ML17279A975

From kanterella
Jump to navigation Jump to search
Insp Rept 50-397/88-09 on 880307-11.No Violations or Deviations Noted.Major Areas Inspected:Response to NRC Bulletin 85-003, Motor-Operated Valve Common Mode Failure, Followup of Inspector Identified Items & Review of Events
ML17279A975
Person / Time
Site: Columbia 
Issue date: 03/30/1988
From: Caldwell C, Johnson P
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML17279A974 List:
References
50-397-88-09, 50-397-88-9, IEB-85-003, IEB-85-3, NUDOCS 8804190120
Download: ML17279A975 (13)


See also: IR 05000397/1988009

Text

U.

S.

NUCLEAR REGULATORY COMMISSION

REGION V

Report

No.

Docket No.

License

No.

50-397/88-09

50-397

NPF-21

Licensee:

Facility Name:

Washington Public Power Supply System

P.

0.

Box 968

Richland,

Washington

99352

Washington Nuclear Project

No.

2 (WNP-2)

Inspection at:

WNP-2 Site,

Benton County, Washington

Inspection

conducted:

March 7 - March 11,

1988

Inspector:

C.

W. Caldwell, Proj ct Inspector

Da

e

S gned

Approved By:

P.

H. Johnson,

Chief,

Reactor Proj'ects

Section

3

Date Signed

Ins ection

Summar

Ins ection

on March

7 - March ll

1988

Re ort No. 50-397/88-09

Areas Ins ected:

Routine project inspection in the areas of scram discharge

volume capacity,

respon'se

to

NRC Bulletin 85-03,

"Motor Operated

Valve Common

Mode Failure"; followup of inspector identified items,

and on-site review of

events.

Inspection procedures

25590,

25573,

92701,

93702,

and 30703 were

covered.

Safet

Issues

Mana ement

S stem

SIMS

Items:

Item 41, Multiplant Action (MPA)

Item B-58, Licensee's

Scram Discharge

Volume Capacity.

Results:

No violations or deviations

were identified.

One inspector followup

item was identified (paragraph

7) which deals with licensee

evaluation to

determine if environmental qualification requirements

are adequately

maintained

during and following the performance of surveillance

procedures.

SS04190i20

S80330

PDR

ADOCK 05000397

O

DCD

DETAILS

Persons

Contacted

Licensee

Personnel

  • C. M.

J.

W.

D. S.

A. G.

K. D.

N. C.

R. L.

R. J.

  • E. R.
  • S. L.
  • W. H.

J.

D.

Powers,

Plant Manager

Baker, Assistant Plant Manager

Feldman,

Plant equality Assurance

Manager

Hosier, Nuclear Safety Assurance

Group Manager

Cowan, Plant Technical

Manager

Bartlett, Plant

gC Supervisor

Koenigs, Plant Technical

Supervisor

Barbee,

Plant Engineering Supervisor

Ray, Instrumentation

and Controls Supervisor

Washington,

Lead Compliance

Engineer

Sawyer,

Control

Room Supervisor

Arbuckle, Compliance

Engineer

  • Denotes

those attending

the final exit meeting

on March 11,

1988.

The inspector also contacted

licensee

operators,

engineers,

technicians,

and other personnel

during the course of the inspection.

Ins ection

To Verif

Licensee's

Scram Dischar

e Volume

Ca abi lit ,

Safet

Issues

Mana ement

S stem

SINS

Item 41

The inspector

reviewed the licensee's

actions to ensure that the scram

discharge

volume

(SDV) capability was in accordance

with long term

commitments.

These

commitments

were in response

to concerns

identified by

the

NRC in Multiplant Action (MPA) Item B-58.

In particular, the licensee

was required to improve the hydraulic coupling between

the

SDV headers

and

the

SDV instrumented

volume, to increase

the reliability of the float

switches

in the instrumented

volume,

and to modify the instrumented

volume

to prevent

damage to the level sensors

by hydrodynamic forces

and water

hammer.

The inspector

reviewed the final safety analysis

report

(FSAR)

and Drawing

N-528, Revision 45, "Flow Diagram, Control

Rod Drive System," to determine

the hydraulic coupling between

the headers

and the instrumented

volume.

The inspector verified that the design basis for the scram discharge

volume was 3.34 gallons

per rod drive unit.

This was identified as

an

acceptable

means of meeting the sufficient volume criterion established

in

General Electric letter

ER 54 dated

March 14,

1972.

Drawing M-528 showed

that the system

was designed with progressively larger piping ((from each

hydraulic control unit (HCU) to the instrumented

volume)) to minimize flow

restriction.

The only location where blockage

needed

to be assumed

in the

design analysis

(piping less

than

2 inches

in diameter)

was the discharge

line form the hydraulic control unit since the piping diameter

was 3/4

inch.

