS 9212300044
Download: ML17289B082 (31)


See also: IR 05000397/1992035

Text

.

U. S.

NUCLEAR REGULATORY COMMISSION

REGION V

Report:

License:

Licensee:

Facility:

Inspection location:

Inspection duration:

Inspected

by:

50-397

NPF-21

Washington Public Power Supply System

(WPPSS)

P.O.

Box 968

3000 George

Washington

Way

Richland,

WA

99352

Washington Nuclear Project

2

(WNP-2)

WNP-2 Site,

Benton County, Washington

October

19

23,

1992

October

26 30,

1992

.

C. Carson

eactor

a saticon

pec>a

>st

a

e

gne

>I

.

Co

entz,

e

r

a >ation Spectra

est

ate

sgne

Approved by:

~Summar:

am

i

eese,

C se

ties Radiological Protection

Branch

II sa

a

e

S gne

Areas

Ins ected:

This routine unannounced

inspection

covered followup items

and the licensee's

radioactive waste

management

program.

The inspection

included gaseous

radwaste

(GRW) management,

liquid radwaste

(LRW) management,

and the Radiological

Environmental

Monitoring Program

(REMP).

Inspection

procedures

92701, 92702,'nd

84750 were used.

Results:

The licensee's

programs for radioactive waste

management

appeared

adequate

in meeting the licensee's

safety objectives.

Three violations,

however,

were identified:

The licensee

had released

low levels of radioactivity in liquids

to the onsite storm drain pond,

a method of disposal

not approved

by 10 CFR 20.301.

2."

3.

The licensee

had not performed

a written safety evaluation for

continuing to operate

the "non-radioactive" Turbine Building sumps

as

a radioactive

system.

Operators

had failed to respond appropriately to alarms

on

WOA-

RIS-31A, the Control'Room ventilation system

remote air intake

radiation monitor.

9212300044 92ii23

PDR

ADOCK 050003'P7

8

PDR

One non-cited violation was identified; regarding the failure of

radiation protection technicians

to maintain positive control of doors

to "high-high" radiation areas,

as required

by Technical Specification 6.12.1.

In addition,

two items were opened for future inspection,

regarding

(1)

the lack of timeliness in resolving the unanticipated

presence

of low-

level radioactivity in the storm drain pond,

and (2) the alternate

acceptance

criteria used for completing the calibration of the

meteorological

wind speed

and wind direction instruments with the output

computer inoperable.

Finally, the inspection identified as

a strength the comprehensive

and

well-documented efforts of the Radiological

Environmental

Monitoring

Program,

which exceeded

the requirements

of the Offsite Dose Calculation

Manual for maintaining effective oversight of radiological conditions in

the immediate site environs.

l

DETAILS

Persons

Contacted

Licensee

  • J

R.

  • C
  • J
  • J
  • A.
  • W.

C.

  • D
  • J
  • S
  • L
  • S
  • p
  • C
  • C
  • Q
  • J
  • D

+M.

  • J
  • W.
  • Q
  • G
  • R

NRC

Baker, Plant Manager

Barbee,

Instrumentation

and Controls

(I&C) Technical

Supervisor

Card, Supervisor,

Radiological

Environmental

Monitoring Program

Chasse,

Regulatory

Programs

Environmental

Engineer

Dabney,

Work Control Hanager

Davis, Principal Health 'Physicist

and Radiochemist

Davison,

Plant Quality Assurance

Manager

Halbfoster,

Chemistry Manager (Institute of Nuclear

Power

Operations)

Feldman,

Assistant

Maintenance

Manager

Gearhart,

Director, Quality Assurance

Grundhauser,

I&C Supervisor

Harrold, Assistant

Plant Manager

Kim, ALARA Engineer

HacBeth,

Radwaste

Supervisor

McGilton, Operational

Assurance

Programs

Manager

Madden, Quality Assurance

Engineer

(QAE)

Parrish,

Assistant Director of Operations

Peters,

Plant Administration Manager

Pisarcik,

Radiation Protection

(RP) Manager

Reis,

Plant Engineering/Compliance

Supervisor

Rhoads,

Operations

Event Assessment

Manager

Shaeffer,'perations

Manager

Shockley,

Health Physics

Manager,

Corporate

Sorensen,

Regulatory

Programs

Manager

Webring, Technical

Manager

  • S. Richards,

Deputy Division Director, Division of Reactor Safety

and

Projects,

Region

V

  • W. Ang, Acting Senior Resident

Inspector

D. Proulx, Resident

Inspector

I

(*) Denotes

those individuals who attended

the exit meeting

on October

23,

1992.

The inspectors

met and held discussions

with additional

members of the licensee's staff during the inspection.

Followu

92701

tern 50-397

IN-88-63

Closed

The inspectors verified that the

licensee

had received,

reviewed,

and taken action

on Information Notice 88-63,

Supplement

2, "High Radiation Hazards

from Incore Detectors

and

Cables."

Item 50-397 91-36-02

Closed

This item involved the licensee's

Updated Final, Safety Analysis Report

(UFSAR).

The inspector

had found

that the

UFSAR Chapter

11, "Radioactive

Waste Hanagement,"

did not

reflect the licensee's

latest

computer

code method

used in quantifying

gaseous-

and liquid radioactive waste effluent releases.

The Offsite

Dose Calculation Manual

(ODCH) had stated that the licensee

used

a

computer

code called

LADTAP II; however,

the

UFSAR had still reflected

that the licensee

used the

GALE computer code.

