ML17286B141
| ML17286B141 | |
| Person / Time | |
|---|---|
| Site: | Columbia |
| Issue date: | 11/15/1991 |
| From: | Eng P Office of Nuclear Reactor Regulation |
| To: | Office of Nuclear Reactor Regulation |
| References | |
| NUDOCS 9111210389 | |
| Download: ML17286B141 (30) | |
Text
gc
~gR RECy 0
4y I
O Iv g Iy IP
()N
+y*~4 UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555 November 15, 1991 Docket No. 50-397 LICENSEE:
FACILITY:
SUBJECT:
Washington Public Power Supply System (WPPSS)
WPPSS Nuclear Project No.
2 (WNP-2)
SUMMARY
OF MEETING WITH WASHINGTON PUBLIC POWER SUPPLY SYSTEM ON OCTOBER 29, 1991$
TO DISCUSS STATUS OF SIMULATOR FACILITY CERTIFICATION On October 29, 1991, members of the NRC staff met with representatives of the Washington Public Power Supply System (the licensee or WPPSS) to discuss the status of the WPPSS Nuclear Project Number 2 (WNP-2) simulator.
The licensee began the meeting by presenting background information regarding its previous request for exemption from the simulation facility certification requirements of 10 CFR 55.45.
The NRC crarited the request for exemption and extended the deadline for certificatiorI of tlIe llNP-2 plant referenced simulator to June 30, 1992.
The request for extension was based on the projected delivery date for the plant referenced simulator by Westinghouse of December 31, 1991.
The licensee stated that it had been informed by the vendor that delivery of the simulator would be further delayed.
The delay is due to difficulties encountered during the development of the boiler model.
The licensee stated that woI'I;ablIe boiler models had been developed by both Singer and Exitech; however, it had not pursued obtaining other models as yet.
The licensee also stated that simulator software architecture had not been proven to simulate plant response on a real time basis.
The licensee stated that Westinghouse was also working on the simulator for Oyster Creek and that GPU Nuclear had also been notified that simulator delivery dates were uncertain.
Although a definitive delivery date for the WNP-2 simulator had not been identified, WPPSS stated that delivery was projected around December 1992.
The licensee also noted that the initial operator licensing exams currently scheduled for August 1992, are required to be conducted on the new plant referenced simulator.
In light of the revised delivery date, the licensee stated that revisions to the operator licensing exam requirements or schedule might be necessary.
The NRC acknowledged the licensee's presentation, suggested that the licensee continue to follow the progress of the simulator vendor closely and requested that it keep the NRC informed of any changes to the simulator schedule.
91li2i0389 9iiii5 PDR ADQCI( 05000397 P
@'ez gag)m
1,I' I
lg II
The licensee stated that it would continue to encourage the vendor and suggested that the NRC visit Westinghouse to witness simulator fabrication.
A list of meeting attendees is provided in Enclosure 1.
A copy of the handout materials provided by the licensee i rovided i En osure 2.
Enclosures:
As stated Patricia L. Eng, Prospect Nanager Project Directorate V
Division of Reactor Projects - III/IV/V Office of Nuclear Reactor Regulation cc w/enclosure:
See next page
- ilj, I
t
'1
Mr. G.
C. Sorensen Washington Public Power Supply System WPPSS Nuclear Project No.
2 (WNP-2)
CC:
Mr. J.
W. Baker WNP-2 Plant Manager.
Washington Public Power Supply System P.O.
Box 968, MD 927M
- Richland, Washington 99352 G.
E.
C. Doupe, Esq.
Washington Public Power Supply System 3000 George Washington Way P. 0.
Box 968, MD 396
- Richland, Washington 99532 Mr. R.
G. Waldo, Chairman Energy Facility Site Evaluation Council Mail Stop PY-11 Olympia, Washington 98504 Mr. Alan G. Hosier, Licensing Manager Washington Public Power Supply System P. 0.
Box 968, MD 956B Richland, Washington 99352 Mr. A. Lee Oxsen, Assistant Managing Director for Operations Washington Public Power Supply System P. 0.
Box 968, MD 1023
- Richland, Washington 99352 Mr. Gary D. Bouchey, Director Licensing and Assurance Washington Public Power Supply System P. 0.