However, blockage

here would only cause, failure of one control rod

to insert.

This was determined to be an acceptable

consequence

for a

single failure and

was evaluated

as part of the design basis..

The

inspector

reviewed drawing N-528 to ensure

that the

SDV vent and drain

valves close

on

a loss of air and toured the control

room to verify that

there

was valve position indication for these valves.

The inspector

noted

that there were two vent and drain valves per

HCU, with each valve powered

from the two trains of the reactor protective

system

(RPS).

As

a result,

if the

RPS should lose

power the valves would fail closed

and were

protected

from a single active failure.

The inspector

reviewed the

FSAR and drawing N-528,

and walked

down the

accessible

portions of the system.

The inspector

found that the

safety-related

instrument level taps

were

on the instrumented

volume,

as

required,

and not connected

to the attached

piping.

The inspector

noted

that there were

6 level instruments

per

SDV.

These consisted of 2

Rosemount

level transmitters

and

4 Magnetrol float switches.

These level

instruments

were set at three different levels.

At the lowest level,

one

of the float switches

would actuate

to indicate that the volume was not

completely

empty during post-scram draining or to indicate that the

SDV

was starting to fill through leakage

accumulation at other times during

reactor operation.

At the second level,

a second float switch would

actuate

a rod withdrawal block when leakage

accumulated

to half the

capacity of the instrumented

volume.

The remaining

two float switches

and

the

two level transmitters

were interconnected

with the reactor protection

system to give

a scram

when

a high water level existed in the instrumented

volume.

The high level

was set to allow for sufficient volume for a full

reactor

scram.

The inspector

noted that there

was

one instrument tap for

every

two level instruments.

In addition,

each instrument

had its own

manually operated

isolation valves.

The header

piping arrangement

was

such that there would be

a relatively slow filling of the instrumented

volume to preclude

a water

hammer effect on the piping and

instrumentation.

The inspector considered

that using this instrument

arrangement

allowed for adequate

redundancy

and diversity.

The inspector

reviewed the following surv'eillance

procedures:

7.4. 1.3.1.4. 1, Revision 1, "Scram Discharge

Volume Operability Test"

7.4.3. 1. 1.17, Revision 1,

"RPS

SDV Level Channels

B and

D Channel

Calibration and Channel

Functional Test"

7.4.3.1.1. 16, Revision 1,

"RPS

SDV Level Channels

B and

D Channel

Calibration and Channel

Functional Test"

7.4. 1.3. 1.1, Revision 6,

"Scram Discharge

Volume Vent and Drain

Valves Operability"

7.4.3.1.1.61,

Revision 7,

"RPS-SDV Level Transmitter

(Channels

A 8

C)

Channel

Functional Test"

7.4.3.1.1.68,

Revision 4,

"RPS-SDV Level Transmitter

(Channels

B

& D)

Channel

Functional

Test"

7.4.3.1. 1.59,,Revision ll, "RPS-SDV Level Transmitter

(Channels

B 8

0) Calibration"

7.4.3. 1.1.60,

Revision ll, "RPS-SDV Level Transmitter

(Channels

A 5

C) Calibration"

The inspector verified that procedures

existed to perform surveillances

periodically in accordance

with the Technical Specification

(TS)

requirements.

The surveillance

procedures

appeared

to be of sufficient

detail to adequately test the level alarm and trip instrumentation.

They

demonstrated

that the scram instrument

response

and valve function tests

were performed at pressure

and temperature

and at approximately

505

control

rod density.

The procedures

also provided for proper restoration

of the system configuration

upon completion of testing.

As

a result of the inspector's

review of the system configuration,

the

inspector considered

that the system

was not susceptible

to

a single

failure; that it was designed

with adequate

volume; that it should

be

subject to minimal hydrodynamic forces

and water

hammer;

and, that the

instrument arrangement

allowed for adequate

redundancy

and diversity.

No violations or deviations

were identified.

Licensee's

Res

onse

To

NRC Bulletin 85-03,

"MOV Corwon

Mode Failures

Durin

P ant Transients

Due

o

Im ro er Sw>tc

Settln

s

The inspector

continued

a review of the licensee's

program for testing of

motor operated

valves

(MOVs) in response

to

NRC Bulletin 85-03.

In

particular,

the inspector

reviewed

the Supply System's

training program

for personnel

performing testing using motor operated

valve analysis

and

testing

(MOVATS) equipment.

In the past,

the licensee

sent their

personnel

to MOVATS Inc. for training on the use of the testing equipment.

Since the original inspection in this area,

the licensee

has instituted

their own training program.

The inspector

reviewed lesson

plan 82-ELE-1100-LP,

"MOVATS 2100/2150 Field

Data Acquisition and Analysis".

