ML17285A880

From kanterella
Jump to navigation Jump to search
Insp Rept 50-397/89-30 on 891023-27.W/summary of Violations. Major Areas Inspected:Routine Unannounced Insp of Fire Protection Programs
ML17285A880
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 11/24/1989
From: Huey F
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML17285A879 List:
References
50-397-89-30, GL-81-12, NUDOCS 8912120173
Download: ML17285A880 (22)


See also: IR 05000397/1989030

Text

U.S.

NUCLEAR REGULATORY COMMISSION

REGION

V

Report Nos.

50-397/89-30

Docket Nos.

50-397

License

Nos.

NPF-21

Licensee:

Mashington Public Power Supply System

P.O.

Box 968

Richland, .Mashington

99352

Facility Name:

Mashington Nuclear Project

No.

2 (MNP-2)

Inspection at:

MNP-2 Site,

Benton County, Mashington

Inspection

conducted:

October 23-27,

1989

Inspectors:

C.

Ramsey,

Reactor

Inspector

'.

'ea

to

Inspector

Approved by:

uey,

>e

Engineering Section

~Summer:

a e

cygne

Ins ection on October 23-27

1989'(Re ort No, 50-397/89-30

Areas Ins ected:

Routine

unannounced

inspection of fire protection program

imp emen

a

~on and related activities.

In addition,

a followup was performed

by the inspectors

on previously identified open items.

Inspection

Procedures

Nos.

64704,

92701

and 30703

and related procedures

referenced

therein were

used.

Results:

General

Conclusions

and

S ecific Findin s:

The inspection identified that you had improperly deleted fire protection

requirements

from your Technical Specifications without first incorporating

those

requirements

into your Final Safety Analysis Report, and.that certain

fire protection procedures

were inadequate

for their intended purpose.

Si nificant Safet

Matters:

None

Summar

of Violations:

Sq12120173

8911203q7

PDR

ADOCK 0

PNU

8

Seven previously identified violations were closed.

One

new violation

regarding failure to implement appropriate

procedural

requirements

for remote

shutdown

was identified.

(paragraph

3.8).

Summar

of 0 en Items:

Ten previously identified Unresolvea

and

Open items were closed.

'One

previously identified Open Item remains

open.

One

new Unresolved

Item was

identified.

DETAILS

1.

Persons

Contacted

Mashin ton Public Power

Sup

1

S stem

~J.

Baker, Assistant Plant Manager

"J

~ Arbuckle, Compliance

Engineer

  • H. Fowler, Fire Marshal
  • H. Aeschelman,

Nuclear Licensing

"M. Hoylman, Supervisor Industrial Safety

  • J. Bell, Manager,

Health

8 Sciences

~N.

Richmond,

Supervisor Occupational

Health

"D. Kerlee, Principal equality Assurance

Engineer

  • D. Moon,

DERD

  • R. Madden, Principal guality Assurance

Engineer

  • T. Messersmith,

Principal Operations

Engineer

.*J. Civay, Generation

Engineer

  • P ~ Harness,

Generation

Engineer

D; Kreig, Generation

Engineer

R. Eyre, Generation

Engineer

R.-Muyco, Generation

Engineer

L. Noble, Generation

Engineer

D. Baynad,

Generation

Engineer

Bonneville

Power Authorit

kD

NRC

Nil 1 iams,

Nuclear Engineer

  • C. Bosted,

Senior Resident

Inspector

C.

Sor'ensen,

Resident

Inspector

  • Denotes those attending

the exit meeting held on October 27,

1989.

2.

.

Licensee Actions on'Previous

Ins ection Findin

s (92701)

A.

(Closed) Violation 397/86-05-01

"Safe Shutdown Methodolo

".

This

v)o a

1on invo ve

e

licensee

s

a1 ure

o prove

e requ>red fire

protection features for the safe

shutdown

method using Reactor

Core

Isolation Cooling/High Pressure

Core Spray identified in the

FSAR

and the original

SER; or the method using Automatic Depressurization

System/Low Pressure

Coolant Injection chosen

by the licensee

and

described

in a March 23,

1983 submittal to the

NRC.

