ML17289B002

From kanterella
Jump to navigation Jump to search
Insp Rept 50-397/92-37 on 921005-21.No Violations Noted. Major Areas Inspected:Reviews Issues Identified by NRC Augmented Insp Team Relevant to WNP-2 920815 Core Power Oscillation Event
ML17289B002
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 11/05/1992
From: Johnson P
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML17289B001 List:
References
50-397-92-37, EA-92-206, NUDOCS 9212010147
Download: ML17289B002 (26)


See also: IR 05000397/1992037

Text

U.S.

NUCLEAR REGULATORY COMMISSION

REGION V

Report No:

Docket No:

License

No:

Licensee:

Facil ity Name:

Inspection at:

50-397/92-37

EA 92-206

50-397

NPF-21

Washington Public Power Supply System

P. 0.

Box 968

Richland,

WA 99352

Washington Nuclear Project

No.

2

(WNP-2)

WNP-2'ite near Richland,

Washington

Inspection

Conducted:

October

5 October 21,

1992

Inspectors:

W. P. Ang, Acting Senior Resident

Inspector

D. L. Proulx, Resident

Inspector

Approved by:

~Summar:

P.

H.

nson, Chief

'eacto

ojects Section

1

'/6'(q z

Date Signed

ns ection

on October

5 October

21

1992

50-397 92-37

t d: t

p

l

1 l

p tl

d t

d t

identified by the

NRC Augmented Inspection

Team relevant to the WNP-2, August

15,

1992 cor e power oscillation event.

Inspection

Procedure

92701

was used.

Safet

Issues

Mana ement

S stem

SINS

Items:

None.

results:

General

Conclusions

and

S ecific Findin

s

i 'cant Safet

Matters:

Several significant safety issues

were previously identified in the

Augmented Inspection

Team (AIT) Report.

~

Control rod patterns

resulted

in strongly skewed radial

and axial

flux profiles that caused

the reactor to become unstable while

oper'ating in a stability region where the

BWR Owners'roup

had

9212010147

921105

PDR

ADOCK 05000397

8

PDR

-r,

recommended

additional precautions.

Inadequate

procedures

and

ineffective training resulted in the nonconservative

rod pattern in

place during the event

(paragraphs

3 and 5).

~

The design

and the associated

reviews performed for the Cycles

7 and

8 core reload mixed fuel design did not adequately

evaluate

core

stability and changes to the thermal hydraulic properties of the

core

(paragraph

4).

~

The licensee's

handling of generic correspondence

did not appear to

be adequate

or in compliance with the Technical Specifications,

and

. contributed directly to the concern

above involving strongly skewed

flux profiles (paragraph

6).

Although no safety limits were violated,

and

no fuel damage

occurred,

the in-phase oscillations which were experienced

indicated

a potential

for fuel 'damage.

The core could, under slightly different circumstances,

have experienced

out-of-phase oscillations which might not have

been

detected

and suppressed

before the core exceeded

the Minimum Critical

Power Ratio

(MCPR) safety limit.

The violations identified below involved multiple barriers that failed to

.preclude the event.

There

was minimal evidence of management

oversight

in assuring that

a March 18,

1992,

BWR Owners'roup

(BWROG) letter,

which recommended

additional precautions

regarding

power oscillations,

was appropriately reviewed.

Weakness

in management

oversight

was also

evident in inadequate

procedures.

This lack of management

oversight

appears to have

been the primary reason for the licensee's

failure to

preclude the event.

Summar

of Violations and Deviations:

Five apparent violations and

one

deviation were identified during this inspection,

as follows:

~

The licensee failed to provide adequate

procedures for developing

control rod patterns,

in that the procedures

in place provide'd

=inadequate direction to prevent

power oscillations

(paragraph 3).

~

The licensee's

Nuclear Safety Assurance

Group

(NSAG) did not proper-

ly review and provide recommended

corrective actions for the

BWROG

letter of March 18,

1992,

as required

by =TS 6.2.3. 1 (paragraph 6).

Core design,

plant procedures,

and operator training were inadequate

at the time of the event to ensure

compliance with 10 CFR 50, Appen-

dix A, General

Design Criterion 12 (paragraphs

4.a, 4.b,

and 5).

The licensee's

application of a mixed core design for the cycle 8

reload core,

and inadequate

analysis

and evaluation of related

changes

in thermal

and hydraulic properties of the design,

did not

receive

an adequate

design review (paragraph 4.c).

Operators .failed to adjust Average

Power

Range Monitor (APRM), flow-

biased

scram

and rod block setpoints

as required

by TS 3.2.2

(paragraph

7.a).

~

The Supply System did not fulfillits commitment,

made in support of

Technical Specifications

Amendment

No. 71, to install

and use the

stability monitor when required

by Technical Specifications.

The

monitor had

been ineffective since its initial installation due to a

0.3

Hz filter installed

on its inputs which had not been appro-

priately considered

(paragraph 7.b).

Pe sons Contacted

A. L. Oxsen, Acting Managing Director

  • J. V. Parrish,

Assistant

Managing Director, Operations

  • J.

W. Baker,

WNP-2 Plant Manager

  • C. H. Powers, Director, Engineering

J.

C. Gearhart,

Director, guality Assurance

  • G. C. Sorensen,

Regulatory

Program Hanager

D. L. Larkin, Engineering Services

Manager

  • D. L. Whitcomb, Nuclear Engineering

Manager

. L. T. Harrold, Assistant Plant Manager

W. D. Shaeffer,

Operations

Manager

  • R. L. Webring, Technical

Hanager

  • L. L. Grumme,

Manager,

Nuclear Safety Assurance

S. L. Washington,

Manager,

Nuclear Safety Engineering

J.

E. Rhoads,

Manager,

Operations

Event Analysis and Resolution

  • D. K. Atkinson, Reactor

Systems

Supervisor

R. H. Torres, Principal Engineer,

Reactor Engineering

  • J. J. Huth, Engineer,

Operations

Event Analysis

and Resolution

  • H. P. Reis,

Compliance Engineer

onneville Power Admi istration

BPA

A. J.

Rapacz,

Project Representative

~D. L. Williams, Nuclear Engineer

.The inspectors

also interviewed various control

room operators; shift

supervisors

and shift managers;

and maintenance,

engineering,

quality

assurance,

and management

personnel.

  • Attended the Exit Meeting on October 21,

1992.

Back round

On March 9,

1988,

La Salle Unit 2 experienced

core power oscillations

due

to a dual recirculation

pump trip.

This event resulted in increased

concern

on the part of the Boiling Water Reactor

Owners

Group

(BWROG) and

the

NRC regarding core stability.

- On June

15,

1988 the

NRC issued

Bulletin 88-07 to advise licensees

regarding possible

core instability

and to require licensee

action to provide training and procedure

changes

to preclude

and mitigate the consequences

of a core oscillation event.

On December 30,

1988,

NRC Bulletin (NRCB) 88-07,

Supplement

1, (Sl) was

issued to provide additional information concerning

power oscillations in

BWRs and to request that licensees

take action to ensure that the safety

limit for the reactor's

minimum critical power ratio

(MCPR) w'ould not be

violated.

One of the actions

requested

by NRCB 88-07 Sl was that "For

propose'd

new fuel designs,

the stability boundaries

should

be reevaluated

and justified based

on any applicable operating experience,

calculated

changes

in core decay ratio using

NRC approved methodology,

and/or core

decay ratio measurements."

On March 3,

1989 the Supply System responded

to

NRCB 88-07 Sl.

This

response

stated that

a proposed

Technical Specification

(TS) change

would

be submitted to further define the stability exclusion boundaries

and to

"Adopt a stronger stability monitoring capability,

namely use of the

ANNA

Stability Monitoring System."

On March 31,

1989; the Supply System

submitted

a TS amendment

request

(in support of cycle 5),

which stated

that "For future cycles in which decay ratio values of 0.9 or greater

are

calculated for points below the

100X rodline, the allowable region will

be modified accordingly."

In early 1991,

a European

BWR experienced

unexpected

regional oscilla-

tions when the operators

thought they were not.in the region of potential

instability as defined

on their power to flow map.

The

BWROG used the

data obtained

from this and other industry events to develop additional

strategies

for prevention of core'instabilities.

On March 18,

1992, the

BWROG issued

a letter whose subject

was "Implementation Guidance for

Stability Interim Corrective Actions" which amplified guidance

contained

in NRCB 88-07 SI.

The

BWROG provided implementation

guidance for

application to procedures

and training programs related to

NRCB 88-07 Sl

to minimize the potential for encountering oscillations.

Attachment

1 to

the letter stated that under

some conditions it might be possible to

violate the

MCPR safety limit during

a regional oscillation while the

APRH signal is oscillating at less than

10X peak-to-peak of scale.

It

further stated that

a regional oscillation of this magnitude

could be

easily recognized

on the local power range monitors

(LPRMs), but might

not always result in LPRH high or downscale

alarms.

Such

a regional

oscillation would also

be apparent

on the average

power range monitors

(APRMs) if they are monitored carefully.

In recognition of the exclusion region uncertainties,

the

BWROG letter

recommended that operator training and retraining programs

encourage

caution when operating

near the region (within 'Approximately 5X in power

and in flow rod line ), minimizing the amount of time spent operating

near the stability exclusion region.

Attachment

1 of the

BWROG letter

stated that:

"BWR stability is influenced

by several

power distribution and

operating state variables that change during normal operation

and

from cycle to cycle.

In particular, the radial

and axial power

distributions

and core inlet subcooling

have

a strong impact on

stability.

Advances in fuel and reload designs

have generally

resulted

in higher fuel bundle

power levels (higher radial peaking

on the average)

over the last

10 years,

which makes

an oscillation

somewhat

more likely today than previously.

The higher bundle power

levels,

which increase

the neutronic efficiency of the reactor,

have

lessened

the stability differences

between

high and lower power

density reactors.

This is because

the lower power density reactors

generally

have more margin to nuclear limits and can therefor e

increase

peaking

more than the higher power density reactors."

The March 18,

1992

BWROG guidance

was received

by the Supply System,

but

there

was

no documented

record of receipt

and processing of the letter.

Training of operators

and shift technical

advisors

(STAs) regarding the

contents of the

BWROG guidance

was performed in May 1992.

0

The WNP-2 cycle 8 core,

a mixed core design of 8x8 and 9x9-9x Siemens

Nuclear

Power

(SNP) Corporation fuel, was loaded during the 7th refueling

outage.

On July 4,

1992, the

WNP-2 cycle 8 core attained initial"

criticality and proceeded

to 100X power.

A subsequent

valve leak inside

the drywell necessitated

a power reduction to

SX power to repair the

valve 'on August 13,

1992.

After the valve was backseated

and the leakage

eliminated,

power ascension

of the reactor

was resumed

on August 14,

1992.

With the reactor at 36.4X power and total core flow at 30.5X, the

reactor operator

prepared to shift the recirculation

pumps to fast speed

by closing the "A" recirculation loop flow control valve.

Power

decreased

to 33.5X and total core flow decreased

to 26.0X,

as expected.

However, reactor

power oscillations started

as the recirculation flow

control valve

(FCV) was closing, at about 2:58 a.m.

on August 15,

1992.

The oscillations were observed

by the operators

and terminated

by a

manual reactor

scram.

The

NRC dispatched

an Augmented Inspection

Team

(AIT) to WNP-2 to assess

licensee

actions

and identify equipment

failures,

human performance errors,

procedure deficiencies,

and quality

assurance

deficiencies that

may have contributed to the event.

Inspection report (IR) 50-397/92-30

documented

the results of the AIT

inspection.

The AIT found no evidence of fuel failure or violation of

fuel safety limits due to the power oscillation.

However, the AIT

identified numerous

issues

associated

with the event.

This special

inspection

was performed to follow up on the issues

identified by the AIT in IR 50-397/92-30

and to determine

the licensee's

. compliance with regulatory requirements

relevant to those issues.

A

review of IR 50-397/92-30 identified the principal issues

which are

discussed

below.

These

issues

were discussed

with licensee

personnel,

and associated

procedures

and records

were reviewed.

Control of Core Power Distribution

The AIT report stated that the August

15 instability event

was caused

by

the control rod pattern selected.

This included all shaper

rods with-

drawn,

and four primary control rods in the core center region withdrawn

to step

28, resulting in a region of high power density in the center of

the core.

This resulted in a decay ratio

(DR) of 1.05,

whereas

a more

conservative

rod pattern could .have resulted in a

DR =as low as 0.3.

A review of plant procedures

was performed to determine

procedure

adequacy

and procedure

compliance leading

up to the August 15,

1992

oscillation event.

Plant Procedures

Manual

(PPH) Procedure

9.3.9,

Revision 8, Control

Rod Withdrawal Sequence

Development

and Control,

and

PPH 9.3.12,

Revision 6, Plant

Power Haneuvering,

were the principal

procedures

that provided the requirements for control rod pattern.

As noted in the AIT report,

PPH 9.3.12 provided several

cautions which,

if followed, would have reduced

the probability of core oscillations.

These cautions

included:

(1)

a recommendation

to flatten radial peaking,

(2) maintaining

a strong bottom peak (while noting that too large

a

bottom peak could prevent the opening of flow control valves after the

recirculation

pumps were shifted to fast speed),

(3) not being overly

aggressive

when pulling shaper rods, with a peaking 'factor of 3.4 as

an

optimum value (considering recirculation

pump vibration and fuel

preconditioning limits), and (4) minimizing the time spent with the

pumps

at slow speed

when establishing

control rod pattern following a power

reduction

(due to concerns for xenon burnup after the power increase).

However,

because

the procedures

did not provide sufficient direction or

criteria for their use,

licensee

personnel

directing the establishment

of

the control rod pattern

on August 15,

1992 did not implement these

cautions;-

Due to the control rod pattern selected,

the radial

and axial

power distribution at the time of pump shift were very skewed

(1.92

radial peaking factor and up to 1.76 axial peaking factor)

and all shaper

rods had been withdrawn at the time of the event.

10 CFR 50, Appendix B, Criterion

V requires that procedures

include

appropriate quantitative or qualitative acceptance

criteria for deter-

mining that important activities have

been satisfactorily, accomplished.

PPN 9.3.12

and 9.3.9 provided qualitative guidance without quantitative

limits.

Inadequate

procedure

guidance or acceptance

criteria was evident

in several

instances,

including the following:

~

Plant Procedures

Manual

(PPM) procedure 9.3.12,

Revision 6, Plant

Power Maneuvering,

paragraph

7. 1.4, Performing

a Rod Set,

subpara-

graph b, Principles

and Objectives,

required that the radial peaking

be flattened in selecting

a control rod pattern for the final rod

pattern but did not provide quantitative limits for the peaking

factors.

~

PPM 9.3.12,

Revision 6, paragraph 7.1.5.c,

Power Distribution Con-

straints,

required that care

be taken to prevent excessive

peaking,

but did not provide quantitative limits for "excessive"

peaking.

~

PPM 9.3.12, Revision 6, paragraph 7.1.5.c,

stated that establishing

too large

a bottea peak will prevent opening of the flow control

valves to 20,000

and 24,000

GPM respectively following the shift to

60 Hz, due to preconditioning limits, but provided no quantitative

limits for the peaking factors.

~

- PPM 9.3. 12, Revision 6, paragraph

7.1.5.d,

stated that care should

be taken to prevent the occurrence of excessive

peaking but did not

provide quantitative limits for the peaking factor s.

PPM 9.3. 12, Revision 6, paragraphs

7. 1.5.d

and 7. 1.5.e,

also

required that the operator not be "overly aggressive"

when pulling

shaper

rods

and that the time spent using slow speed recirculation

pumps

be minimized when performing

a rod set following a reduction

in power or prior to the second

ramp in a startup.

However, the

procedure

did not provide quantitative

acceptance criteria for the

rate of pulling shaper

rods or for the time spent using slow speed

recirculation

pumps for the noted conditions.

PPM 9.3. 12, paragraph

7.1.5.e,

stated that the more time spent at

low power, the more fierce the xenon burn will be following power

increase.

However, the procedure did not provide qua'ntitative

limits for the time spent at low power,

or quantify the "fierce

xenon burn."

0-

0

-

The lack of specific requirements for reactor

power distribution parame-

ters,

as discussed

above,

allowed the STA/Station Nuclear

Engineer

(SNE)

to implement

an unstable control rod withdrawal pattern that generated

the very high peaking factors.

PPH 9.3.9

and

PPH 9.3.12 did not provide

appropriate qualitative or quantitative acceptance

criteria for power

distribution parameters.

This is an apparent violation of 10 CFR 50,

Appendix B, Criterion

V (397/92-37-01).

PPH 9.3.12 allowed deviations

from the rod withdrawal

sequence after

reactor

power exceeded

20X; the SNE's freedom to make such deviations

was

considered

necessary

by the licensee to account for various power and

'core considerations.

Deviations from the approved

sequence

above

20X

power were

a common practice, with rod pulls based

on calculations

by the

STA/SNE.

This practice resulted in large variations in core stability

during several

startups,

due to excessively

peaked

power distributions

resulting from the various rod patterns

selected

by the STA/SNE.

There

were

no administrative controls requiring peer

review of the SNE's

changes

to prescribed control rod order sheets.

PPH 1.3. 1 specified that

the responsibility of the Control

Room Supervisor

(CRS)

was to ensure,

among other things,

a conservative

approach to operations

involving core

reactivity changes.

For the August 15,

1992 event, there

was

no operator

review of STA/SNE changes

to the prescribed

control rod withdrawal

sequence.

