MONTHYEARML23271A1542023-09-28028 September 2023 NRR E-mail Capture - Point Beach Nuclear Plant, Units 1 and 2 - Acceptance of License Amendment Request to Revise TS 5.5.17, Pre-Stressed Concrete Containment Tendon Surveillance Program ML23208A3072023-07-27027 July 2023 NRR E-mail Capture - Point Beach Nuclear Plant, Units 1 and 2 - Acceptance of Relief Requests Regarding I6-RR-1, I6-RR-2, and I6-RR-3 (EPIDs L-2023-LLR-0030, L-2023-LLR-0031, L-2023-LLR-0032) ML23173A1522023-06-22022 June 2023 Request for Additional Information NextEra Fleet Emergency Plan Amendment Request ML23136A2782023-05-0505 May 2023 Email to R Coffey Point Beach SLRA Second Annual Update - Request for Additional Information Set 1 ML23122A0132023-05-0101 May 2023 NRR E-mail Capture - Point Beach 1 & 2 - Final RAI - License Amendment Request Regarding Risk-Informed Approach to Address GSI-191 ML23109A1862023-04-19019 April 2023 and Turkey Point Acceptance of Requested Licensing Action Proposed Alternative to Asme Section XI Authorizing Implementation of Asme Code Case N-752-1 ML23033A0292023-01-31031 January 2023 NRR E-mail Capture - Point Beach 1 & 2 - Final RAI (Volume 2) - License Amendment Request Regarding TSTS-505 ML22354A1612022-12-20020 December 2022 NRR E-mail Capture - Point Beach 1 & 2 - Final RAI - License Amendment Request Regarding TSTS-505 ML22291A3692022-10-18018 October 2022 NRR E-mail Capture - Point Beach Nuclear Plant, Units 1 and 2 - Acceptance of License Amendment Request to Use Beacon Power Distribution Monitoring System ML22249A0052022-09-0202 September 2022 NRR E-mail Capture - Point Beach Nuclear Plant, Units 1 and 2 - Acceptance of License Amendment and Exemptions Regarding Risk-Informed Approach to Address GSI-191 ML22229A1052022-08-17017 August 2022 Response to Questions Regarding Point Beach Nuclear Power Plant with Attachment ML22229A1022022-07-18018 July 2022 Original Request - Questions Regarding Point Beach Nuclear Power Plant ML22196A0062022-07-15015 July 2022 NRR E-mail Capture - Point Beach Nuclear Plant, Units 1 and 2 - Acceptance of Requested Licensing Action TSTF-505, Revision 2, Provide Risk Informed Extended Completion Times - RITSTF Initiative 4b ML22094A0802022-04-0404 April 2022 NRR E-mail Capture - Point Beach Nuclear Plant, Units 1 and 2 - Acceptance of Requested Licensing Action License Amendment Request to Adopt TSTF-366 ML22006A2762022-01-0606 January 2022 SLR - FW: Subsequent License Renewal of Point Beach Nuclear Plant Unit Numbers 1 and 2, Manitowoc County, Wisconsin ML22006A1952022-01-0606 January 2022 SLR - FW: (External_Sender) 3 Additional Organizations Endorsing the Coalition (Now 50 Organizations, and 27 Individuals) Public Comments NRCs Dsgeis on NextEra Point Beach Nuclear Power Plant Subsequent License Renewal, D ML22006A2012022-01-0606 January 2022 SLR - FW: Comments of Michael J Keegan on Dseis Point Beach ML22004A1672022-01-0404 January 2022 SLR - Ref: Point Beach ML22004A3192022-01-0404 January 2022 SLR - FW: Point Beach ML22004A0012022-01-0404 January 2022 SLR - FW: Comments of Michael J Keegan on Dseis Point Beach ML22006A1942022-01-0404 January 2022 SLR - (External_Sender) 3 Additional Organizations Endorsing the Coalition (Now 50 Organizations, and 27 Individuals) Public Comments NRCs Dsgeis on NextEra Point Beach Nuclear Power Plant Subsequent License Renewal, Docke ML22004A3212022-01-0404 January 2022 SLR - FW: Comments of Michael J Keegan on Dseis Point Beach ML22004A3202022-01-0404 January 2022 SLR - FW: (External_Sender) 3 Additional Organizations Endorsing the Coalition (Now 50 Organizations, and 27 Individuals) Public Comments NRCs Dsgeis on NextEra Point Beach Nuclear Power Plant Subsequent License Renewal, D ML22004A1732022-01-0404 January 2022 SLR - FW: (External_Sender) 3 Additional Organizations Endorsing the Coalition (Now 50 Organizations, and 27 Individuals) Public Comments NRCs Dsgeis on NextEra Point Beach Nuclear Power Plant Subsequent License Renewal, D ML22004A3182022-01-0404 January 2022 SLR - FW: EPA Comment Letter - Point Beach SEIS ML22006A1992022-01-0303 January 2022 SLR - (External_Sender) Comments of Michael J Keegan on Dseis Point Beach ML22004A3172021-12-21021 December 2021 SLR - (External_Sender) EPA Comment Letter - Point Beach SEIS ML21362A6822021-12-17017 December 2021 SLRA Safety RAIs Set 14 Final Email ML21362A6712021-12-15015 December 2021 SLRA Safety RAIs Set 13 Final Email ML22006A2752021-12-0202 December 2021 SLR - (External_Sender) Subsequent License Renewal of Point Beach Nuclear Plant Unit Numbers 1 and 2, Manitowoc County, Wisconsin ML21341A6102021-11-16016 November 2021 SLRA Safety RAI Set 12 Final Email ML21314A4212021-11-10010 November 2021 Fws to NRC, Concurrence with ESA Determination for Point Beach Subsequent License Renewal ML21307A1522021-11-0909 November 2021 NRC to Fws, Request for Concurrence with Endangered Species Act Determinations for Point Beach Subsequent License Renewal ML21287A0852021-10-14014 October 2021 SLRA Safety RAI Set 11 Final Email ML21279A1202021-10-0505 October 2021 Email: Wi Shpo Review Point Beach Nuclear Plant SLR ML21286A6032021-10-0505 October 2021 SLRA Safety RAIs Set 10 Final Email ML21273A0232021-09-0202 September 2021 SLRA Safety RAI Set 9 Final Email ML21242A2282021-08-27027 August 2021 SLRA Draft Safety RAI Set 9 ML21242A2292021-08-27027 August 2021 SLRA Draft Safety RAI Set 9 Email ML21242A2462021-08-26026 August 2021 SLRA Safety RAIs Set 8 Final Email ML21242A2222021-08-23023 August 2021 SLRA Draft Safety RAI Set 8 ML21242A2232021-08-23023 August 2021 SLRA Draft Safety RAI Set 8 Email ML21242A2192021-08-20020 August 2021 SLRA Safety RAI Set 7 Final Email ML21242A2132021-08-13013 August 2021 SLRA Safety RAIs Set 7 Draft Email ML21242A2142021-08-13013 August 2021 SLRA Safety RAIs Set 7 Draft ML21242A2042021-08-12012 August 2021 SLRA Safety RAIs Set 5 Final Email ML21224A2042021-08-12012 August 2021 LTR-21-0225-1-RIII. Time Sensitive: Request for Further Inspection ML21242A0142021-08-12012 August 2021 SLRA Safety RAIs Set 6 Final Email ML21242A2382021-08-12012 August 2021 SLRA Safety RAIs Set 6 Final Email ML21242A0112021-08-0909 August 2021 SLRA Draft Safety RAIs Set 6 Email 2023-09-28
[Table view] |
Text
NRR-PMDAPEm Resource From: Chawla, Mahesh Sent: Wednesday, October 04, 2017 2:14 PM To: Schultz, Eric; Locke, Kim (Kim.Locke@nexteraenergy.com); Manthei, Scott; Kilby, Gary; Catron, Steve (Steve.Catron@fpl.com)
Subject:
LIC-109 Acceptance Review Supplement Request - Point Beach Units 1 and 2 LAR 287 -
Application to adopt 10 CFR 50.69, "Risk-Informed Categorization and Treatment of Structures (SSCs) for Nuclear Power Plants" - MG0196/MG0197
Dear Mr. Schultz:
By letter dated August 31, 2017 (ADAMS Accession No. ML17243A201), NextEra Energy Point Beach, LLC submitted a license amendment request for the Point Beach Nuclear Plant, Units 1 and 2. The proposed amendment would revise the licensing basis by adding a license condition to allow for the implementation of the provisions of Title 10 of the Code of Federal Regulations (10 CFR) Section 50.69, "Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors."