The inspector verified that the licensee

has provided the required

fire protection features for the ADS/LPCI safe

shutdown methodology,

as described

in the current approved fire protection program

(FSAR

Ammendment

No. 39).

Enforcement action on this item will be the

subject of separate

correspondence.

(Closed) Violation 397/86-05-02

"Safe Shutdown Train Se aration/

ro ec ion

.

is vio a ion invo ve

e

icensee

s

ai ure

o

~pqi

d

p

ti

p t ti

f9'

18'

of thermolag

on intruding steel) of cabling and equipment

necessary

to support safe

shutdown in the Reactor Building and Cable Spreading

Room.

The inspector verified that the licensee

has provided the required

separation

or protection for safe

shutdown cabling and equipment

necessary

to support safe

shutdown in the Reactor Building and Cable

Spreading

Room.

Enforcement action

on this item will be the subject

of separate

correspondence.

(Closed) Violation 397/87-02-01

"Failure. to Install

uglified Fire

arriers

or

e

ro ec ion o

a

e

u

own

rains

.

is

vio ation invo, ve

e

icensee

s app ication

o

an unqualified one

hour fire barrier (Thermolaq extrusion spray) for the protection of

redundant

safe

shutdown train cabling in conduit and cable trays

located in the Reactor Building, Radwaste

Building Cable

Chase

and

Cable Spreading

Room.

The inspector verified that the licensee's

Nonconformance

Report

(NCR) No. 286-440

and Maintenance

Work Requests

MIIIR Nos.

AT2895 and

AT1048, required the removal of the unqualified fire barrier

material

and the installation of a "tested configuration" qualified

one hour fire barrier,

and that this work had been independently

verified and signed off as complete

by the licensee.

The rework of

the fire barrier installation was performed in accordance

with

licensee

Procedure

No.

PPM-10.25.89.

The inspector performed

a

'alkdown

and verified that fire barrier installations

met the

criteria for

a "tested configuration" one hour fire barrier rating.

Enforcement action

on this item will be the subject of separate

correspondence.

(Closed) Violation 397/88-16"Ol

"Failure to Provide

Re uired Three

our

ire

arrier

ro ec ion

or

esi

ua

eat

emova

s

em

a ve

o.

-

a

in

in

e

eac or

ui

in

.

is

vio ation invo ve

e

icensee.

s

ai. ure

o provi

e required three

hour fire barrier protection to protect against

a Loss of Coolant

Accident (LOCA).

The postulated

accident would be caused

by fire

induced hot shorts which open the

RHR System high-low pressure

interface motor operated isolation valve No. V-9.

The inspector verified that the licensee's

high-low pressure

interface analysis

had been revised

so that appropriate

consideration

was given to the high-low pressure

interface concern

in accordance

with NRC Generic Letter 81-12 and Branch Technical

'osition

RSB 5-1.

The licensee's

Basic Design

Change

(BDg) No.

88-0211-0A, requiring 'the installation of three

hour fire barrier

protection

on the subject

RHR System motor operated isolation valve

cabling in the Reactor Building.had been verified and signed off as

complete

by the licensee.

Enforcement action on this item will be

the subject of separate

correspondence.

E.

{Closed) Violation 397/88-16-02

"Failure to Provide

0 erator

roce ura

ns ruc ions

or

e

oss

o

0

ower

u

lies

F.

ue

o

u

i

e

i

mpe ance

au

s

.

is vio,ta ion invo ve

he

icensee

s

ai ure to prov>

e opera ing procedures

for loss of the

525 volt OC power distribution system resulting from high. resistance

faults during a Design Basis Fire (OBF).

The inspector verified that the licensee's

High Impedance

Fault

Analysis Calculation

No. NE-02-85-19-5c,

dated August 8, 1988,

appropriately

considered

the failure of the normally energized

125

volt OC power feeders

due to a high resistance

ground, with a fault

'current increasing to 'just below the fuse rating breaker trip

setting.

The analysis

also considered

normally de-energized

125

volt OC power feeders

and interconnected

control circuits to

determine if other possible failure modes exist.

