GO2-82-538, Complains That Siting Issues Resolved During CP Proceedings Being Unnecessarily re-evaluated as Part of OL Review. Reviews Nonproductive Since Plant Mods Totally Impractical. Siting Review Should Be Concentrated Into CP Stage

From kanterella
(Redirected from ML17276B510)
Jump to navigation Jump to search
Complains That Siting Issues Resolved During CP Proceedings Being Unnecessarily re-evaluated as Part of OL Review. Reviews Nonproductive Since Plant Mods Totally Impractical. Siting Review Should Be Concentrated Into CP Stage
ML17276B510
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 06/11/1982
From: Ferguson R
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
To: Palladino N
NRC COMMISSION (OCM)
Shared Package
ML17276B508 List:
References
GO2-82-538, NUDOCS 8206210270
Download: ML17276B510 (5)


Text

82062i0270 820&ii PDR ADOCK 05000397 A

PDR It Mfashington Public Power Supply System P.O. Box 968 3000 George Washington Way Richland, Washington 99352 (509) 372-5000 G02-82-538 Docket No. 50-397 June ll, 1982 The Honorable N. J. Palladino Chairman U.

S. Nuclear Regulatory Commission Washington, D.

C.

20555

Dear Hr. Chairman:

Subject:

OPERATING LICENSE REVIEWS OF SITING ISSUES Based on Supply System experience over the past few years, I believe that reviews of siting issues which were resolved during Construction Permit proceedings are being unnecessarily reevaluated as part of the Operating License reviews.

These in-depth Operating License reviews deplete both utility and NRC financial and manpower resources and are largely nonproductive with respect to improved plant safety'.

It is my beltef that changes in NRC rules and policy are needed in this regard.

The reviews of the seismic design basis for our WNP-2 plant provide an excellent example of the problem that concerns me.

WNP-2 is located on the Hanford Reservation near Richland, Washington, and is currently more than 90 percent complete.

Precedent for the 0.25g seismic design basis for the Hanford site was established in 1970 by DOE (then AEC) and NRC reviews associated with the Fast Flux Test Facility.

In 1973, reviews of the WNP-2 Construction Permit Application reconfirmed adequacy of this design basis.

In 1975 and 1977 respectively, reviews associated with issuance of Construction Permits for WNP-1 and WNP-4 again confirmed the 0.25g design value.

Despite these four previous comprehensive

reviews, the NRC staff has undertaken an exhaustive reevaluation of Hanford geology and seismology as part of the Operating License review for WNP-2.

We estimated that the Supply System expended about 8.3 million dollars in seismic studies to support, obtaining Construction Permits for our Hanford plants, and an additional 9.3 million dollars on evaluation of geology and sei smi c issues since that time.

These estimates do not include the cost of extensive programs sponsored by NESCO, associ ated with the Skagit/Hanford plant and by DOE related to their Hanford facilities.

The review of WNP-2 seismic issues is continuing

today, and this issue has twice caused postponement of the ACRS meeting

1

NJ Palladino Page 2

June ll, 1982 Operating License Reviews of Siting Issues to.review the WNP-2 Application.

Yet, there is no significant new information (such as an unexpected major earthquake) that would justify such a massive review effort.

Certainly as a result of these multi-million dollar efforts, the level of confidence in the Hanford site has been improved somewhat since issuance of the Construction Permit.

However, the basis for granting the CP remains sound.

The level of confidence in the adequacy of the seismic design basis was sufficient for issuance of CPs for our three Hanford plants, and in the absence of significant new information should be adequate for operation of these plants.

Changes in state-of-the-art methodology for assessing site

geology, seismology, meterology, etc.,

should not be sufficient justification for undertaking a major effort to reevaluate previous decisions regarding a plant's design basis' should note, that I do not question the technical competence or good intention of the individual reviewers, or even the validity of individual questions when viewed in isolation.

However, when viewed from the broader perspective of multiple reviews of a site at a time when modifications of e plant's design basis is totally impractical, the efforts associated with these reviews seem unnecessary and nonproductive.

In our view, the expendi ture of more than 9 million dollars associated with post-Construction Permit review of seismic issues at Hanford has been largely a wasted effort in that it did not, and will not, serve to enhance the safety margins of our Hanford plants.

Instead it has the potential to result in a net decrease in safety due to the drain of resources involved.

In recent

months, a concern has been expressed that excessive regulatory demands on utilities may be resulting in an overall deleterious effect on nuclear plant safety.

I believe that modification of rules and revision of NRC staff review policies to concentrate on comprehensive reviews of siting at the Construction Permit proceedings, and elimination of exhaustive reviews and litigation of such issues at the Operating License stage, would be a positive step toward reducing the demands on the utility industry without impacting plant safety.

Such a change would be somewhat comparable to a recent rule which eliminated the review of alternatives to the plant at the Operating License stage.

The detailed reviews of siting issues have evolved in recent

years, I believe, primarily because of the potential for detailed public hearings on these issues at the Operating License stage.

However, hearings on such issues should logically be limited to

NJ Palladino Page 3

June 11',

1982 Operating License Reviews of Siting Issues the CP stage (prior to major construction efforts and financial commitments) except when there is significant new information'uch a change

would, I believe, be fully consistent with the intent of the Atomic Energy Act and NRC regulations, and should be implemented by the Commission as soon as possible.

I am hopeful you will find these comments constructive in nature as they are intended, and I would be happy to make myself or members of my staff available to provide additional information on this matter as necessary.

Yery truly yours,

~XX R.

L. Fer son Managing Director GDB/sm cc:

N Reynolds C Walske D&L AIF

0 w.saw+

E 4'

I'