The inspectors

reviewed the latest

UFSAR change

(Amendment 44),

and

found that the licensee

had incorporated

the appropriate

ODCH references

into the

UFSAR, Chapter ll.

The inspectors

had no further concerns

in

this matter.

tern 50-39

2- 3-03

Clos'ed

This item involved the Radiological

Environmental Monitoring (REHP) group's report that samples of the plant

storm drain pond

had contained

State of Washington reportable levels of

iodine-131,

cerium-141,

and cobalt-60.'n

addition, the iodine-131

levels exceeded

the

NRC reporting criterion.

The licensee

had held

meetings with officials of the Washington State

Departments

of Health

and Ecology, in June

1992.

The licensee

had issued

a root cause

and

corrective action report

on storm drain pond, discharge

operations.

The inspectors

completed

an assessment

of the

pond contamination

and the

licensee's

evaluation.

This matter is discussed

in detail in Section

4(d) of this report.

Followu

of Items of Noncom liance

92702

Item 50-397 91-36-03

Closed

This violation involved an engineer's

failure to follow written radiation monitor calibration procedures.

Also, the procedure

had

been technically incorrect,

and the engineer

had

not written a procedure deviation

as required

by administrative

procedures.

Both instances

were violations of Technical Specification (TS) 6.8.1.

The inspectors verified that corrective actions listed in the licensee's

January

24,

1992,

"Response

to the Notice of Violation," had been

implemented.

Also, the licensee's

radiation protection department

had

performed

a self-assessment

on procedural

adherance

in September

1992.

The inspectors

examined

the status of the self-assessment

as presented

in a memorandum,

"Status of Radiation Protection

Department

Procedure

Compliance Plan," dated October 22,

1992.

Based

on the status of the

procedure

adherence

self-assessment

and the corrective actions in the

'esponse,

the inspectors

had

no furthe} concerns

in this matter.

Item 50-397 92-13-02

Closed

This violation involved the licensee's

failure to have written and approved procedures'for

the calibration of

installed personnel

contamination monitors (IPHs).

The

WNP-2 plant had

had at least

12

IPHs in service,

and the corporate organization

had

had

one

IPH in-service.

The violations had

been against

TS 6.8. 1 for not

establishing written and approved

procedures

for calibrating

IPHs.

The inspectors verified that the corrective actions,

as listed in the

licensee's

July 24,

1992,

"Response

to the Notice of Violation," had

4.

been

implemented.

The inspectors verified that radiation protection,

maintenance,

and corporate health physics

had developed

procedures

for

calibrating

IPMs owned by the Supply System.

Based

on the

inspectors'eview

of the

IPH calibration procedures,

there is no further concern in

this matter.

Radioactive'Waste

Treatment

Effluents

and the Radiolo ical

Environmental Nonitorin

Pro ram

RENP

84750

a.

Off as Radiation Honitorin

S stem

(1)

Performance Honitorin

The inspectors

reviewed offgas system data from the licensee's

performance

monitor

(PHE) program,

including graphs trending six

parameters

from September

1990-to,Harch

1992.

In addition, the

inspectors

examined

Procedure

PPH 8.4.46,

"Offgas System

Performance Honitoring," and reviewed efficiency and reliability

test results

from October

1991 to September

1992.

In discussions

with the system engineer

and performance

monitor

engineer,

the inspectors

observed that the

PHE program did not

trend

any radiological

parameter for offgas.

The

PNE engineer

acknowledged

the inspectors'bservation,

and stated that

consideration

would be given to trending offgas radiological

performance.

(2)

Ex losive

Gas Honitorin

TS 3.3.7.12 requires that the explosive

gas monitoring

instrumentation

channel

be operable to detect

hydrogen buildup in

the offgas system.

TS Action Statement ill'requires that offgas

grab. samples

be collected

and analyzed within an 8-hour period if

the minimum number of hydrogen analyzer

channels

are not operable.

The inspectors

reviewed applicable

records related to operation

and reliability of OG-AY-12A, the offgas hydrogen analyzer.

In

addition, discussions

were held with cognizant maintenance

and

engineering

perso'nnel,

and observations

were

made of work in

progress.

The inspectors

noted the following items:

(a)

OG-AY-12A had

been in and out of service several

times in

October

1992.

Review of the licensee's

Limited Condition

for Operations

(LCO) Logbook revealed

LCO entries for OG-AY-

12A dated October

4 and

19,

1992.

In addition,

Problem Evaluation

Request

(PER) 292-1170

stated that

a violation of TS 3.3.7. 12 had occurred

on

October

14,

1992,

when the chemistry department

had missed

the 4-hour offgas hydrogen analysis.

PER 292-1170 stated

that the missed

hydrogen analysis

had

been

caused

by

a

-problem with the gas

chromatograph.

The licensee

'

subsequently

issued

Licensee

Event Report

(LER) 50-397/92-

38-01

on this matter.

(b)

On October 20,

1992,

a chemistry technician

was observed

performing

an offgas hydrogen

sample

and analysis pursuant,

to TS 3.3.7. 12.

The chemistry technician collected the

sample

and performed the analysis in accordance

with

surveillance test

PPH 12.5.23A,

"Recombiner

Sampling

and

Analysis."

(c)

Maintenance

Work Request

(HWR) AP-0911

had

been written for

repairs to OG-AY-12A.

The inspectors

observed

a portion of

these repairs in progress,

and discussed

monitor reliability

with I&C personnel

performing the repairs.