Based

on the analysis results,

the licensee's

Remote

Shutdown

Procedure

No.

PPM 4. 12. 1. 1 (Revision

No.

12)

had been revised to

instruct operators

to remove certain

loads

from the main

distribution panel

(No. DP-SI-2) within two hours following a fire

and Control

Room ev'acuation.

Additional

emer gency lighting was

provided to support operator

accomplishment

of these actions.

The

inspector verified that the High Impedance

Fault Analysis

Calculation

No. NE-02-85-19-.5c

had been verified and checked

'independently.

The licensee

indicated that these

actions would be

referenced

in the next

FSAR revision

(Ammendment

No. 41),

as part of

the approved fire protection program.

Enforcement action

on this

item will be the subject of separate

correspondence.

Closed) Violation 397/88-16-04

"Failure to Provide

Re uired Fire

arrier

ro ec ion

or

mer enc

iese

enera or an

arious

er

a e

u

own

s

em

a

in

oca

e

in

e

a

e

rea in

oom

.

is vio a ion invo ve t e

icensee

s

ai ure

o provi

e

ire

barrier protection in the Cable Spreading

Room for the Division II

Emergency Diesel Generator cabling and the associated

cabling for

safe

shutdown

systems identified by the licensee

in a March 21,

1983

submittal to the

NRC.

This submittal

changed

the licensee's

original safe

shutdown methodology.

The inspector verified that the licensee's

HMR Nos.

AT5712 and

AT5920, requiring the installation of Thermolag fire barrier

material

on the Division II Emergency Diesel Generator

and required

safe

shutdown

system cabling located in the "20 Foot Exclusion Zone"

of the Cable Spreading

Room,

had been verified independently

and

signed off as complete

by the licensee.

The work requests

required

that the Thermolag fire barrier material

be installed in accordance

with licensee

Procedure

No.

10.25.89.'he

inspector performed

a walkdown and verified that the fire

barrier material

was installed

on cable trays located in the "20

Foot Exclusion Zone" of the Cable Spreading

Room.

The licensee

had

distinctly identified the boundaries

of the "20 Foot Exclusion Zone"

by placing metallic tape

on the length and width of the protected

cable trays.

Enforcement action

on this item will be the subject of

separate

cor respondence.

G.

(CIosed)

Unresolved

Item 397/86-25-01

"Control

Room Desi

n

e iciencies

.

is i

em i en i ie

e

concern

a

ontrol

Room design deficiencies

reported to the

NRC by the licensee

in LER

No.84-031

and its six revisions

were associated

with Allegation

File No.

RV-86-A-0004.

The inspector verified that the licensee's

corrective actions for

. the Control

Room design deficiencies

reported in LER No.84-031

and

its six revisions

had

been

implemented.

This issue will be tracked

with Allegation File No.

RV-86-A-0004.

This item is closed.

H.

(0 en) Followu

Item 397/86-25-03

"Fire Mains Routed Beneath Safet

e a

e

ruc ures in

io a ion o

a iona

ire

o

e

e uiremen

s

.

is i

em i enti ie

e

concern

a

un ergroun

ire mains

installed in the vicinity of and under Catagory

1 structures

may .

compromise

the integrity of the structures

in the event of a pipe

separation

or rupture.

In response

to this concern,

the licensee

demonstrated

that several

of the underground fire mains could be properly isolated in the

event of pipe separation

or rupture,

and their installation was in

accordance

with National Fire Protection Association

(NFPA) code

requirements.

However, the actions required to satisfactorily

mitigate

a rupture of the

12 inch fire main No. FP(43)-1,

beneath

the Diesel Generator Building have not been resolved with NRR.

This

issue

has

been the subject of considerable

discussion

between

NRR

and the licensee.

The licensee

informed the inspector that an

additional submittal

(G02-89-158 dated

September

11, 1989)

had been

made to NRR.

This submittal provided

a revised justification and

code expert opinion regarding this condition.

This item will remain

open pending

NRR resolution.

I.

Closed) Violation 397/87-19-29

"Instrument Rack Terminations".

is vio a ion invo ve

e

icensee

s

ai ure

o proper y ins all

terminal

lugs in Class I instrument

racks.