Prior to the event,

the control rod sequence

used

by the crew

caused

very high neutron flux peaking

and did not conform to guidance

provided by the licensee's

procedures.

The lack of (1) instructions or

procedures

to control deviations

from the approved

rod withdrawal se-

quence

above

20X power,

and (2),requirements

for peer review of the SNE's

changes to prescribed control rod order sheets

(to ensure

a conservative

approach to operations

involving core reactivity changes)

is an apparent

violation of 10 CFR 50, Appendix B, Criterion V, and was identified as

another

example of the previously mentioned

procedure violation.

4.,

Core Desi

The AIT report stated that the core design

had contributed to the

observed

power oscillations,

in that the

WNP-2 Cycle 8 core was

a mixed

core design with unbalanced

flow characteristics.

This resulted in,the

relatively low-power, low resistance

8x8 bundles starving reactor coolant

flow from the high-power

and high resistance

9x9-9x bundles.

For the

operating conditions that existed during the 8/15 power oscillation

event,

the

DR would have

been

20X lower for a full 8x8 core

and

10X lower

for a full 9x9-9x core.

10 CFR 50, Appendix A, General

Design Criterion 12, states

that "The

reactor core

and associated

coolant, control,

and protection

systems

shall

be designed to assure that power oscillations which can result in

conditions exceeding

specified acceptable

fuel design limits are not

possible or can

be reliably and readily detected

and suppressed."

a.

Susce tibilit of BWRs to Power Oscillations

Which Can Result

'n

Conditions

Exceedin

S ecified Acce table

Fuel

Desi

n Lim'ts

As previously noted in paragraph

2 of this report, the

NRC issued

.

NRCB 88-07 because

of concerns

regarding core stability and power

oscillations in BMRs.

NRCB 88-07 Sl recognized that power oscil-

lations that can result in violations of the Hinimum Critic'al

Power

Ratio safety limit were possible in BWRs.

A June

1989

GE report

(NEDO-31708) concerning fuel thermal

margin during core thermal

hydraulic oscillations in a

BWR, stated that the possibility of

violating the safety limit HCPR does exist for sufficiently large

oscillation magnitudes.

The Harch 18,

1992

BWROG letter, Attach-

ment 1,

Paragraph

1.b, stated:

"... under

some conditions it may be possible to violate

the

HCPR Safety Limit during

a regional oscillation while

the

APRH signal is oscillating at less

than

10X peak-to-

peak of scale.

A regional oscillation of this magnitude

would be easily recognized

on the

LPRHs, but may not

.

always result in LPRH High or Downscale

alarms.

Such

a

regional oscillation would also

be apparent

on the

APRHs

if they are monitored carefully."

As a result of the generic concern regarding

power oscillation that

could result in conditions that violate the

HCPR safety limit, the

BWROG provided "Interim Recommendations

for Stability Actions" and

NRCB 88-07 Sl requested

BWR licensees

to implement the

BWROG

recommendations.

In addition,

NRCB 88-07 Sl stated that for new

fuel designs,

the stability boundaries

should

be reevaluated

and

justified based

on calculated

changes

in core decay ratio using

NRC

approved

methodology,

decay ratio measurements,

or applicable

operating experience.

Furthermore,

the March 18,

1992

BWROG letter

cautioned that radial

and axial power distributions

and core inlet

subcooling

had

a strong

impact

on core stability. It further

cautioned that fuel and reload designs

had resulted in higher fuel

bundle power levels,

making oscillations more likely.

The above

paragraphs

establish that

BWRs can experience

power oscillations

that can violate IKPR safety limits.

They further establish that

new core designs,

such

as the

WNP-2 cycle 8 Bx8 and 9x9-9x mixed

fuel loading required further review for core stability and further

consideration of precautions

that may be necessary

to provide for

possible instability.

The AIT report stated that "AIT LAPUR calculations

also indicated

that the out-of-phase

mode of instability did not have

much margin

to instability. If the

LAPUR calculations

had

been performed before

the event,

they would have

shown that the instability could have

been either in-phase or out-of-phase with almost equal probability."

The WNP-2 Cycle 8 core experienced

in-phase

power oscillations

on

August 15,

1992 while power

was between

36.4X and 33.5X,

and core

flow was between

30.5X and 26.0X.

This was below the region of

, concern defined in TS 3.2.6

(Region A) and below the stability

monitoring area

above the 80X rodline and less than

45X total core

flow, as defined in the bases for TS 3.2.7.

R

Based

on the above paragraphs,

the inspectors

concluded that the

MNP-2 Cycle 8 core could have experienced

in-phase or out-of-phase

power oscillations.

Although no safety limits were violated on

August 15,

1992, it is possible that power oscillations could result

in conditions which exceed specified acceptable

fuel design limits.

Consequently, it was important that adequate

procedures

and training

exist to enable the licensee's staff to be able to reliably and

readily detect

and suppress

power oscillations,

both in-phase

and

out-of-phase.

Since

such oscillations could occur below the 80 per-

cent rodline and outside the

TS defined stability exclusion zone, it

was important that the procedures

and training be adequate

to allow

them to readily detect

and suppress

power oscillations in this area.

ead

and Reliable Detect

on

a

d Su

ression of BWR Power

Oscillations

Recognizing that power oscillations were possible in BWRs,

GE, the

BWROG and the

NRC performed

numerous

studies

and reviews

and issued

various advisories

and recommendations

to provide for ready

and-

reliable detection

and suppression

of power oscillations.

A

November

1988

BWROG letter provided interim recommendations

for

stability actions that defined power/flow operating regions for core

stability and

recommended

actions for entry into the stability

exclusion region.

NRCB 8807 Sl requested

BWR licensees

to implement

those

recommendations,

and emphasized

the need for unambiguous

pro-

cedures

and training for implementation of those recommendations.

In March 1992, the

BWROG provided further guidance

on the implemen-

tation of the stability interim corrective actions

based

on lessons

learned

.from recent operating experience.

The March 18,

1992

BWROG

letter provided several

recoaeendations

for prevention,

detection

and suppression

of power oscillations.