Later review of the

HWR results

revealed that OG-AY-12A was

satisfactorily repaired,

tested,

and returned to service.

In addition, the results of surveillance test

PPH

7.4.3.7. 12.23,

"Offgas Hydrogen Analyzers

A and

B Monthly

Channel

Functional

Test/Channel

Calibration," indicated that

the calibration

was satisfactorily completed.

(3)

Off as Radiation Monitorin

The inspector reviewed surveillance test procedures

PPH

7.4. 11.2.7.2,

"Isotopic Analysis of Gases

at the Hain Condenser,"

and

PPH 7.4.4.5.4,

"Isotopic Analysis of Offgas Samples,"

used for

performing isotopic analysis

on offgas.

The inspector

found both

procedures

were adequate for quantifying offga's.

The inspector

observed

a chemistry technician perform surveillance

test

PPH 7. 1. 1, "HP/Chemistry Shift Channel

Check."

This test

provided

a method for routinely ensuring the operability of

process

and effluent radiation monitors

as required

by TS 3.3,

TS 3.3.7,

TS 3.4.3. 1,

and

ODCM 6.2.2.6.3.

The inspector

compared

the

results of three

PPH 7.1. 1 radiation monitor surveillances.

No

notable differences

were found in the data examined.

(4)

REA-RIS-609

A

B

C

and

D WNP-2 Isolation

and Actuation Si nals

The REA-RIS-609 Reactor Building Vent Monitors provide WNP-2's "1"

isolation

and actuation signals

when the Reactor Building Exhaust

Plenum radiation level measures

13 millirad/hour. The isolation.

signal

closes

the Reactor Building secondary

containment

system

isolation valves

ROA-V-1 and 2,

and

REA-V-1 and 2.

The actuation

signal starts

the standby

gas treatment

system.

TS Table 3.3.2-2a,

TS Table 4.3.2.1-1,

and

TS Table 3.6.5.2-1

require the Reactor Building Exhaust

Plenum radiation monitors to

be demonstrated

operable

by testing the isolation

and actuation

functions.

The inspectors

examined the licensee's

test

program

for demonstrating

the REA-RIS-609 "Z" isolation

and actuation

functions operable.

(a)

"Z" Si nal Surveillance Testin

The inspectors

held discussions

with plant system engineers

about the surveillance test

programs for verifying REA-RIS-

609 "Z" signal functions.

The system engineers

discussed

the following surveillance test procedures:

PPM 7.4.6.5.2. 1, "Reactor Building Ventilation

Isolation Valve Operability"

PPH 7.4.3.2.2.11,

"Balance of Plant Logic System

Functional Test"

PPH 7.4.3.2.3.7,

"Secondary

Containment Isolation on

Reactor Building Exhaust High"

The inspectors

found the system engineers

knowledgeable

about the test requirements,

and the surveillance tests

adequately

tested

the "Z" signal functions.

(b)

REA-RIS-609

A

8

C

and

D Calibrations

The inspectors

examined the calibration program for REA-RIS-

609 radiation monitors,

and held discussions

with the

responsible

engineer.

The engineer

discussed

the following

calibration

and surveillance test procedures:

Instrument Haster Data Sheet for REA-RIS-609 A, B,

C,

and

D

PPH 12.3.7,

"Reactor Building HVAC Exhaust

Plenum

. Monitor Calibration"

PPH 7.4.3.2.1. 15A, "Secondary

Containment Isolation

Reactor Building Channel

Functional Test"

PPH 7.4.3.2. 1. 16,

"Secondary

Contaiment Isolation

Reactor Building Vent Channel

A Channel

Calibration"

PPH 7.4.3.2. 1.81,

"Radiation Calibration of Reactor

Building Exhaust

Plenum Monitor REA-RIS-609A"

The system engineer

was knowledgeable

about the calibration

and test programs for the REA-RIS-609 monitors.

The

inspectors

reviewed results

from the June

1992 calibrations

of REA-RIS-609A and REA-RIS-609B,

and did not find any

problems.

The inspectors

concluded that the REA-RIS-609

radiation monitor calibration program was adequate.

(c)

Set oint Calculation for t e REA-RIS-609 Mon'tors

The licensee

was implementing

a program for re-verifying

setpoint calculations of var,ious instruments,

including the

REA-RIS-609 monitors.

The inspectors

compared the licensee's

February

1985

setpoint calculation for the REA-RIS-609 monitors to the

updated setpoint calculations

from Hay 1992.

The

  • inspectors'eview

of the two REA-RIS-609 setpoint

calculation methods did not reveal

any concerns.

The

inspectors

considered

the licensee's

setpoint calculation

method program

a positive effort.

The licensee's

program for offgas radiation monitoring, in the aspects

reviewed,

was adequate

in meeting the licensee's

safety objectives.

No

violations of NRC requirements

were identified.

b.

Standb

Gas Treatment

S stem

The inspector

examined

the licensee's

standby

gas treatment

(SBGT)

system surveillance test program.

The

SBGT system is

a engineered-

safety-feature

atmosphere

clean-up

system that has high efficency

particulate air

(HEPA) filtration units and charcoal

adsorption units.

Technical Specification (TS) 3.6.5.3 sets the requirement for testing

the

SBGT system consistent

with Regulatory

Guide

(RG) '1.52,

"Design,

Testing,

and Haintenance Criteria for Post-Accident

Engineered-Safety-

Feature

Atmosphere

Clean-up

System Air Filtration and Adsorption Units

of Light Water. Cooled Nuclear

Power Plants."