The licensee's

corrective action for the violation included:

rework

of the instrument rack terminations;

revision of procedure

No.

10-25-19 (Revision 13) to include specific instructions regarding

45

to 90 degree

bends

on terminal lugs;

and implementation of formal

requirements

for "pull tests",

including documentation of test

results.

This violation is considered

closed.

J.

(Closed

Followu 'tem 397/88-16-03

"Conformance With Re ulator

Guide

is i

em i en >>e

e

concern

a

ivision

an

U>v>sion II components

and associated

cabling instalied in the

Remote

Shutdown

Panel

were not provided with the physical separation

required

by Regulatory

Guide 1.75.

The inspector verified that the licensee's

Basic Design

Change

(BDC)

No. 88-0186-0A, requiring the installation of a fire barrier to

maintain

6 inch separation

between residing

and intruding cabling of

Division I and Division II components

in Remote

Shutdown

Panel

No.

E-CP-C61/POOl

had been verified independently

and signed off as

complete

by the licensee.

During plant walkdowns,

the inspector

observed that the required fire barrier

had been installed to

maintain the specified physical

separation.

This item is considered

closed.

K.

(Closed)

LER No. 397/87-30

"U

raded Technical

S ecification

ire

a

ot

onstruc

e

to

ua i

as

a

ree

our= ire

arr>er

e

licensee

reporte

o

e

>n

o.

-

a

e

a waste

Building block wall "3W3", located

on the 487 to 507 foot level

between

column lines 15.6 and 17.0 did not have the required three

hour fire rating.

The inspector verified that. the licensee's

HMR No.

AT7669, requiring

the installation of Thermolaq to upgrade

the rating of the wall, was

verified independently

and s>gned off as complete

by the licensee.

During plant walkdowns; the inspector

observed that the Thermolag

had

been applied to the wall as specified

by the tOR.

This item is

considered

closed.

L.

(Closed)

LER No. 50-397/89-27

"Inade uate Seismic Restraints"

~

The

licensee

s

en

) )e

a

seismic

res rain

s were m)sslng

rom two

Post Accident Sampling

System valves.

The inspector

found that,

upon identification of this condition, the

appropriate

Technical Specification action statement

was entered.

Plant shutdown

was initiated when the restraints

could not be

restored

in one hour.

Records

indicated that the supports

may have

been

removed during system modification in 1983.

A sample of

similar work at that time showed that supports

were correctly,

reinstalled

on similar valves.

A sample of current work orders

showed that supports

were identified and reinstalled appropriately.

The inspector

reviewed the licensee's

program to identify and

reinstall supports.

It appeared

satisfactory.

The missing

restraints

appeared

to be

an isolated occurrence.

This item is

closed.-

H.

(Closed)

LER No. 50-537/88-26 "Instrument Sensin

Line Su

orts".

n

a

e y

va ua

1on

epor

s

en

1 le

a

ere

was

a

potential for fire damage to instrument sensing line supports.

By analysis,

the licensee

determined that modification of the

supports

was required.

The inspector

reviewed the licensee's

analysis

and found it satisfactory.

Based

on this analysis,

the

licensee

plans to install Thermolag

and replace bolts

on supports

to

satisfy fire protection requirements.

The scheduled

completion date

is December

31,

1989. Until that time,

MNP-2 (L. Aeschelman)

has

confirmed that the areas

containing these

supports will remain

on

a

fire watch in accordance

with MNP-2 fire protection plan and

procedures.

This item is closed.

I

(Closed)

LER No. 50-397/89-7 ".Failure 'to com

1

with Fire

rotec ion

s

em

e ector

urvei

ance

ec nica

eci ication

equirement

.

wo

ire protec ion survei

ance

proce ures

were not

~fh IINP-2 T

h i

1

Sp if'i

3.3.7.9,

hi

h

addressed

fire protection surveillances.

The procedures

reflected

the actual plant configuration of a thermal fire detector in the

standby service water

pump houses

rather than

an ionization fire

detector

as required

by Technical Specifications.