The letter emphasized

the

need for procedures

and training to implement the recommendations

for ready detection

and suppression

of power oscillations.

As noted previously, the

WNP-2 cycle 8 core had

an approximately

equal probability of in-phase or out-of-phase

power oscillations for

the August 15,

1992 operating conditions.

GE provided further

information regarding the difficulties of recognizing out of phase

power oscillations in NEDO 31708

as follows:

"During a regional oscillation, since

one half of the core

is oscillating

180 degrees

out of phase with the other

half, there is significant cancellation

in the

APRM signal

which is a simple average of approximately

15-20 local

power range monitors

(LPRH) distributed throughout the

core.

Because

the magnitude of the local neutron fluxes

is not completely represented

in the

APRM signal,

the

oscillation magnitudes

may be larger compared to a core-

wide oscillation before operator action or automatic

mitigation occurs.

Although previous studies

have

demonstrated. that very large magnitude neutron flux oscil-

lations are required to challenge

the safety limit HCPR

(Reference

1 and 2), the relationship

between local

oscillation magnitudes

and

LPRH and

APRM signals

has not

been established."

As noted

above,

APRH signals

can not reliably detect regional

(or

out-of-phase)

core oscillations.

Reliance

on

LPRH upscale

and

downscale

alarms,

and the procedures

and training relevant to

recognition of core oscillation based

upon those alarms,

would not

have provided ready

and reliable detection

and suppression

of out-

of-phase oscillations.

Annunciator

response

procedure

4.603:48,

Revision 2, for windows 2-5

and 5-6, specified operator actions in response

to LPRH upscale

and

downscale

alarms.

The annunciator

response

procedures

did not

mention the possibility of core oscillations,

and did not require

a

manual reactor trip for core oscillations,

but did require that the

STA be informed of those alarms.

Plant procedures

therefore did not

appear to provide adequate

instructions for ready

and reliable

detection of out of phase

power oscillations.

As previously noted,

the

WNP-2 August 15,

1992 power oscillation

event occurred with power/flow operating conditions that were below

the 80 percent rodline.

PPH 4;12.4.7,

Revision 6, Unintentional

Entry into Region of Potential

Core Power Instabilities, did require

a manual scram for periodic

LPRH upscale or downscale

alarms that

appear

on the full core display, or any

LPRH having oscillations

greater

than

20 watts/cm'.

However, the procedure did not apply

below the 80X rodline and with core flow greater

than 45X.

Plant

procedures

therefore did not appear to provide adequate

instructions

for ready

and reliable detection of out of phase

power oscillations

with operating conditions below the 80 percent rodline.

Further-

more, plant procedures

did not appear to provide adequate

instruc-

tions for suppression

of power oscillations that could occur below

the 80 percent rodline since

PPH 4.12.4.7 Revision

6 did not apply

when operating conditions were below the 80 percent rodline.

Ade uac

of

icensee

Review o

WNP-

C cles

7 and 8 Co e

esi

ns

The March 18,

1992

BWROG guidance discussed

the uncertainties

associated

with the definition of the stability "exclusion region"

and emphasized

the need for closer monitoring of the

LPRH signals

while operating in areas

near ("approximately

5X in power and in

flow control line") the exclusion region.

The letter also provided

guidance for suppression

of core power oscillations

upon

recognition.

WNP-2 licensed operators

and

SNE/STAs

had been trained

on the

BWROG guidance,

but the training was ineffective (see

paragraph

5 of this IR for additional details).

The August 15,

1992

WNP-2 core power oscillation was readily detected,

and was

effectively suppressed

when the control

room operator

(CRO) manually

scrammed

the plant.

However,

a number of procedure

and training

inadequacies

existed,

as discussed

above

and in other sections of

this report, that minimized the reliability of detection

and

suppression

of regional or out-of-phase oscillations in the

WNP-2

Cycle 8 core.

The design

and operation of the WNP-2.Cycle 8 core

appear to have violated

10 CFR 50, Appendix A, General

Design

Criterion

(GDC)

12 (50-397/92-37-02).

The AIT report further stated that the Cycle

7 WNP-2 calculated

stability decay ratios were not provided to

NRC in the cycle

7

licensing submittal.

The reduced stability margin (decay ratio

greater

than 0.75) which was calculated

by SNP for Cycles

7 and

8

0

resulted

in operation with reduced

thermal

margin during power

oscillations

(the critical power r'atio

(CPR) operating limit was

exceeded

during the 8/15/92 event).

The licensing bases

assumed

that

a design basis

accident

would not be initiated from a condition

which exceeded

the

CPR operating limit.

The Supply System

and

SNP

accepted

the reduced stability margin for Cycles

7 and 8 without

adequately

reviewing the possibility of a design basis

accident

(DBA) being initiated during a period of reduced stability margins

and potentially reduced

CPR.

The licensee

performed

a 10 CFR 50.59 evaluation for both the Cycle

7 and Cycle 8 core reloads.

The evaluations

determined that the

core reload. for Cycles

7 and 8 did not: (1) increase

the probability

of occurrence of an accident evaluated previously in the licensing

basis

document,

(2) increase

the consequences

of an accident

previously evaluated,

(3) increase

the probability of occurrence of

malfunction of equipment,

or the consequences

of the malfunction of

that equipment,

(4) create the possibility of a different type of

accident,

or different type of malfunction of equipment,

or (5)

reduce the margin of safety

as defined in the basis for any TS.

The licensee's

basis for the

10 CFR 50.59 evaluations

was the Core

Operating Limits Report

(COLR), the supporting

analyses

and reports

performed

by the licensee

and

SNP,

and the licensee's

review of

those reports.

The Reload Analysis Reports

(RARs) for both cycles

were supporting reports for the

COLRs.

The

RARs evaluated

core

hydrodynamic stability, and determined that the decay ratios

(DRs)

for both reloads

were within acceptable limits.

The

DRs were

determined for three

power and flow data points within the TS

defined exclusion region

and were determined for the end-of-cycle

(EOC)

and all rods out conditions.

