Requests ACRS Subcommittee Meeting Be Delayed Only 4 Wks Since Response to Geology Questions Submitted 4 Wks Late. Addl Delay Could Generate Another Series of Questions Depleting Util Resources But Resulting in No Plant Changes
Date released: 06/27/2018 Download: ML17276B508


Complains That Siting Issues Resolved During CP Proceedings Being Unnecessarily re-evaluated as Part of OL Review. Reviews Nonproductive Since Plant Mods Totally Impractical. Siting Review Should Be Concentrated Into CP Stage
ML17276B510
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 06/11/1982
From: Ferguson R
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
To: PALLADINO N J
NRC COMMISSION (OCM)
References
Download: ML17276B510 (5)
Requests ACRS Subcommittee Meeting Be Delayed Only 4 Wks Since Response to Geology Questions Submitted 4 Wks Late. Addl Delay Could Generate Another Series of Questions Depleting Util Resources But Resulting in No Plant Changes
ML17276B506
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 06/11/1982
From: Bouchey G
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
To: DENTON H R
Office of Nuclear Reactor Regulation
References
Download: ML17276B506 (6)