This training plan was designed

to expand

upon the

MOV actuator training course that was required for all personnel

performing

MOVATS testing.

The lesson

plan was constructed

to teach

personnel

how to perform signature acquisition according to the

manufacturers'pecification

and the plant procedure.

The inspector

found

that it provided

a review of motor operated

valve actuator operation

and

a

detailed description of the theory of operation

and the use (including

hands-on

experience)

of MOVATS equipment.

The inspector

found that the

licensee's

program for training personnel

closely followed the technical

content of the Limitorque operator

manual

and the

MOVATS Inc. training

manual.

Discussions

with the licensee

indicated that personnel

performing

MOVATS testing will be trained

and tested prior to the next refueling

outage at which time additional testing will take place.

The inspector

considered

that the licensee's

training program

was adequate

to train

personnel

performing

MOV testing.

Additional inspections will take place

during the upcoming refueling outage to ensure that the Supply System's

overall

program for performing

MOV testing is adequate.

No violations or deviations

were identified.

Licensee Actions

On Previous

NRC Ins ection Findin

s

a.

Closed)

Fol lowu

Item

87-11-01),

"Determination of Need for

us ment to

e

n er

ro ram

This item identified that the equipment

used for the

MOV testing

program

was not controlled under the Measuring

and Test Equipment

(MKTE) program.

The inspector

recommended

that the licensee

evaluate

the need for this equipment to be included

as

MSTE.

Discussions

with the licensee

revealed that the

NOVATS equipment

has

been incorporated

in the

MSTE program.

The equipment

was sent to

NOVATS Inc. for calibration prior to use during the upcoming

refueling outage

since the Supply System did not have the facilities

to perform the calibrations.

In addition, this equipment will be

recalibrated

on

a periodic basis.

The inspector considered

that the

licensee's

actions

were appropriate

to control the use of this

equipment.

Therefore, this item is closed.

Closed)

Followu

Item

87-21-01

"Review Of Work Performed

Under

Vita

NWR Pro

ram

This concern dealt with the level of detail specified for work on

vital maintenance

work request

(NWR)-1378 and the apparent

lack of

strict controls for work performed

on vital

MWRs in general.

NWR-1378

was

issued to repair the clutch mechanism for the valve operator

on

main steam

leakage control

(MSLC) valve 1A.

Due to various

problems

encountered

and the lack of strict controls established

in the

NWR,

the motor operator failed on July 20,

1987.

The inspector

observed

the licensee's

repair of the operator

on NSLC valve lA several

days

later.

However,

long term corrective actions

had not been

implemented until recently.

During this inspection,

the inspector

reviewed the licensee's

long

term corrective action which was to issue

Revision

8 to

PPN 1.3.7,

"Maintenance

Work Request".

This revision defined additional

controls (e.g., additional

reviews

and more definitive instructions

to personnel) for work to be performed

on vital NWRs.

The inspector

considered

that the procedure revisions

should lessen

the potential

for error when performing work specified in vital NWRs.

Therefore,

this item is closed.

Closed

Followu

Item

87-21-02

, "Review Of Licensee's

Con

s urat>on

ontro

ro ram

This item identified the inspector's

concern

over the licensee's

configuration control program.

In particular,

jumpers

were found

missing

by the licensee

in July,

1987 from 12 of 16 valves

in the

MSLC system for no apparent

reason.

These

jumpers

were specified to

be in place

by the applicable

upper tier drawings for the valves.

The inspector

noted that similar concerns

over the configuration

control

program were identified in the safety

system functional

inspection

(SSFI) that was conducted

in August,

1987.

For immediate

corrective actions,

the licensee

performed

a walkdown of motor

operated

valves of which the status

of the installed jumpers

was

indeterminate.

Long term corrective actions

were not implemented

until recently.

For long term corrective action,

the licensee

issued

a revision to

PPM 1.4. 1, "Plant Modifications".

This procedure revision was

designed

to better integrate

the activities of all groups

involved in

the modification process.

In addition,

the

new procedure

required

that the plant system engineer

perform

a post modification review

and/or walkdown of the system modification.

This walkdown will be

performed with support

form the Design Engineering,

Maintenance,

Operations,

and gA/gC as appropriate

to assure

completion of all

required work prior to returning the system to service.

The

licensee's

corrective actions

should minimize the potential for

future configuration control errors.

Therefore, this item is closed.

No violations or deviations

were identified.

5.

Licensee

Event

Re ort

LER

Followu

The inspector

reviewed the following LER packages

to determine

the extent

of the licensee's

corrective actions.

These

packages

included the

proposed modifications which the Supply System intends to implement during

the upcoming refueling outage.

Based

upon the inspector's

review of the

proposed corrective actions,

these

LERs are considered

closed.