The DRs were determined

using

the

NRC approved computer

code called

COTRAN.

The August 15,

1992

WNP.-2 Cycle 8 core oscillation demonstrated

that

oscillations could occur outside the exclusion region

and that the

RAR evaluation

was not sufficiently thorough nor conservative.

The

AIT report noted that staff analyses

and

SNP hydraulic stability

evaluations after the August 15,

1992 event indicated the 9x9-9x

fuel design to be less stable than other fuels in US BWRs.

The AIT

. report stated that for the operating conditions at the time of the

August

15 oscillations,

the AIT calculated

a core-wide

DR of 1.05,

a

hot channel

DR of 0.83,

and

an out-of-phase

DR of 1.0.

The

RAR, the

COLR and the

10 CFR 50.59 evaluations for the Cycles

7 and

8 reloads

were therefore not conservative.

The

10 CFR 50.59 evaluations for

the Cycle

7 and 8 reloads

appeared

to be inadequate

in that they did

not sufficiently consider the changes

in thermal hydraulic charac-

teristics of the reload cores

and did not appropriately evaluate

their effect on or possible

changes

to the various conditions

analyzed

pursuant to 10 CFR 50.59,

'as noted at the beginning of this

paragraph.

'This was identified as

a potential violation of 10 CFR 50,-. Appendix B, Criterion III (50-397/92-37-03).

As noted

above,

the NRC-approved

computer

code for WNP-2 stability

evaluations

is

COTRAN.

As also noted

above,

the

COTRAN code

may not

0

-10-

necessarily

provide conservative results,

and the methodology for

assessing

core stability by evaluating three points within the TS-

defined exclusion boundary

may not be conservative.

The AIT report

noted that;SNP

was considering submitting for review arid approval

its core stability analysis

computer

code ca'lied STAIF.

The

. licensee

indicated that other computer

codes we'e also available

and

were being considered.

Pending further licensee

and

NRC review of

the methodology

and computer code used for core stability evalua-

tions, this was identified as

an Unresolved

Item (50-397/92-37-04).

+gn~i

As noted previously,

r'eady

and reliable detection

and suppression

of

power oscillations

depended

heavily on good procedures

and training.

As

'reviously discussed,

procedures for the detection

and suppression

of

power oscillations were not adequate.

Training for detection

and

'uppression

of power oscillations

was also insufficient.

The AIT report noted that

a licensee Training Department

lesson

plan for

STA training, Reactivity Mismanagement

Events, that included information

from the March 18,1992

BWROG letter,

was issued

on May 27,

1992.

How-

ever, the training attendance

record for the

STA on shift during the

event indicated that he had attended

the training for the subject lesson

plan on May 7, 1992, before it was approved

on May 27,

1992.

The AIT

report stated that all operators

on shift during the event

had attended

requalification training that included training on instability events.

However,

none of the licensed operators

who were on shift during the

event

and

who were subsequently

interviewed by the team could recall

having attended training that addressed

the March 18,

1992

BWROG letter

.nor any of the specific guidance from the letter.

The AIT report further

stated that operators

interviewed considered that the area of core

instability was well defined

and that there

was

no possibility of the

reactor

becoming unstable

outside the TS-defined exclusion area.

As noted in previous sections of this report, operating

procedures

did

not incorporate the guidance

contained in the March 18,

1992

BWROG let-

ter.

The training'rovided to the

STAs and licensed operators

included

the guidance

contained in the

BWROG- letter, but was not consistent with

applicable operating procedures.

The inspectors

noted that

some aspects

of the training could have

been followed without violating existing

procedures

(e.g.,

using extra caution

when operating

near the stability

exclusion region by turning on the stability monitor prior to the time

required

by the procedures).

However, the training was inadequate

because

other aspects

could not and should not have

been followed without

procedural

changes

(e.g.,

power/flow conditions for changing recirc

pump

speed).

As noted in previous sections of this report, the rod pattern

and operating conditions at the time of the event differed from the

guidance

provided by the

BWROG letter.

WNP-2 TS 6.4. 1 states

that

a retraining

and replacement

training program

shall

be maintained for the plant staff and shall include familiarization

with relevant industry operational

experience.

Training on the March 18,

1992

BWROG letter was performed.

However, the training appeared

to be

ineffective and inadequate

in that it was not based

on existing operating

0

~

~

4

-11-

procedures

and none of the

on shift operators

interviewed could recall

the training having been provided.

The inadequate

and ineffective

training provided

on the industry operational

experience

and guidance

communicated

by the March 18,

1992

BWROG letter is addressed

as part of

the apparent violation of 10 CFR 50, Appendix A,

GDC 12 (paragraphs

4.a

and 4.b).

andlin

of Generic

Commu 'tio s

The AIT report

and the previous section of this report noted that the

March 18,

1992

BWROG letter provided significant guidance

and industry

advice that most likely would have precluded the occurrence of the WNP-2

oscillation event

had the guidance

been followed.

-The licensee

was

on

distribution for the March 18,

1992

BWROG letter as follows:

~

The letter was addressed

to the

BWROG Executive Committee.

The

WPPSS Deputy Managing Director is a aember of the

BWROG Executive

Committee.

~

The letter was addressed

to the

B'WROG Primary Representatives.

A

WPPSS Licensing Department

engineer is the

WPPSS

BWROG Primary

Representative.

~

Members of the Stability Committee

and Reactivity Controls Committee

were sent copies of the letter.

Six WPPSS representatives,

from the

licensing, technical staff and Nuclear Engineering organizations,

were members of those

committees.-

~

The fuel vendor,

SNP,

was sent

a copy of the letter .

As noted in the AIT report, the fuel vendor,

SNP,

acknowledged receipt of

the letter but had no documented

record of when it was received.

Discus-

sions with management

personnel of the

SNP fuel design group indicated

that they were not aware of the letter.

Further discussion with the fuel

vendor indicated that,

based

upon

a review of the letter after the event,

the fuel vendor

had no additional actions to be performed

as

a result of

'he

letter.

