Notice of Deviation from Insp on 880829-0930.Deviation Noted:Diesel Generator Fuel Oil Tanks DO-TK-1A,DO-TK-1B & DO-TK-2 Declared Operational W/O Completing New Calibr
ML17284A596
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 10/27/1988
From: Martin J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML17284A594 List:
References
50-397-88-32, NUDOCS 8811160352
Download: ML17284A596 (2)


Text

APPENDIX B NOTICE OF DEVIATION Washington Public Power Supply System P.

0.

Box 968

Richland, Washington 99352 Docket No. 50-397

,License No.

NPF-21 During an NRC inspection conducted during the period of August 29 to September 30, 1988, a deviation from your commitments to the NRC was identified.

In accordance with the General Statement of Policy and Procedure for NRC Enforcement Actions, 10 CFR Part 2, Appendix C (1988), the deviation is listed below:

The Washington Public Power Supply System reply (WPPSS G02-88-025, dated January 29, 1988) to a Notice of Violation issued with NRC inspection report 50-397/87-19 stated in part in section B, under Date of Full Com liance,. that calibration of the diesel generator fuel oil tank level instrumentation will be accomplished by July 20, 1988.

Contrary to the above, at the time of this inspection the new calibration of diesel generator fuel oil tanks DO-TK-lA, DO-TK-1B and DO-TK-2 had not been completed and the tanks had been declared operational.

This is a Deviation from a commitment.

Please provide to the U.S.

Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington DC, 20555, with a copy to the Regional Administrator, and a copy to the NRC Resident Inspector, in writing within 30 days of the date of this Notice, the reason for the Deviation, the corrective steps which have been taken and the results

achieved, the corrective steps which will be taken to avoid further deviations, and the date when your corrective actions will be completed.

OR THE NUCLE R

REGULATORY COMMISSION Dated'at Walnut Cre

,, galifornia thi s ~>

day of 4~~ 1988 Wc/~d 4

J.

B. Martin Regional Administrator