The inspector

performed

a system walkdown with the

SBGT system engineer,

and reviewed the following surveillance tests:

PPM 7.4.6.5.3. 1, "Standby

Gas Treatment

System Operability Test"

PPH 7.4.6.5.3.5,

"Standby

Gas Treatment

System

HEPA DOP Test

and

Visual Inspection"

PPH 7.4.6.5.3.5B,

"Standby

Gas Treatment

System Unit "B" .HEPA

Filter Test"

PPM 7.4.6.5.3.6B,

"Standby

Gas Treatment

System Unit "B"

Filtration System

Carbon Adsorber Test"

PPH 7.4.6.5.3.6,

"Standby

Gas Treatment

System Adsorber Bypass

Leakage Test"

The inspector

examined

SBGT system performance monitoring evaluation

(PHE) data.

The licensee's

PHE group had trended

several

SBGT filter

parameters

that were based

on

PPH 7.4.6.5.3.

1 test data from February

1991 to August 1992.

The inspector

found the trended data

on

SBGT

a

positive indication of system performance.

it

7

The surveillance tests

reviewed

had

been

conducted

in a timely manner,

and had

been

performed successfully

in accordance

with TS 3.6.5.3

and

RG 1.52.

The inspector concluded that the licensee's

SBGT program was

fully capable of meeting -the licensee's

safety objectives.

No

violations of NRC requirements

were identified.-

c.

Control

Room Ventilation

S stems

The inspectors

reviewed the status of the Control

Room normal

and

emergency ventilations

systems

by system walkdowns, discussions

with the

system engineer,

and reviews of procedures

and calibrations.

Selected

surveillances

required

by TS 4.7.2 were reviewed,

including the

following tests:

7.4.7.2. 1, "Control

Room Emergency Ventil-ation System Operability"

7.4.7.2.2B,

"Control

Room Div-B Emergency Filtration System

HEPA

Filter Test"

7.4.7.2.3B,

"Control

Room Div-B Filtration System

Carbon

Adsorber Test"

7.4.7.2.5;

"Control

Room Emergency Filtration Heater Operability"

7.4.7.2.8,

"Control

Room Ventilation Pressurization

Flow Test"

7.4.3.7. 1.25,

"Radiological Calibration of Remote Air Intake

Nonitor WOA-RIS-31A"

The surveillance tests

reviewed

had

been conducted, in a timely manner,

and

had

been

performed successfully

in accordance

with TS requirements.

During a system walkdown, the inspectors

noted

a deficiency tag,

dated

October

12,

1992, for WOA-RIS-31A (a control

room emergency ventilation

"

system remote intake radiation monitor).

The deficiency tag indicated

that the monitor was spuriously alarming every

5 minutes.

I

To understand

the significance of this condition, the inspectors

reviewed several

procedures

and records,

and held discussions

with

operators,

system engineers,

and

RP personnel.

(1)

Ins ector Followu

The inspectors

asked the on-shift Control

Room supervisor

whether

WOA-RIS-31A was considered

operable.

The supervisor stated that

the spurious

alarms

had not been

observed recently,

and that the

monitor appeared

to be operating normally.

The supervisor stated

further that based

on these observations

the monitor should

be

considered

operable.

The supervisor stated that, to his

knowledge,

no operability determination

had

been performed for the

monitor.

l

0

I

1I

The inspectors

reviewed the Control

Room log for TS Limiting

Conditions for Operation

(LCOs),

and verified that no entry had

been

made in the

LCO log for WOA-RIS-31A. 'n addition, the

inspectors

reviewed the Control

Room operator's

log for October

12,

1992,

but were unable to find any entry regarding

alarms or

abnormal

performance related to WOA-RIS-31A.

The inspectors

also discussed

the condition of the monitor with

the

RP effluent analyst

and the

IKC Technical Supervisor.

Both

individuals stated that they had only recently

been

informed of

the monitor's condition.

The inspectors

were also informed that

the monitor's behavior indicated

a possible detector failure,

and

that

a detector replacement

and monitor calibration were scheduled

for October 22,

1992.

Licensee

Followu

On Wednesday,

October

21, the inspectors

were informed that the

detector

replacement

would be delayed,

due to performance of a

written safety evaluation

(per

10 CFR 50.59) for voluntary entry

into an

LCO, occasioned

by taking the monitor out of service for

repair.

The inspectors

were informed, further, that detector

replacement

might not be necessary,

because

welding had

been going

on near the monitor,

and electronic noise

engendered

by the

welding was seen

as

a possible

cause of the spurious monitor

alarms.

On October 22, the inspectors

were informed that the

RP effluent

analyst

had compiled data from computer records of October

12.

These

records

indicated that the alarms

on WOA-RIS-31A had not, in

fact,

been spurious,

but had

been

due to the actual

presence

of

radioactivity.

The inspectors

reviewed these

records with the

RP effluent

analyst.

The monitor records

showed

a build-up and decrease

in

radioactivity over approximately

a 4-hour period.

Other radiation

monitors with sample points in the

same general

area of the site

showed

a similar rise

and fall in activity levels (although

no

other monitors were recorded

as alarming).

The

RP effluent analyst -had also reviewed records of

meteorological

data for the

same 4-hour period.

This data

indicated that the source of radioactivity had probably

been the

"building wake effect,"

as observed

on previous occasions

under

similar meteorological

conditions.