Also, the

procedures

and plant have

seven ionization fire detectors

in the

Power Generation

Control Cabinet rather than eight as required

by

Technical Specifications.

The licensee

states

in LER 89-7, that, with respect to these

specific detectors,

the Technical Specifications

were incor rect as

submitted for approval

in November of 1983.

The licensee

states

that, with respect

to these fire detectors,

the Technical

,

Specifications

do not reflect the plant as designed.

The current

number

and type of- these fire detectors

installed in the plant and

referenced

in the procedures

do reflect the plan as designed.

The inspector confirmed that

a walkdown of Technical Specification

fire protection

systems

was conducted.

No additional

inconsistencies

were found between applicable fire protection

systems,

surveillance

procedures,

or Technical Specifications.

The

inspector also confirmed that the subject areas

were maintained

on

a

fire tour until Technical Specifications for fire protection were

deleted in May, 1989.

The licensee

states all inconsistencies

with

procedures

were resolved after that date.

This item is closed.

(Closed)

Followu

Item No. 50-397/88-19-01 "Labelin

of Status of

tan

ower.

n ica ors

.

uring a review o

e

os

cci

en

onitoring

ys

em,

our gauges

which monitor the status of standby

power were found to have inconsistencies.

Three

ammeters

were not-

labled to denote

charge

or discharge,

and

a voltmeter was labeled to

denote

an incorrect bus.

In addition, the meters

were labeled

by

bus only and not with the instrument tag number.

The inspector

observed

the labels.

The subject instruments

were

correctly labeled

and the inspectors'oncerns

were addressed.

This

item is closed.

(Closed)

LER No. 88-22

"Missin

Thermola

in Radwaste Buildin

a

e

rea in

oom

ire

arrier.

n

inspec or i en i ied

ive ca

e

rays par ia

y ex en ing into the 20 ft. fire barrier

area which did not have required insulation.

The inspector verified that the licensee

corrected this deficiency

by installing the required insulation.

The licensee

determined that

these deficiencies

were caused

by personnel

error and ineffective

corrective action of earlier deficiencies.

This item is closed.

(Closed)

SER 0 en Item No.

5

"Se aration

and Protection of

e un an

rains in

e

a

e ween

e

rimar

on ainmeni; Vessel

an

e

io o ica

ie

a

.

is i

em i en i ie

e

,concern that the'gnition of the polyurethane

foam material

installed in the annulus

space

between

the Primary Containment

Vessel

and the Biological Shield Mall would cause

the inoperability

of redundant

safe

shutdown train cabling routed within the annulus

space.

The inspector verified that licensee

Procedure

No. 80-FPT-0702-LP,

".Fire Match Training", contai'ns specific instructions to personnel

performing fire watch duty to identify penetrations

through primary

containment that must be protected

from ignition sources.

This item

is considered

closed.

R.

(Closed)

SER 0 en Item No.

27

"Re ulator

Guide 1.39

Com liance".

is i

em i en i ie

e

concern

a

e

me

o

o

e

licensee's

compliance with Regulatory Guide 1.39 guidelines for

implementation the fire protection program was not'clearly defined.

I

The inspector

reviewed the licensee's fire protection program

implementation

Procedure

Nos.

PPM 1.3. 10 "Fire Protection

Program",

. 1.3. 19 "Housekeeping",

1.3.35,

"Administrative Procedures"

and

1.3.36 "Fire Protection Training".

The procedures

appear to

establish

a program that adheres

to the imp'lementation guidelines of

Regulatory Guide 1.39.

This item is considered

closed.

Im lementation of Routine Fire Protection

Pro

ram (64704)

A.

Technical

S ecification Surveillances

Limitin Conditions for

era ion an

erne ia

c ions

During a review of surveillance

procedures

and the site fire

protection program,

the inspector

found that the licensee

had not

followed the requirements

of Generic Letters 86-10 and 88-12.

The

Generic Letters state actions which the licensee

must accomplish

before the fire protection section of Technical Specifications

can

be removed

from the'operating

license.

Specifically, the Generic

Letters required

MNP2 to incorporate all fire procection Technical

Specification'Sur veillances,

Remedial Actions and Limiting

Conditions for Operations

(LCOs) into the

FSAR fire protection

program before removing the'fire protection section

from Technical

Specifications.

I

Contrary to the Generic Letters guidance,

the inspector

found the

fire protection section of Technical Specifications

had been

'eleted,

while the

FSAR fire protection program did not contain any

of the required remedial

actions or LCOs.

Also, the

FSAR contained

only general

references

to surveillances

associated

with fire .

protection,

and did not contain the specific requirements

of the

surveillances

which had been required by'he deleted section of

Technical Specifications

section.

(1)

Although the licensee

stated that individual fire protection

surveillances

were being accomplished

by specific surveillance

procedures,

there

was

no plant procedure

implementing the

overall programmatic or schedular

requirements

which had been

(2)

(3)

deleted

from Technical Specifications.

The inspector

was

informed by the

MNP2 Fire Marshall

(S.

Fowler) that all the,

sui vei llances

were still required to be performed

on schedule

because

they were

NRC commitments

and listed by the computer

tracking system.

The inspector did not consider the tracking

system sufficient to implement programmatic control.

In a letter dated

November

14,

1989,

the licensee

confirmed

that all fire protection Surveillances,

Remedial

Actions and

LCOs deleted

from Technical Specifications

had been

incorporated in the

MNP2 fire protection program.

In letters to the

NRC dated February

10, 1987,

and Harch 31,

1989, the licensee

requested

that the fire protection section

oi Technical Specifications

be deleted

based

on the guidance of

Generic Letters

86'-10 and 88-12.

In fact, the licensee

had not

fully implemented

the Generic Letter guidance

upon which

NRC

approval of the license

amendment

was based.

In particular,

the

NRC issued

a Safety Evaluation Report with License

Amendment 67, the

ammendment

which allowed

MNP2 to delete the

fire protection section

from Technical Specifications.

This

report noted that "the licensee

confirmed that the operational

conditions,

remedial actions

and test requirements

associated

with the removed fire protection technical s~ecifications

have

been included in the fire protection program'.

Although this

statement

was incorrect,

the licensee

incorporated

the

amendment

and did not notify the

NRC of the incorrect statement

upon reciept of the report.

The licensee

states

that after the license

amendment

was

approved in Nay, 1989, the fire protection remedial actions,

surveillances,

and

LCO's were

no langer

maintained

as part of

Control

Room logs.

During discussions

with the inspectors,

on

November 1, 1989, licensee

enqineers

stated that they would not

be able to quickly determine if they would currently be subject

to a remedial action or

LCO which would have

been required by

the deleted section of Technical Specifications.

The licensee

later confirmed on November 14, 1989, that all remedial

actions

that would have

been required

by the

LCOs in the deleted

Technical Specifications

section are in place.

Because

the

licensee

engineers

were unable to quickly determine fire

protection system status in the area of remedial actions

and

LCOs, more detailed

NRC inspection is warrented of the

administrative control of the fire protection program.

This is

considered

an unresolved

item (89-30-01)

and requires further

inspection.

B.

Safe

Shutdown

Procedures

The inspector

reviewed the plant procedures

to be'used

in the event

of a fire or Control

Room evacuation.

The procedures

are Revision

5

of 4. 12. 4. 1, "Fire"; Revision 12 of 4. 12. 1.1, "Control

Room

Fire/Evacuation";

and Revision

3 of 4.12. 1.2,

"RPV Remote

Cooldown".

The following deficiencies

were found in procedure

4. 12.1.1.:

(1)

Step A.10) requires

valve RHR-Y-1238 to be closed.

The correct

valve is RMR-Y-123A.

RHR-Y-123B is the similar valve in the

other train.

The purpose of this step is to isolate the

low

pressure

RHR system

from the high pressure

side for Division I

(A train).

This deficiency is mitigated in part because,

in

previous

correspondence,

the

NRC (NRR) noted that during

a fire

in the control

room, heat

induced short circuits could open

both of these

valves,

causing

an intersystem

loss of coolant

accident.