(Closed)

LER 87-17 Revision 0,

"RWCU System Isolation

Due To

Demineralizer Influent Valve Leakage"

(Closed)

LER 88-02 Revision 0, "Part 21 Report Dealing With Potential

For An Unmonitored Release

Path Through Reactor

Core Isolation

Cooling System Piping"

No violations or deviations

were identified.

6.

Plant Tour

The inspector

conducted

a tour of the reactor building on March 8,

1988 to

assess

the licensee's

housekeeping

activities.

In general,

the building

cleanliness

was adequate.

However, the inspector identified

a discrepancy

as identified below.

The inspector

found that the bolts

had

been

loosened

and the cover

was

open for terminal

box TB-IR-68-2 Division 2 on the 548 foot elevation of

the reactor building.

The inspector

noted that

a sticker

had been

attached

to the front cover of the box identifying that it was under

PPN

10. 1.21,

"Maintenance of Environmentally gualified Equipment," control.

The inspector questioned

the licensee

as to why this box cover had

been

left open

and reviewed procedure

PPM 10. 1.21 to determine

environmental

qualification (Eg) requirements for terminal

boxes.

The inspector discussed

this item with the licensee

who identified that

the operators

entered

TB-IR-68-2 and other terminal

boxes

the previous

day

to perform Surveillance

Procedure

7.0.0, "Shift and Daily Instrument

Checks

(Nodes

1, 2, 3)."

In the case of TB-IR-68-2, the operators

were

required to check the

cam position for the containment inerting system

timer.

The inspector

reviewed

PPM 10.1.21

and found that step 10.1.21.7.B.6

specified that

Eg equipment that

was covered

by the Technical

Specifications

(TS) surveillance

program shall

have the special

requirements

for the equipment specified in the surveillance

procedure.

However, the inspector

found

no

Eg requirements

specified in surveillance

procedure

7.0.0.

Discussions

with cognizant licensee

personnel

indicated

that terminal

box TB-IR-68-2 was

a spray tight enclosure

only.

The

Eg

requirements

were intended for the seals

used

on conduit that penetrate

the bottom of this box.

These

seals

must

be reinstalled after completion

of work to ensure that water does

not flow through the conduit to the

electrical

component at the end of the conduit run.

For immediate corrective action,

the Instrumentation

and Control

technicians

closed the cover and tightened

the bolts for TB-IR-68-2.

In

addition, technicians

inspected

other boxes to ensure that they were

properly closed.

Although the case of TB-IR-68-2 did not appear to be of

any safety significance,

the inspector

expressed

concern to the Supply

System

management

that there

may be surveillance

procedures

that should

have

Eg requirements

specified in them but do not.

The licensee

management

stated that they would take steps

to ensure that

Eg

requirements

were met when performing surveillance

procedures.

The

licensee's

actions

on this matter will be reviewed in the future and is

identified as inspector

followup item (397/88-09-01).

No violations or deviations

were identified.

On-Site Review of Events

On March 9, 1988, the Supply System identified to the

NRC the possible

desire for a temporary waiver to TS 3.8.2.1 since they could not meet the

surveillance

requirement limits specified in Table 4.8.2.1-1.

In

particular,

24VDC battery

BO-1B had

a pilot cell specific gravity below

the 1.200 Category

"A" limit and

an overall battery average specific

gravity of 1. 190 which was below the 1.205 Category

"B" limit.

However,

at no time was the

TS allowable value exceeded.

The reason for the low

specific gravity on this battery

was determined

to be stratification as

a

result of the discharge that took place the, previous

week while performing

breaker testing.

At that time, the power supply for the battery charger

was

removed

from service

and battery

BO-1B had to act as the power supply

for various

DC equipment.

The licensee

contacted

the vendor to determine

if any corrective actions

could be taken for the low gravities experienced

in each of the jars for battery B0-1B.

The result of the discussion with the vendor

led the licensee

to take

specific gravities at various heights in each of the battery jars

and then

average

the values (in each jar) to determine its actual specific gravity.

The results of the measurements

indicated that the specific gravity for

the pilot cell

and the average specific gravity for the battery

was

significantly higher than the Category

"A" and "B" limits.

As

a result,

the Supply System contacted

the

NRC to specify that the

need for a

temporary

TS waiver was not necessary.

The major concern with the electrolyte stratification was idehtified to be

an accelerated

degradation

of the battery jars thereby reducing their

expected lifetime.

As

a result of this concern,

the Supply System

began

an evaluation to determine

the best method for reducing stratification.

The inspector will monitor the licensee's

progress

in this during future

inspection efforts.

No violations or deviations

were identified.

On March ll, 1987,

an exit meeting

was held with the licensee

representatives

identified in paragraph

1.

The inspector

summarized

the

inspection

scope

and findings as described

in this report.