The purpose of this letter is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this LAR. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.
The NRC staff has reviewed your application and concluded that the information delineated below is necessary to enable the NRC staff to make an independent assessment regarding the acceptability of the proposed amendment request in terms of regulatory requirements and the protection of public health and safety and the environment.
In order to make the application complete, the NRC staff requests that licensee supplement the application to address the information requested below by a date to be agreed upon during a teleconference to discuss this information. This will enable the NRC staff to complete its detailed technical review. If the information responsive to the NRC staffs request is not received by the above date, the application will not be accepted for review pursuant to 10 CFR 2.101, and the NRC staff will cease its review activities associated with the application. If the application is subsequently accepted for review, you will be advised of any further information needed to support the NRC staffs detailed technical review by separate correspondence.
Supplemental Information Request
- a. Clarify whether a high winds hazard screening evaluation or the high winds PRA will be used during the safety significance categorization process consistent with Section 5.4 of NEI 00-04, as endorsed by RG 1.201, Revision 1.
- b. If the high winds PRA will be used during the safety significance categorization process, describe the peer review process applied to the high winds PRA, indicate whether it was a full-scope peer review and identify the guidance used to perform this peer review (e.g., ASME/ANS RA-Sa 2009, RG 1.200, Revision 2). Include any necessary gap- or self-assessments if current guidance/standards were not 1
used in the peer review. In addition, provide all F&Os characterized as findings from the peer review of the high winds PRA. For each F&O, include details of its disposition or why not meeting the corresponding Capability Category II requirements has no impact on the application.
- c. If a high winds hazard screening evaluation will be used during the safety significance categorization process, describe this screening evaluation. Also, discuss how this evaluation is consistent with the screening criteria in Section 6-2 of ASME/ANS RA-Sa 2009, as qualified by RG 1.200, Revision 2, and reflects the current as-built, as-operated plant.
Please arrange a teleconference to discuss this information with the NRC staff. If you have any questions, please contact me. Thanks Mahesh Chawla Project Manager Phone: 301-415-8371 Fax: 301-415-1222 mahesh.chawla@nrc.gov 2
Hearing Identifier: NRR_PMDA Email Number: 3756 Mail Envelope Properties (Mahesh.Chawla@nrc.gov20171004141300)
Subject:
LIC-109 Acceptance Review Supplement Request - Point Beach Units 1 and 2 LAR 287 - Application to adopt 10 CFR 50.69, "Risk-Informed Categorization and Treatment of Structures (SSCs) for Nuclear Power Plants" - MG0196/MG0197 Sent Date: 10/4/2017 2:13:44 PM Received Date: 10/4/2017 2:13:00 PM From: Chawla, Mahesh Created By: Mahesh.Chawla@nrc.gov Recipients:
"Schultz, Eric" <Eric.Schultz@nexteraenergy.com>
Tracking Status: None "Locke, Kim (Kim.Locke@nexteraenergy.com)" <Kim.Locke@nexteraenergy.com>
Tracking Status: None "Manthei, Scott" <Scott.Manthei@nexteraenergy.com>
Tracking Status: None "Kilby, Gary" <Gary.Kilby@fpl.com>
Tracking Status: None "Catron, Steve (Steve.Catron@fpl.com)" <Steve.Catron@fpl.com>
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 4240 10/4/2017 2:13:00 PM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received: