August 8, 1988 Docket No. 50-397 Washington Public Power Supply System P.O.
Box 968 Richland, Washington 99352 Attention:
Mr. G.
C. Sorensen Manager of Regulatory Programs Gentlemen:
Subject:
Management Meeting This will confirm the telephone discussion between Mr. A. L. Oxsen and Mr. P.
H. Johnson of this office on July 29, 1988 concerning a management meeting to be held between NRC and Supply System representatives in the Region Y conference room, at 10:00 a.m.
on August 18, 1988.
The purpose of this meeting is to discuss the Systematic Assessment of Licensee Performance (SALP) for the period June 1, 1987 through May 31, 1988.
Also included is a copy of the Notice of Significant Licensee Meeting which lists the anticipated attendees at the meeting.
Sincerely, D. F. Kirsch, Director Division of Reactor Safety and projects
Enclosure:
Notice of Significant Licensee Meeting CC:
See next<page' 88082 60248 880808 PDR ADOCK 05000397 9
PNU
Mr. Nicholas S. Reynolds, Esq.
- Bishop, Cook, Purcell 5 Reynolds 1200 Seventeenth
- Street, N.W.
Washington, DC 20036 Mr. G.
E. Doupe, Esq.
Washington Public Power Supply System P. 0.
Box 968 George Washington Way Richland, Washington 99532 Mr. Curtis Eschels, Chairman Energy Facility Site Evaluation Council Mail Stop PY-ll Olympia, Washington 99504 Dr. G.
D. Bouchey, Director Licensing and Assurance Washington Public Power Supply System P. 0.
Box 968, MD280 Richland, Washington 99352 Mr. C.
M. Powers WNP-2 Plant Manager Washington Public Power Supply System P. 0.
Box 968, MD 927M Richland, Washington C
e11 son
/+/ 8 8/5/88 wf" RZimmerman ACh ffee 8/f/I'88 8
/88 DKir ch 8/P/88 S
E YES'O YES P
NO ES NO P
ES /
P'~ ASCII'p, 0
Cy
~
~> +i I
)
0O l
Oh0
/y 0
UNITED STATES NUCLEAR REGULATORY COMIVllSSION REGION V 1450 MARIALANE,SUITE 210 WALNUTCREEK, CALIFORNIA94596 August 8, 1988 NOTICE OF SIGNIFICANT.LICENSEE MEETING Name of Licensee:
Washington Public Power Supply System Name of Facility:
WNP-2 Docket Number:
50-397 Date and Time of Meeting:
Location of Meeting:
Purpose of Meeting:
NRC Attendees:
Licensee Attendees:
August 18, 198&, 10:00 a.m.
Region V Conference Room Discussion Of Systematic Assessment of,Licensee Performance (SALP) For The Period Of June 1, 1987 Through Hay 31, 1988 J.
B. Hartin, Regional Administrator D. F. Kirsch, Director, Division of Reactor Safety and Projects R. A. Scarano, Director, Division of Radiation Safety and Safeguards G.
W. Knighton, Director, Project Directorate V,
NRR R.
P. ZiIIIIerman, Chief, Reactor Projects Branch P.
H. Johnson, Chief, Reactor ProjectsSection III R. B. Samworth, Project Manager, NRR C. J. Bosted, Senior Resident Inspector C.
W. Caldwell, Project Inspector D.
W. Mazur, Managing Director A. L. Oxsen, Assistant Managing Director for Operations G.
D. Bouchey, Director, Licensing and Assurance J.
P. Burn, Director, Engineering C. M. Powers, P'lant Manager L. T. Harrold, Manager, Generation Engineering C. H. McGilton, Manager, Operational Assurance Program
L NOTE:
Attendance at this meeting by NRC personnel other than those listed above should be made known by August 12, 1988 via a telephone call to P.
H. Johnson, FTS 463-3745 CC:
NRC Participants Listed Above D. Crutchfield, NRR G. Holahan, NRR B. Faulkenberry, RV A. Chaffee, RV R. Scarano, RV G. Cook, RV D. Persinko, NRR