Box 968, MD 280 Richland, Washington 99352 Regional Administrator, Region V
U.S. Nuclear Regulatory Commission 1450 Maria Lane, Suite 210 Walnut Creek, California 94596 Chairman Benton County Board of Commissioners P. 0.
Box 190
- Prosser, Washington 99350-0190 Mr. R.
C. Sorensen U. S. Nuclear Regulatory Commission P. 0.
Box 69
- Richland, Washington 99352 Nicholas S. Reynolds, Esq.
Winston I% Strawn 1400 L Street, N.W.
Washington, D.C.
20005-3502
sp I,
t' I
The licensee stated that it would continue to encourage the vendor and suggested that the NRC visit Westinghouse to witness simulator fabrication.
A list of meeting attendees is provided in Enclosure l.
A copy of the handout materials provided by the licensee is provided in Enclosure 2.
Enclosures:
As stated cc w/enclosure:
See next page DISTRIBUTION mTl NRC 5 Local PDR F. Miraglia J. Partlow B. Boger M. Virgilio C. Thomas PDV r/f T. Quay P.
Eng OGC E. Jordan S.
Shankman WNP-2 SRI N. Hunemuller R. Gallo A. Dromerick ACRS(10)
P.
Johnson (RV)
Qgiinat aigne4 by Patricia L. Eng, Project Manager Project Directorate V
Division of Reactor Projects - III/IV/V Office of Nuclear Reactor Regulation NAME RCe PE tg
- TQuay DATE: 11/)6/91: 11//E/91:
11/5~/91 Document Name:
10/29 WNP2 MEETING
~ %
Al II k
H l'I M
ENCLOSURE 1
WASHINGTON PUBLIC POWER SUPPLY SYSTEM October 29, 1991 MEETING ATTENDEES Nuclear Regulatory Commission C. 0. Thomas, Deputy Director, DLPg R.
M. Gallo, Chief, Operator Licensing Branch N.
K. Hunemuller, Reactor Engineer P. L. Eng, Project Manager Washington Public Power Supply System G.
C. Sorensen,
- Manager, Regulatory Programs J.
P, Burn, Director, Special Projects D.
W. Fraley,
- Manager, Simulator Projects R.
B. Bartmettlor, Manager, Nuclear License Training
1 lj
WNP-2 SIMULATOR PROJECT STATUS OCTOBER 29, 1991
%ASHlÃGTOND.C.
RNP-2 SlMUL4TOR
>I 1
1
ITEMS FOR DISCUSSION
~ SUMhhWY OF PROGRESS ON NEW SIMULATOR
~ TASKS TO COMPLETE 2 ONGOING CONCERNS
~ CERTIFICATIONPROGRAJvI
~ CURRENT SMULATORPERFORMANCE TRAIiiUNG~% B~QQvHNATj.ONPLANS
~ DISCUSSION WNP-2 SIMULATOR October 29, 1991
t
)
lt I
It tlf
)If
PROGRESS UPDATE
~Ari1~10 October 1 1
1.Scope of simulated systems defined with completion ofpreliminary design documentation pending.
- 1. 37 (of50) system models installed with 29 approved by the Supply System 2.Component model development in process for valves, pumps and motors.
2.Allcriticalhandler programs integrated and audited.
Two documents pending.
3,Handful ofintermediate system design documents provided fe." Supply System review.
- 3. Awaiting 8 system model design documents for review.
4.Test procedure scope being negotiated; preparation not started.
- 4. All315 erst-draft acceptance test procedures complete with 225 approved by Supply System.
5.Instructor station not functional.
- 5. 36 of 37 features operate with most fully implemented.
6.Panel delivery and installation at vendor facility pending.
- 6. Hardware fullyfunctional and documented; most discrepancies limited to cosmetic features.
October 29, 1991
II gl I
t III f
p',
Ij
PROGRESS UPDATE CONTINUED
~Ariel90 October 1 1
7.Configuration management system (CMS) in development
- 7. Outstanding CMS issues resolved with continued oversight ofdatabase integrity; now inuse by Supply System.
. 8."Up-front" documentation lags develoment; hardware, CMS, instructor, handler descriptions all pending.
- 8. Most non-model documentation provided forreview and customer acceptance.
TYNP-2 SIMUL4T October 29, 1991
f
(,
V
TASKS TO COMPLETE
- 1. Key Model Development - final design review, installation and checkout of several key "main energy loop" models remains. Allmodels must be operational to validate vendor testing.
- 2. Customer Approvals - resolve all outstanding discrepancies on instructor station and hardware, receive and review remaining documents; Supply System has a defined scope of work required to allow testing.
3, Ven allot.'P i e I:eating - Westinghouse to perform a defined subset of acceptance test gro-cedures to assure Supply System can conduct fullcomplement of tests.
- 4. Supply System Testing - successfully conduct complete factory acceptance tests at the vendor's facility.
- 5. Facility Preparation - only final modifications remain for installation.
- 6. Delivery, Acceptance and Shakedown - deliver, install and assure reliable operation.
Acclimate trainers and staff to develop training and exam scenarios.
Hap-2sIMULATOR October 29, 1991
t h
f t
I I
I I
II
'i t
ONGOING CONCERNS
~
Boiler Model - Supply System still captive to GPU Nuclear's model development.
Progress has been unsteady and until recently, not critical path.
Other Models - uncertain about main energy loop models not yet reviewed.
~
Quality - balance between our determination to have the highest fidelity and to deliver our simulator.
9J'estinghouse's haste may indicate future problems.
Schedule -The vendor is over a year behind the original delivery schedule. The critica1 gath has been model development and documentation.
The test program is urdRely, to be complete by our deferred date for certification.
TVNP-2 SIMULATOR October 29, 1991
I r.
lr K
I
SUPPLY SYSTEM ACTIONS To stimulate Westinghouse to perform and to expedite the program me have:
- l. Limited the scope of prelinnnary testing to verify the simulator's readiness, the Supply System's test program shrill validate the simulator's performance.
- 2. Demanded that a parallel path to install an alternative boiler model be initiated; procure a completed model from another vendor.
- 3. ivIKintain top management oversight and pressure on westinghouse executI:ves to attend to their simulator development problems.
- 4. Invoked liquidated damages provided by the contract for late delivery.
RVfP-2 SIMVL4TOR October 29, 1991
lt II I
I I
C lf j
I "I
I I
I
)
I I'
jj
>f
CERTIPICATIONPROGRAM The simulator procurement Technical Specification provides basis to certify physical and dynamic fidelitywithout exceptions.
Test program designed meet CFR requirements and ANSI/ANS 3.5, Regulatory Guide 1.149, and NUREG-1258 guidance.
The Supply System maintains a configuration management system which tracks plant changes for updates on delivery of the simulator.
A certification plan has been established which detaQs each functional area and section of our planned submittal.
Abstracts of tests and assessment of available data and analysis, plant procedures, LER's, FSAR's, etc. have been made to establish the test program.
Test results are, and remain the missing element for our submittal.
WNP-2 SIMULATOR October 29, 1991
CURRENT SIMULATORPERFORMANCE In April 1990, outlined the upgrades made to the current simulator to support its
- remairmg useful life.
Upgrades included new or significantly improved boiler/recirculation, condensate
~
and feedwater and steam line models, enhancements to the instructor system and installation of a stimulated plant process computer and graphics display system.
Since the upgrade project we have continued to address discrepancies identified by the training and examination programs and enhanced the simulator s transient response to support training and examination for emergency operating conditions.
The simulator has continued to be used successfully to support traixung and operator license examinations.
Listed below are significant NRC examinations that have been conducted on the simulator in 1991:
- March Annual R/Q Examination and Operational Evaluation
- June Operational Evaluation and Re-examination
- August Annual R/Q Examination September Annual R/Q Examination and Operational Evaluation WNP-2 SIMULATOR October 29, 1991
j
TRAININGANDEXAMINATIONPLANS Conduct:
~
Operational Evaluation and Individual Operator Re-examination in February 1992.
~
Traixnng on the phase two EOP Revision for all Licensed Operators during the period of June - October 1992.
Initial Licensed Operator simulator training during the period of July - November 1992.
~
Licensed Operator Annual Re-qualification Examination in November 1992 (the NRC would examine a minimum of 12 operators).
~
Replacement Operator NRC Examination in December 1992 for 9 operators.
W1VP-2 SIMUL4TOR October 29, 1991
t Li