Levels of radioactivity, wind

speed

and direction,

and ventilation system configuration

supported this conclusion.

The licensee's

evaluation

concluded that the October

12,

1992,

alarms

on WOA-RIS-31A had

been valid alarms,

and that the monitor

had

been operable at all times.

(3)

NRC Assessment

and Conclusion

In review of applicable

TSs, licensee

procedures,

and records,

the

inspectors

noted the following:

TS 3.3.7. 1 requires

a minimum of two monitor channels to be

operable

per remote intake. If one of the required monitors

is inoperable,

isolation of the associated

remote air intake

is required within

1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.

TS 6.8. 1 requires that written procedures

shall

be

established,

implemented,

and maintained covering the

activities referenced

in Regulatory Guide 1.33,

Appendix A.

Regulatory

Guide 1.33,

Appendix A, Section

5, references

procedures for abnormal,

off-normal, or alarm conditions.

Licensee

Procedure

4.826.Pl,

Revision

1, describes

the

following required action for responding to a control

room

emergency ventilation system remote intake radiation monitor

alarm:

2.

Determine the source of radioactivity in

the remote intake.

The inspectors

noted that the Control

Room operators

had not

responded

appropriately to the October

12,

1992 alarms

on MOA-RIS-

31A, in several

ways:

(a)

The operators

had mistakenly

assumed that the alarms

were

invalid, and therefore failed to determine

the source of

'adioactivity in the remote intake.

(b)

Even if the operators'ssumptions

had

been correct

(such

that the alarms

were invalid and the monitor inoperable),

,their response

would not have

been justified," because

they

had not followed TS requirements

for an inoperable monitor.

(c)

Because of the lack of operator action, the analysis of the

source of radioactivity had not taken place until 10 days

after the alarm condition.

The inspectors

also noted that plant design,

as currently

~ configured,

depended

on operator action, for manual isolation of

the air intake valves

under adverse

radiological conditions.

This

action was

based

on maintaining

a habitable Control

Room during

accident conditions in accordance

with General

Design Criterion 19

of 10 CFR 50, Appendix A.

The inspectors

observed that prudent

operator

response

to alarms

was

an essential

feature in

determining the source of radioactivity and responding

appropriately.

10

The inspectors

concluded, further, that the failure of Control

Room operators to follow Licensee

Procedure

4.826.P1,

as given

above,

constituted

a violation of TS 6.8. 1 (50-397/92-35-01).

Mith the exceptions

noted,

the licensee's

programs for maintenance

and

operation of the Control

Room ventilation systems

appeared

adequate

in

accomplishing the licensee's

safety objectives.

One violation was

identifi.ed.

d.

Li uid Effluent Monitorin

The inspectors

reviewed aspects

of the licensee's

liquid effluent

monitoring'program

by performance

of, system walkdowns, discussions

with

system engineers

and

RP personnel,

and review of applicable

procedures

and records.

The following surveillance tests

were reviewed:

16.5.3,

"Turbine Sump

1 Radiation Monitor Channel

Functional

Test"

16.5.6,. "Turbine Sump

2 Radiation Monitor - Channel

Functional

Test"

16.5.9,

"Turbine Sump

3 Radiation Monitor - Channel

Functional

Test"

16.5. 1; "Turbine

Sump

1 Radiation Monitor - Channel Calibration"

16.5.4,

"Turbine

Sump

2 Radiation Monitor - Channel Calibration"

In review of the Turbine Building sump drain system,

the inspectors

raised

several

concerns,

as presented

in the following discussion.

(1)

S stem Descri tion

\\

Drains in the Turbine Building flow to five major sumps.

Sumps T-

1, T-2,

and T-3 are non-radioactive

by design.

Sumps T-4 and T-5

are radioactive

by design.

Discharge

from the radioactive

sumps is normally routed to

radwaste.

Discharge

from the non-radioactive

sumps is normally

routed (via the roof drain system) to the storm drain pond,

located outside the protected

area,

near the

MNP-2 warehouse.

During normal operation,

the storm drain pond receives

approximately 30,000 gallons of liquid per day.

The storm drain

pond is unlined,

and

has

no outlet.

The non-radioactive

sumps

have radiation monitors, set at 80X of

the liquid effluent- limits of 10 CFR 20, Appendix B, Table II.

Exceeding

these setpoints will automatically redirect

sump

discharge

to radwaste.

0

~

~

(2)

Back round

and Timeline

On July 30,

1992, the licensee

had sent the

NRC a Special

Report

regarding unanticipated

levels of radioactivity that

had

been

detected

in the storm drain ponds

(see discussion

in Section

2,

above).

During the onsite inspection,

the inspectors

reviewed the

=licensee's

history of storm drain pond sampling,

in order to

determine the timeliness of the licensee's

actions in responding

to the unanticipated

levels of radioactivity.

(a)

Technical

Evaluation Request

(TER) 88-0157, April 1988:

This TER stated that low levels of radioactivity had

been

found in the storm drain pond.

It recommended

a thorough

investigation

and corrective actions to determine

and

eli'minate the source of unanticipated radioactivity.

(b)

Problem Evaluation

Request

(PER) 289-0731,

September

1989:

This

PER stated that low levels of zinc-65

and other

nuclides

had

been

found in soil samples

from the storm drain

pond.

These

concerns

were incorporated into the ongoing

action for TER 88-0157

(discussed

above).

(c)

PER 292-0531,

May 1992:

This

PER stated that elevated

activity and abnormal

red color had

been

observed

in surface

water samples

from the pond.