The

NRC determined that the only acceptable

assur ance 'of avoiding this possibility

was to remove

power from

the valves

RHR-Y-123A and -B.

The licensee

stated that the

valves were closed

and power has

been

removed

from these

valves

by administratively requiring the circuit breakers

to remain

open.

Nonetheless,

this i's

a significant procedural

deficiency.

The licensee

changed, the procedure to specify the

correct valve..

(2)

Step A.3) requires

the reactor vessel

level to be monitored,

.

and lists instrument.MS-LI-10R,

which does

not exist.

The

correct instrument,

which is correctly labeled

on the remote

shutdown panel,

is HS-LI-10.

The licensee

changed

the

procedure

to specify the instrument correctly.

(3)

Step A,27) requires that cooling equipment

RRA-FN-j. be

made

operable

before the

RMR 2B pump

room exceeds

specified

temperature

limits.

The correct equipment is RRA-FN-3.

RRA-FN-1 cools

a different pump room.

The licensee

changed

the

procedure to specify the correct cooling equipment.

The licensee

stated that this deficiency is mitigated because,

when the

RHR 2B pump is energized,

RRA-FN-3 is automatically

energized.

In addition, the procedure

requires hourly

temperature

monitoring of the

pump room.

If the temperature

exceeds

150'F, operators

are instructed to make the cooling

equipment

(which was incorrectly identified as

RRA-FN-1)

operable.

The highest safe operating temperature

for the

pump

is listed as

200 F.

The licensee

state'd that the following

would have to occur for the

pump

room to exceed the safe

operating temperature:

(a)

The fan would fail to auto'matically energize

(b)

The temperature

would have'to rise above 150'F

(c)

The operator would energize

(the incorrent) fan RRA-FN-1

(d)

The temperature

would climb if the incorrect fan was

energized

(e)

On the next hourly temperature

reading,

the operator would

not notice that, althouqh

a fan'was

energized to cool the

room, the

room was getting hotter and the

2B pump room'fan

was not running.

(f)

Step (e) would be repeated

every hour until the

room

temperature

exceeded

200

F.

The licensee

considers it .unlikely that all the above steps

would occur.

(4)

Step A.27) requires that cooling equipment

WHA-TI-9 be

made

oper able before the

Remote

Shutdown

Room exceeds

specified

temperature

limits.

WMA-TI-9 is a temperature

indicator.

= The

Remote

Shutdown

room is cooled by the

same cooling equipment

that cools the cable spreading

room.

The licensee will

determine .the corrective action for this error during the next

biannual

review required by plant procedures.

Individually, these

procedure deficiencies

do not prevent the safe

shutdown of the plant i.f a Control

Room fire occurs.

However, these

deficiencies

would delay important plant corrective actions

and would

require already burdened

operators

to search for and verify the correct

equipment.

f

Deficiencies similar to the ones listed above

can

be found in the

Alternate

Remote

Shutdown section of the

same procedure,

and in the

"RPV

Remote

Cooldown" procedure

4. 12. 1.2.

The deficiencies listed above

are considered

a violation of Criterion V

of Appendix

B to 10 CFR 50 and Condition No. 2.C(14) of Facility

Operating

License

No.

NPF-21.

This violation (397/89-30-02) will be the

subject of separate

correspondence.

C.

Fire Bri ade

Readiness

ualifications of Fire Bri ade

Members

The licensee's

Procedure

No. 1.3. 1 "Conduct of Operations",

Revision

No. 16, section 1.3. 1.5.B.5 requires that a minimum of five

individuals serve

on the Plant Fire Brigade.

At least

two of these

individuals are required to be equipment operators.

The on-duty

Shift Support Supervisor is the designated

Fire Brigade Leader.

The

remainder of the fire brigade is composed of fire brigade support

personnel (i.e. Chemistry/Health

Physics Technicians)

as specified

by licensee

Procedure

No. 1.3.36 "Fire Protection

Program Training".

Section 1.3.36.5.B of licensee

Procedure

No. 1.3.36 requires all

fire brigade

members

to have

an initial physical examination

by a

physician to determine that they are fit for strenuous

physical

activity, as experienced

in firefighting activities.