The adequacy of the fuel vendor's

handling of the letter

will be referred to the

NRC Vendor Inspection

Branch for further

evaluation.

The Supply System received the

BWROG letter, but no documented

record

existed to determine

when the letter was received.

The only available

evidence of any action taken

by the licensee

regarding the letter was the

May 27,

1992

STA training lesson

plan and the operator requalification

program that included tt aining regarding information contained

in the

letter.

As previously noted,

operating

procedures

were not changed,

the

training performed

was ineffective,

and. no documented

action was taken

by

the Nuclear

Engineering

Department relevant to specific provisions of the

letter.

WNP-2 TS 6.2.3. 1 states

that the Nuclear Safety Assurance

Group

(NSAG)

shall function -to examine industry advisories

and shall

make. detailed

recommendations

for revised procedures,

operations activities, or other

means of improving unit safety to the Director of Licensing

and

-12-

Assurance.

PPM 1. 10.4, Revision 9, External Operating

Experience

Review,

provides the requirements

for the

WNP-2 External Operating

Experience

.

Review Program.

This procedure listed various sources of operational

experience

data.

However, the procedure

was inadequate

in that it did

not include

a requirement for the review and processing of BWROG

information.

The TS 6.2.3. 1 requirements

did not appear to have

been

complied with in that

NSAG had no documented

record of receipt of the

March 18,

1992

BWROG letter, despite its multiple distribution to Supply

System personnel;

no review was performed;

and

no recommendations

relevant to it were provided.

This was identified as

an apparent

violation of TS 6.2.3. 1 (50-397/92-37-05).

7.

~Dt

a ~

d 'tment of

R

l w

iased

Set o'nts

Technical Specification 3.2.2 states that "The APRH flow biased

simulated thermal

power-upscale

scram trip setpoint

(S)

and flow

biased

neutron flux-upscale control rod block trip setpoint

(Srb)

shall

be established

according to the following relationships:

Tri

Set oint

S < (0.66W + 51X)T

Srb < (0.66W + 42X)T

llowable Value

S

< (0.66W. + 54X)T

Srb < (0.66W + 45X)T

where:

S and Srb are in percent of RATED THERMAL POWER.

W

Loop recirculation flow as

a percentage

of loop

recirculation flow which produces

a rated core flow

of 108.5 million lbs/hr.

T

Lowest value of the ratio of FRACTION OF RATED

THERMAL POWER divided by the

MAXIMUM FRACTION OF

LIMITING POWER DENSITY.

T is always less than or

equal to 1."

This TS was applicable

when reactor

power was greater than or equal

to 25X.

No exception for TS 3.0.4 or 4.0.4 was in effect during the

period of the event.

The action statement for TS 3.2.2 states that "With the

APRH flow

biased

simulated thermal

power-upscale

scram trip setpoint and/or

the flow biased neutron flux-upscale control rod block trip setpoint

less conservative

than the value

shown in the Allowable Value column

for S or Srb,

as

above determined, initiate corrective action within

15 minutes

and adjust

S and/or Srb to be consistent with the Trip

Setpoint value within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> or reduce thermal

power to less than

25X in four hours."

As'n alternative to adjusting the trip settings,

TS 3.2.2 allowed

the licensee to increase

the gain of the

APRHs so that the

APRMs

would read artificially high by a factor of T (or T-factor).

- 13-

The basis for this

TS states:

"The scram settings

and rod block

settings

are adjusted in accordance

with the formula in this

specification

when the combination of THERNAL POWER and

NFLPD

indicates

a higher peaked

power distribution to ensure that

an

LHGR

[linear'eat generation rate] transient

would not 'be increased

in

the degraded condition."

During a review of data provided by the licensee,

the AIT noted that

the thermal limits printout of 1:53 a.m.

on August 15 indicated that

T was 0.793.

However, the licensee did not perform the flow biased

setpoint adjustments

or APRN gain adjustments

as described

above,

prior to exceeding

25 percent

power and within the prescribed

time

limit.

In addition, the licensee

subsequently

provided five other

thermal limits*printouts, obtained

between

12:53

and 3:00 a.m.

on

August 15,

1992, which also indicated that the adjusted flow biased

setpoints

should

have

been in effect.

The lowest value calculated

,for the T- factor was 0.746, for the printout obtained just prior to

closure of the

A loop recirculation flow control valve.

Technical Specification 4.0.4 states that entry into an operational

condition or other specified applicable condition shall not be made

unless

the surveillance

requirements

associated

with the Limiting

Condition for Operation

have

been performed within the applicable

surveillance interval, or as otherwise specified.

Review of licensee

records indicated that

PPN 7.4.2. 1,

"Power

Distribution Limits" had not been performed

on August

14 or August

15

(PPN 7.4.2. 1 was the licensee's

implementing procedure for

determining margin to the thermal limits, and for adjustment of the

flow biased setpoints

as discussed

above).

The STA stated. that

TS 3.2.2

had always

been interpreted

by the Supply System staff to

allow 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after achieving

25% power for performance of PPN

7.4.2.1.

The STA also stated that although the computer printouts

indicated that the

APRN flow biased setpoints

required adjustment,

this adjustment

could also

be delayed for 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.

The AIT calculated that'the proper scram setpoint

should

have

been

43.6X power,

and the rod block/APRN Upscale

alarm setpoint should

have

been 36.9X.

However, although the maximum peaks of the power

oscillations

(48.75 percent

power maximum on two of the APRNs)

appeared

to exceed the scram setpoints that should

have

been in

effect,

a scram would not have occurred.

The instrumentation for

the flow biased

scram inserts

a six-second

time delay to simulate

the thermal

time constant of the fuel,

and therefore

does not

provide scram protection for a power oscillation event.

However,

the flow biased

rod blocks

and

APRN Upscale

alarms

do not have

a

time delay.

These trips apparently

would have

been received earlier

in the event if the setpoints

had

been lowered, providing the

operators

with earlier information to diagnose

the onset of power

oscillations.