This

PER resulted in the

Special

Report being sent to NRC.

(d)

Quality Finding Report

(QFR) 292-014,

June

12,

1992:

This

QFR stated that unmonitored releases

(such

as those to the

storm drain pond) indicated

a programmatic failure.

The

QFR

made

numerous

references

to the licensee's

UFSAR,

NRC

regulations,"

and

NRC bulletins

and information notices.

(e)

PER 292-0781,

June

27,

1992:

This

PER stated that temporary

drain lines

had

been inadvertently routed from main

condenser

conductivity cell taps to the non-radioactive

Turbine Building sumps without prior sampling.

The

PER also stated,

as part of the evaluation,

that

followup sample results

had found the T-2 (non-radioactive)

sump to contain 4.6 E-7 microcuries/milliter (uci/ml).

Since this level

was less

than the limits of 10 CFR 20,

Appendix B, however,

the

sump

had

been realigned to the

storm drain pond (with the apparent

concurrence

of the

PER

evaluators).

(f)

Response

to

QFR 292-014,

August 3,

1992:

This response

stated that

a root cause

analysis of the problem had

been

- completed.

Host of the radioactivity in the storm drain

ponds

was attributed to liquids from turbine overhaul.

The root cause

analysis

attached

to the response

cited

12

specific transfers of red liquid that

had

been

made from the

T-5 (radioacti.ve)

sump to the T-2 (non-radioactive)

sump

on

Hay 3 and

May 12.

The activity of the liquid, as recorded,

had.been

approximately 7.0 E-6 uci/ml.

A total, of

approximately

1000 gallons

had

been transferred

to T-2 (and

subsequently

discharged

to the storm drain pond).

As one corrective action, the response

recommended

a

thorough evaluation of potential leak paths into the non-

radioactive Turbine Building drain system

by September

7,

1992.

(3)

Re ulator

and License

Re uirements

10 CFR 20.301 requires that no licensee

dispose of licensed

radioactive material

except

by certain specified

methods (i.e.,

by

approved transfer methods or via approved effluent discharge

paths).

10 CFR 20.302 allows licensees

to apply for approval of

procedures

for alternate

methods of disposal

not otherwise

authorized.

10 CFR 50.59 requires-,

in part, that the licensee

shal-l maintain

records of changes

to the facility or procedures

described

in the

UFSAR, including

a written safety evaluation that provides the

basis for determining that the change

does not involve an

unreviewed safety question.

'FSAR Section 9.3.3,

"Equipment

and Floor Drainage Systems,"

states

in part:

Equipment

and floor drainage

systems

are provided to

handle radioactive

and non-radioactive

wastes

in

separate

systems.

Radioactive

wastes

are collected in

the building sumps

and

and transferred

to the radwaste

system for treatment,

sampling

and disposal

or reuse

within the plant.

Roof drains

and non-radioactive

floor drains are drained

by gravity or pumped to the

storm drain system.

UFSAR Section 9.3.3.2.3.

1 describes

the non-radioactive

Turbine

Building sumps that are routed to the storm drain system.

NRC IE Bulletin 80-10,

"Contamination of Nonradioactive

System

and

Resulting Potential for Unmonitored, Uncontrolled Release

of

Radioactivity to Environment," requests

operating licensees

to

take several

actions.

Specific action is designated

for

situations in which nonradioactive

systems

become radioactively

contaminated:

(a)

Use of, the system

must

be restricted until the cause of

contamination is identified and corrected,

and the system

~ decontaminated.

13

(b)

If continued operation is necessary

with the system

contaminated,

a safety evaluation

must

be performed per

10 CFR 50.59

(as given above).

(c)

If the evaluation

concludes that the system

may be operated

as

a radioactive

system,

any potential

releases

must

be

controlled

and maintained to the levels

addressed

in 10 CFR 50, Appendix I.

(4)

Discussions

With Plant

RP Mana ement

On October 22,

1992, the inspectors

discussed

with members of

plant

RP management

the levels of radioactivity found in the storm

drain pond samples.

The inspectors

noted the following points of

discussion:

(a)

Plant

RP management

stated that, to their knowledge,

issues

surrounding the radioactivity in the storm drain pond did

not represent

a non-compliance with NRC requirements

or a

non-conformance

to license conditions.

(b)

Based

on their belief that this matter did not constitute

a

non-compliance,

plant

RP management

also felt that the storm-

drain radioactivity concerns

had

been

addressed

in

a timely

manner.

(c)

Plant

RP management

was not aware of any instances

in which

radioactive liquid had knowingly been routed to the non-

radioactive Turbine Building sumps or discharged

to the

storm drain pond.

On October

23,

1992, the inspectors

discussed

with plant

RP

management

the response

to (FR 292-014

and the associated

root

cause

analysis

(see Section 4.d(2),

above).

The inspectors

pointed out that the root cause

analysis

described

instances

in

which radioactive liquid had knowingly been

sent to the storm

drain pond.

After review, plant

RP management

acknowledged

the

statements

in the root cause analysis,

but stated that neither the

(FR response

nor the root cause

analysis

had ever

been routed to

them.

(5)

NRC Assessment

After review of the documents

discussed

above,

and after

discussions

with plant

RP management

and other members of the

plant staff, the inspectors

noted the following points:

(a)

Sample results

from the storm drain pond indicated the

presence

of radioactivity in levels well above environmental

background;

however,

none of the sample results or surveys

of the

pond indicated radioactivity in levels that would

pose

a significant radiological

hazard

by

a reasonable

t,(

14

pathway of exposure.

