NRR E-mail Capture - Acceptance Review - Wolf Creek Generating Station - Request for Indirect License Transfer (EPID No. L-2017-LLM-0005))
ML17286A012
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 10/12/2017
From: Balwant Singal
Plant Licensing Branch IV
To: Muilenburg W
Wolf Creek
References
EPID No.: L-2017-LLM-0005
Download: ML17286A012 (2)


Text

NRR-PMDAPEm Resource From: Singal, Balwant Sent: Thursday, October 12, 2017 4:03 PM To: Muilenburg William T Cc: Pascarelli, Robert; Blechman, Paula

Subject:

Acceptance Review - Wolf Creek Generating Station - Request for Indirect License Transfer (EPID No. L-2017-LLM-0005))

By letter dated September 5, 2017 (Agencywide Access and Management System (ADAMS) Accession No. ML17255A222), Wolf Creek Nuclear Operating Corporation (WCNOC, the licensee) submitted an indirect license transfer request for Wolf Creek Generating Station. The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

Based on the information provided in your submittal, the NRC staff has estimated that this licensing request will take 300 hours12.5 days <br />1.786 weeks <br />0.411 months <br /> to complete. The licensee has requested the NRC staff to complete the review and issue an Order by March 1, 2018 and the NRC staff will make every effort to meet the requested schedule. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.

These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including complexity and uniqueness of the review, requests for additional information, unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities. Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.

If you have any questions, please contact me.

1

Hearing Identifier: NRR_PMDA Email Number: 3768 Mail Envelope Properties (719f2016946340209567bc59a65c9716)

Subject:

Acceptance Review - Wolf Creek Generating Station - Request for Indirect License Transfer (EPID No. L-2017-LLM-0005))

Sent Date: 10/12/2017 4:02:36 PM Received Date: 10/12/2017 4:02:00 PM From: Singal, Balwant Created By: Balwant.Singal@nrc.gov Recipients:

"Pascarelli, Robert" <Robert.Pascarelli@nrc.gov>

Tracking Status: None "Blechman, Paula" <Paula.Blechman@nrc.gov>

Tracking Status: None "Muilenburg William T" <wimuile@WCNOC.com>

Tracking Status: None Post Office: HQPWMSMRS05.nrc.gov Files Size Date & Time MESSAGE 2733 10/12/2017 4:02:00 PM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received: