Docket No. 50-397
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION V
1990 N. CALIFORNIABOULEVARD
SUITE 202, WALNUTCREEK PLAZA
WALNUTCREEK, CALIFORNIA94596
February
18,
1981
V2@g
'ZOil,~
Washington Public Power Supply System
P. 0.
Box 968
Richland,
99352
Attention:
Mr. R.
G. Matlock
Program Director,
WNP-2
Gentlemen:
Subject:
NRC Inspection
This refers to the inspection
conducted
by Mr. A. Toth of this office during
January
1981 of activities authorized
by
NRC Construction Permit No. CPPR-93,
and to the discussion of our findings held by Mr. Toth with Mr. R. Johnson
and other members of your staff at the conclusion of the inspection.
Areas
examined during this inspection are described in the enclosed
inspection
report.
Within these areas,
the inspection consisted of selective examinations
of procedures
and representative
records,
interviews with personnel,
and
observations
by the inspector.
No items of noncompliance" with NRC requirements
were identified within the
scope of this inspection.
In accordance
with Section 2.790 of the NRC's "Rules of Practice," Part
2,'itle
10,
Code of Federal
Regulations,
a copy of this letter and the enclosed
inspection report will be placed in the NRC's Public Document
Room.
If this
report contains
any information that you believe to be proprietary, it is
necessary
that you submit a written application to this office, within 20
days of the date of this letter, requesting that such information be withheld
from public disclosure.
The application must include
a full statement of
the reasons
why it is claimed that the information is proprietary.
The application
should
be prepared
so that any proprietary information identified is contained
in an enclosure to the application, since the application without the enclosure
will also
be placed in the Public Document
Room. If we do not hear
from
you in this regard within the specified period, the report will be placed
in the Public Document
Room.
tl
4
I
/
"ti~
- IP
February
18,
1981
Should you have
any questions
concerning this inspection,
we will be glad
to discuss
them with you.
Sincerely,
Enclosure:
IE Inspection Report
No. 50-397/81-01
G. S.
Spe cer, Chief
Reactor Construction
and Engineering
Support
Branch
cc w/enclosure:
M. E. Witherspoon, guality Assurance
Director
W. C. Bibb, Project Manager
WNP-2 Project