For additional perspective

on the sample results,

see

Attachment

-A to this report.

(b)

Although the storm drain pond is located outside the

licensee's

protected

area, it is within the "restricted

area"

as presented

in the

UFSAR, Section

2. 1. 1.3.

The

inspectors

noted,

however, that the licensee

did not control

access

to the storm drain pond area for the purposes

of

minimizing radiation exposure.

(c)

Discussions

with plant staff and review of records

indicated

a lack of understanding

of the legitimate

uses of the non-

radioactive Turbine Building sumps,

as follows:

(i)

Since the

sump monitor alarms

had

been set at 80X of

the limits of 10 CFR 20, Appendix B, Table II, some

members of plant staff had

assumed that any liquids

containing radioactivity in levels less

than the alarm

setpoint could legitimately be disposed of in these

sumps.

(ii)

The licensee's

evaluation of PER 292-0781

(see Section

4.d(2),

above) clearly demonstrated

this lack of

understanding.

After sample results

from the T-2 sump

had

shown the

sump liquid to be radioactive. (but less

than

10 CFR 20, Appendix

B levels),

the

sump discharge

had been re-routed to the storm drain pond.

(d)

(e)

The licensee

was unable to provide evidence that

TER 88-0157

had ever

been closed,

or that the evaluation of unmonitored

radioactive inputs to the storm drains,

requested

by the

TER,

had ever been performed.

The inspectors

noted,

specifically, that the evaluation

requested

by the

1988

TER

was, in essence,

the

same

as the evaluation

requested

by the

1992

gFR ((FR 292-014,

discussed

above).

'I

The licensee

had not performed

a written safety evaluation,

per

10 CFR 50.59, to justify continued operation of the

"non-radioactive" Turbine Building sumps

as

a radioactive

system.

(f)

The licensee

had not applied to the

NRC, per

10 CFR 20.302,

for approval of disposal of licensed radioactive material

via the storm drain pond.

The inspectors

concluded, first, that routing radioactive liquids

to the storm drain pond was

an unapproved

method of disposal

of

licensed radioactive'aterial,

and

as

such constituted

a violation

15

of 10 CFR 20.301

(50-397/92-35-02).

The inspectors

concluded,

second,

that the licensee's

failure to

perform

a written safety evaluation for operating

as radioactive

a

system designed to be non-radioactive

constituted

a violation of

10 CFR 50.59 (50-397/92-35-03).

The inspectors

concluded, finally, that the lack of timeliness

surrounding the resolution of this area indicated the need for

improvement

by management

in responding to radiological concerns.

This item will be further addressed

in a future inspection

(50-

397/92-35-04).

(7)

Licensee

Res

onse

At the exit interview on October 23,

1992, the licensee

acknowledged

the inspectors'bservations

related to radioactivity

in the storm drains.

The licensee

stated that priority would be

given to resolving this matter.

In subsequent

telephone

conversations,

the plant

RP Hanager stated

that the non-radioactive

Turbine Building sumps

had

been

redirected

to radwaste until evaluation of the situation could be

more fully completed.

In addition, the licensee

was continuing to

evaluate

(a)

the

amount

and concentration of radioactive material

currently in the storm drain pond,

(b)

the potential

pathways for unmonitored radioactive material

to enter non-radioactive

systems,

and

(c)

- methods of restricting access

to the storm drain pond for

the purposes of minimizing radiation exposure.

The licensee's

programs for monitoring and control of liquid radioactive

waste

appeared

to warrant

improvement in several

areas,

as discussed.

Two violations of NRC requirements

were identified.

V

e.

Radiolo ical Environmental Honitorin

Pro ram

REHP

The inspectors

evaluated

aspects

of this program area

by interviews with

cognizant personnel,

reviews of recent records

and reports,

and

observation of work in progress.

Observations

were

made regarding

(1)

environmental

sampling

and analysis

and

(2) meteorological

monitoring.

Environmental

Sam lin

and Anal sis

The

REHP sampling records

and schedules

indicated that sample

collection had been

conducted

at the locations

and frequencies

prescribed

in the Offsite Dose Calculation Hanual

(ODCH), Table

6:3. l.l-l.

The inspectors

noted the following items:

h

H

fi

L

I'I

0

16

(a)

In addition to the locations specified in the

ODCH, the

REHP

group routinely sampled other site locations,

in a

commendable effort to maintain

a thorough,

comprehensive

oversight of radiological conditions in the site environs.

Sampling history and radiological profiles of each location

had

been well-documented.

(b)

One inspector

observed

performance of Environmental

Program

Instruction

(EPI) 12.4.5,

"Sediment Sampling," at the

upstream

and downstream locations

on the Columbia River

bank.

Sample collection was performed in a technically

sound manner,

and in accordance

with the procedure.

(c)

Review of selected

sampling records

indicated that the

offsite vendor laboratory

used

by the licensee

had

been

able, in all cases

reviewed, to meet the requirements

of the

ODCH for achieving lower limits of detectability

(LLDs).

(2)

Heteorolo ical Honitorin

The inspectors

reviewed recent calibration

and performance

data

for the meteorological

monitoring instruments,

and toured the

licensee's

meteorological

monitoring system with the system

engineer.

Several

observations

were

made:

(a)

(b)

The licensee

had upgraded

the Control

Room chart recorders

during the last outage.