In addition, the operators

may not have increased

reactor

power to 36.4 percent,

due to the close proximity to the rod

block trip point.

The AIT concluded that the licensee did not appear to have complied

with Technical Specification 3.2.2.,

but had not bypassed

a required

scram.

The AIT also concluded that the flow biased

rod blocks

and

APRH Upscale

alarms would have

been received

eat lier in the event

had the setpoints

been lowered, providing th'e operators with earlier

information to diagnose

the onset of power oscillations.

The

licensee's

failure to lower the

APRN flow biased

scram,

rod block,

and

APRH Upscale alarm setpoints

before exceeding

25X power is an

apparent violation of TS 4.0.4

and 3.2.2 (50-397/92-37-06).

The AIT report noted that Surveillance

Procedure

7.4.2.7.3 did not

account for the 0.3

Hz filter installed in the

LPRM inputs to the

stability monitor nor for the

SNP evaluation

and subsequent

change

to the Advanced Neutron Noise Analysis

(ANNA) monitor alarm that was

necessitated

by the filter.

The 0.3 Hz filter caused

a significant

error of the decay ratio displayed

by the

ANNA stability monitor and

would not have been fully effective for TS required stability

monitoring had NNP-2 been previously in the

TS defined region of

instability.

On March 31,

1989, the Supply System requested

an

amendment to TS

3/4.2.7, Stability Honitoring, to redefine the

TS Region

C stability

monitoring zone

on the basis of the installation of ANNA.

The

Supply System stated that

ANNA provided

a stronger, faster,

more

sophisticated

means of monitoring the stability of the core.

Based

on the coamitment to install

and use

ANNA in accordance

with the TS,

the

NRC approved

TS amendment

no.

71

on June

23,

1989.

ANNA was

installed

and tested at

WNP-2 in March of 1989 and modified and

tested

in February of 1990.

As noted in the AIT report, the testing

of ANNA and the procedures for use of ANNA did not recognize the 0.3

Hz filters installed between

ANNA and the

LPRN inputs to ANNA.

The

0.3 Hz filters rendered

ANNA ineffective.

This appears

to be

a

Deviation from a commitment to install

and

use

ANNA in accordance

with the TS, in support of a TS amendment

request.

This was

identified as

a potential deviation (50-397/92-37-07).

8.

~C

This special

inspection

reviewed the issues identified by the AIT, along

with the applicable licensee

procedures

and records.

The issues

were

discussed

with the licensee.

Previous sections of this report identified

five apparent violations, which were also communicated to the licensee.

Numerous

bar riers existed that, if more effective, could have precluded

the WP-2 oscillation event.

Full utilization of industry experience

and

advice,

adequate, operating procedures,

adequate training,

and adequate

design reviews were barriers that could have prevented

the core oscilla-

tions

on August 15,

1992.

In conjunction with the identified violations,

however,

these barriers to preclude the occurrence

of the event failed.

The control

room operators

mitigated the consequences

of the event

and

terminated it by scramming the plant.

However, this special

inspection

found that management

oversight in relation to the barriers

noted

above

-

0

0

-15-

was conspicuously lacking.

No management

oversight regarding review and

implementation of the

BWROG March 18,

1992 letter was evident.. It

appeared

that licensee

management

was not adequately sensitive to core

stability issues

at WNP-2.

This lack of management sensitivity to core

stability and insufficient management

oversight to preclude the occur-

rence of the event appeared

to be the principal underlying cause of the

barrier failures that led to the oscillation event.

9. ~Ud tt

Unresolved

items are matters

about which more information is required to

determine whether they are acceptable

items, violations, or deviations.

An unresolved

item addressed

during this inspection is discussed

in

paragraph

4.c of this report.

The inspectors

met with licensee

management

representatives

periodically

during the report period to discuss

inspection status,

and

an exit

meeting

was conducted with the indicated personnel

(refer to paragraph

1)

on October 21,

1992.

The scope of the inspection

and the

inspectors'indings,

as noted in this report,

were discussed

with and acknowledged

by the licensee representatives.

The licensee

did not identify as proprietary any of the information

reviewed by or discussed

with the inspectors

during the inspection.

The licensee

stated that

a response

to the AIT report was being prepared,

and that it would address

the concerns

raised

by the AIT report

and the

-potential violations identified during this special

inspection.

The

licensee stated that their response

would be submitted

by October

30,

1992.

A summary of the licensee's

preliminary position on the apparent

violations is as follows:

a.

Inadequate

procedures

(PPM 9.3.9

and 9.3. 12):

the licensee

agreed

that the procedures

were inadequate.

Failure to follow procedures

for rod pattern selection:

the licensee

acknowledged that the

procedures

were inadequate,

but because

the procedures

were

inadequate,

the licensee did not believe that the procedures

were

not followed.

b.

10 CFR 50, Appendix A,

GDC 12, core design violation: it was the

licensee's

opinion that out-of-phase oscillations would not occur

before in-phase oscillations were experienced.

Furthermore,

the

licensee

was of the understanding

that as long as

NRCB 88-07 was

complied with, the generic concerns

regarding core oscillation and

compliance with GDC 12 were addressed.

The licensee

also acknow-

ledged the weaknesses

of the training provided,

but considered that

although the training did not preclude the event, the operators

adequately mitigated it by scramming the plant.

C.

Inadequate

design evaluations for Cycles

7 and

8 core reload design:

the licensee

acknowledged that the stability calculations

performed

were not conservative.

However, the licensee

considered that they

-

-16-

had used the methods for which they were licensed,

and that those

were the best tools available at the time.

d.

Failure of NSAG to formally review and provide recommendations

regarding the

BWROG March 18,

1992 letter:

the licensee

acknow-

ledged that

NSAG did not review the letter but considered that

a

definition of industry advisories

included in the

TS requirement

was

necessary.

e.

Failure to adjust

APRH flow biased

scram

and rod block setpoints

as

required

by TS:

the licensee

agreed with the apparent violation.