In addition,

once every year,

the procedures

require fire brigade

members to be

re-examined to determine

continued fitness for performing

strenuous'irefighting

activities.

The procedure

references

10 CFR 50,

Appendix

R as

one of the bases for this requirement.

Section III.H

= of 10 CFR 50; Appendix

R requires that the qualifications of the

fire brigade -include an annual

physical

examination to determine

their ability to perform strenuous firefighting activities.

During a licensee quality assurance

surveillance

(No.86-114) in

July 1986, several

deficiencies

were identified associated

with the-

qualification and training of fire brigade personnel.

Among these

deficiencies

were: (a), failure to estab'lish

a fire brigade

on

several shifts;

and (b), annual. physical

examinations for strenuous

firefighting activities were not conducted.

The inspector's

followup activities regarding these

concerns

included

a review of an October 23,

1989 listing of qualified fire

brjgade personnel

and

random comparison of this list to the Radwaste

Control

Room Log of fire brigade

member assignments

on each shift

during the period July 13 through October 26,

1989.

The review

disclosed that all personnel

assigned

to the fire brigade during

this period were

on the list of qualified fire brigade personnel.

The inspector further reviewed the licensee's

annual. physical

examination requirements

for fire brigade personnel

and reactor

operators.

The criteria for each examination requires slightly

different special tests,

but neither examination requires

a physical

fitness stress test to determine

the ability of fire brigade

personnel

to perform strenuous firefighting activities.

According

to the licensee,

either of the annual

physical

examinations

can

be

used to satisfy the fire brigade physical

examination criteria of

the licensee's

Procedure

No. 1.-3.36.

During the exit meeting the licensee

indicated that consideration

had been given to implementing

a physical fitness stress test

as

part of annual fire brigade personnel

physical

examinations,

but

decided against it.

The licensee further stated that it was their

belief that .no such

NRC requirement exists.

However, the licensee

agreed to reconsider

the need for

a physical fitness stress

test to

determine

the ability of fire brigade personnel

to perform strenuous

firefighting activities.

D.

Results of maintenance

Surveillance Testin

Performed

The inspector performed

a limited scope review of the results of the

following maintenance

surveillance tests:

Test Procedure

la%

2.4. 9

Title

Remote

Shutdown

Panel Operability

7.4.3.7.9.45

Instrumentation (Fire Detection)

7.4.3.7.9.50

Instrumentation (Fire Detection)

ANI File N-219

E.

Results of Inde endent

ualit

Oversi ht Reviews

Annual Fire

Pump Test Results

The electric

and diesel

driven fire pump (Nos.

FP-002A and FP-0028)

annual testing

was performed

by American Nuclear Insurers

(ANI) in .

June

1989.

The results of this testing indicated that the pumps

performed satisfactorily.

The Remote

Shutdown

Panel

and fire

detection

system operability testing

was performed by the licensee

in April 1989.

The test results indicated that these

systems

also

performed satisfactorily.

The inspectors

reviewed

two of the licensee's

independent quality

oversight review audits that were performed pursuant

to the

requirements

of Technical Specification 6.8.1.

Audit No.88-455

was

a three year audit which was-performed

during the period September

. 14 through September

18,

1989.

The audit results

were compared to

the previous fire protection audit and the results

showed 'that

significant improvement

had

been

made in fire protection

program

implementation in that there were noticeably fewer audit

findings.'he

previous

annual audit (No.87-418)

was conducted

during the

period September

26 through 30,

1988.

The audits

appeared

to be

thorough

and of sufficient depth.

The licensee's

quality assura'nce

representative

provided the

inspectors

with the plan for auait

No.69-501.

The audit was

scheduled

to be conducted

during November

1989.

The audit scope

was

broad

and contained

plans for auditing key fire protection'orogram

parameters,

including followup on the licensee's

response

to

previous audit findinas.

4.

Exit Neetina

30703)

An exit meeting

was held with the licensee's

staff on October 27,

1989.

The items of concern in this report were discussed

at that time.

The

licensee

acknowledged

the scope

and content of the inspection findings.