The licensee

also planned to

install

a new digitized 7-point recorder in the

meteorological

tower local equipment

shed.

Records

indicated that the system

had

been performing

reliably.

Channel

checks

and channel

calibrations

had

been

performed at the frequencies

specified in TS Table 4.3.7.3-

l.

(c)

In review of the most recent calibration of the 33-foot and

245-foot wind speed

and wind direction channels,

the

inspectors

noted that certain readings

had not been taken at

output points

HET-POl and HET-P02,

due to the computer being

down.

The inspectors

asked the system engineer

what

alternate

acceptance

criteria had

been

used to ensure that

the loop was satisfactorily calibrated.

The system engineer

stated that further research

was necessary

to determine

what

criteria had

been

used.

This matter will be reviewed in a

future inspection

(50-397/92-35-05).

The licensee's

REHP and meteorological

monitoring program appeared

adequate

in meeting the licensee's

safety objectives.

The extra

measures

taken

by the

REHP group, in order to maintain

a comprehensive

and well-documented

status of radiological conditions in the immediate

site. environs,

appeared

to be

a program strength.

No violations or

deviations

were identified.

17

Control of Access to "Hi h-Hi h", Radiation Areas

On October 21,

1992, the licensee notified the inspectors of two

instances

in which individuals violated TS 6.12.1 requirements for

ensuring that doors to "high-high" radiation areas

are controlled by

radiation protection staff.

(A "high-high" radiation area is an area in

which dose rates

measure

1000 millirem/hour or more.)

TS 6. 12. 1 requires that high-high radiation area doors

have continuous

health physics technician

coverage

when open.

If health physics

technicians

are not present,

the doors must

be locked closed,

and the

keys must

be under the control of the radiation protection department.

The inspector

examined

Problem Evaluation Request

(PER) 291-1186

and

PER

291-1187,

which described

both of the high-high radiation area doors

as

having

been discovered

open

on the morning of October

21;

1992.

PER

291-1186 stated that the gate to the "B" Reactor Water Cleanup

Room in

the Radwaste

Building had

been found open.

PER 291-1187 stated that the

gate to the Waste Storage

Area in the Radwaste Building had

been

found

open.

In neither case

had health physics technicians

or other personnel

remained

in the area while the doors were open,

and in both cases

health

physics technicians

had

been responsible for leaving the doors

open.

The licensee's

radiation protection staff had found the doors

open

during

a routine tour.

The licensee

had taken prompt corrective action

to restore

access

control

by locking the doors

and re-establishing

key

control.

The licensee

had determined,

fur ther, that the root cause of

these

incidents

was preventable

personnel

error.

A procedure

change

was

implemented,

requiring 2-person

independent verification when locking

high-high radiation area doors.

The inspectors

concluded that leaving the two doors

open

and unattended

was

a violation of TS 6.12.1.

However,

based

on the isolated nature of

this matter,

and based

on the promptness

and thoroughness

of the

, licensee's

corrective action, the inspectors

concluded that the criteria

in Section

V.G of the

NRC Enforcement Policy had

been satisfied.

As a

result, this violation will not be cited (50-397/92-35-06).

Exit Interview

The inspectors

met with members of licensee

management

at the conclusion

of the onsite portion of the inspection

on October 23,

1992.

The scope

and findings of the onsite portion of the inspection

were summarized.

The licensee

acknowledged

the inspectors'bservations.

'

l

~ 'i

'

ATTACHHENT A:

COHPARISON TABLE FOR

STORM DRAIN POND SURFACE

MATER SAMPLES

(all numbers given in picocuries/liter)

Nuclides

Cobalt 60

Cerium 141

Cesium

137

Iodine

131

Manganese

54

Antimony 125

Zinc 65

Tritium

10 CFR 20

Appendix

B

Table II*

30,000

90,000

20,000

300

100,000

20,000

100,000

3,000,000

WNP-2 ODCH

Reporting

Levels**

300

50

2',000

300

3P PPP****

State of

Mashington

(DOH)

S

i

L

100

100

100

100

100

100

1,000

Storm Drain

Surface Mater

Sam le Results***

II

124.7

707

5.7

21.1

5.8

20.8

52.9

100 - 270,000-

Values established

for radioactivity in liquids discharged

by approved

effluent pathways-to unrestricted

areas

(e.g., rivers

and oceans

generally releases

to large bodies of water,

assuming

substantial

dilution).

    • Standard

reporting values for surface water

(based

on Standard

Technical

Specifications)

as given in the

WNP-2 Offsite Dose Calculation

Manual

(ODCH).

These

values

were derived

based

on (1)

10 CFR 50, Appendix I

limiting doses

due to liquid effluents,

and (2)

1970 "state-of-the-art"

technology for monitoring and detection capabilities.

NOTE: Reporting is only required

when these

values

are exceeded for all

samples

averaged

over

a calendar quarter.

      • Based primarily on May 13,

1992,

sample of the storm drain pond.

Tritium values

are given over the range

seen in 1992 samples.

In

addition:

I.

The T-2 sump contents

were discharged

to the storm drain on tune

27,

1992, at

a concentration of 460 picocuries/liter (pCi/1).

2.

The T-5 sump contents

were transferred

and discharged to the storm

drain

on Hay 3 and Hay 12,

1992, at

a concentration of 7000 pCi/1.

        • For drinking water,

a more restrictive value of 20,000 pCi/1 is used,

based

on 40

CFR

141

(EPA drinking water standards).