Monthly Operating Rept for Apr 1995 for Re Ginna Nuclear Power Plant
ML17263B055
Person / Time
Site: Ginna Constellation icon.png
Issue date: 04/30/1995
From: Walden J, Widay J
ROCHESTER GAS & ELECTRIC CORP.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9505180246
Download: ML17263B055 (7)


Text

P RIQRITY ACCELERATED RIDS PROCESSING REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)

FACIL:50-244 Robert Emmet Ginna Nuclear Plant, Unit 1, Rochester G

AUTH.NAME AUTHOR AFFILIATION WALDEN,J.

Rochester Gas

& Electric Corp.

WIDAY,J.A.

Rochester Gas

& Electric Corp.

RECIP.NAME RECIPIENT AFFILIATION DOCKET N

05000244

SUBJECT:

Monthly operat'or Apr 1995 for RE Ginna Nuclear Power Plan

/950509

. r.

DISTRIBUTION CODE: IE24D COPIES RECEIVED:LTR ENCL 2 SIZE:

TITLE: Monthly Operating Report (per Tech Specs NOTES:License Exp date in accordance with 10CFR2,2.109(9/19/72).

0 05000244 R

RECIPIENT ID CODE/NAME PD1-1 PD INTERNAL: AEOD/SPD/RRAB NRR/DISP/PIPB RGN1 EXTERNAL: LITCO BRYCE,J H

NRC PDR COPIES LTTR ENCL 1

1 1

1 1

1 1

1 1

1 1

1 RECIPIENT ID CODE/NAME JOHNSON,A FILE CE EER~O NRR/DOPS/OECB NOAC COPIES LTTR ENCL 1

1 1

1 1

1 1

1 D

C U

N YOTE TO ALL"RIDS" RECIPIENTS:

PLEASE HELP US TO REDUCE iVKSTE!COYTACTTIIE DOC!.'MENTCONTROL DESK, ROOK! PI -37 (EAT. 504-2083 ) TO F LIXIINATE YOI'R NAZIL F ROTI DISTRIBUTIONLIS'I'S FOR DOCI, NIEX'I'S5'OL'ON"I'L'f:.D!

TOTAL NUMBER OF COPIES REQUIRED:

LTTR 10 ENCL 10

I EN/II iSZS Z8/

II I/S/III!l ROCHESTER GAS AND ELECTRIC CORPORATION o 89 EAST AVENUE, ROCHESTER, N.Y. 14649-0001 TORE STAVE TELEPHONE AREA CODE 7VVI 546-2700 GINNA STATION May 9, 1995 US Nuclear Regulatory Commission Document Control Desk

.Washington, DC 20555

Subject:

Dear Sir:

Monthly Report for April, 1995 Operating Status Information R.

E. Ginna Nuclear Power Plant Docket No. 50-244 Pursuant to our Technical Specification 6.9.1, attached herewith is the monthly operating status report for Ginna Station for the month of April, 1995.

Very truly yours, s

h A. Wi a t Manager JAW:tjn Attachments c:

Mr. Thomas T. Martin NRC (1)

,950518024b 950430 PDR

ADOCK'05000244

-R PDR

II I 0

A j

VX003"z-It

?E~g 1

OPERATING DATAREPO%

50-244 COMPLETED BY Ma 9 1995 V

John V. Walden TELEPHONE 15)5244446 Ext.588 Notes

1. Unit Name:

R.E. GINNANUCLEAR POWER PLANT

2. Reporting Period:

A ril 1995 3.

Licensed Thermal Power (MWt):

1520 4.

Nameplate Rating (Gross MWe):

490 5.

Design Electric Rating (Net MWe):

470 6.

Maximum Dependable Capacity (Gross MWe):

490 7.

Maximum Dependable Ca pacity (Net MWe):

470 8.

IfChanges Occur in Capacity Rating (Items Number 3 Through 7) Since Last Report, Give Reason:

9.

Power Level to Which Restricted, IfAny (Net MWe:

10. Reason For Restrictions, IfAn:

This Month Yr:to-Date Cumulative-

11. Hours In Reported Period
12. Number of hours Reactor Was Critical
13. Reactor Reserve Shutdown Hours
14. Hours Generator On-line
15. Unit Reserve Shutdowri Hours
16. Gross Thermal Energy Generated (MWH)
17. Gross Electrical Energy Generated (MWH)
18. Net Electrical Energy Generated (MWH)
19. Unit Service Factor (%)
20. Unit AvailabilityFactor (%)
21. Unit Capacity Factor (using MDC Net) (%)
22. Unit Capacity Factor (using DER Net) (%)
23. Unit Forced Outage Rate (%)

719.0 28.9 0.0 0.0 0.0 9.0 0.0 0.0 0.0 0.0 0.0 0.0 ERR 2879.0 2056.3 0.0 2027.1 0.0 3007884.0 1017317.0 967351.0 70.4 70.4 71.5 71.5 0.0 222887.0 177872.1 1687.6

'74999.4 8.5

'48523121.0 82251369.0 78076581.0 78.5 78.5 75.6 75.6 5.6

24. Shutdowns Scheduled Over Next 6 Months (Type, Date and Duration of Each):

Refuelin and Maintenance Started 3/26/95 Finished 5/4/95 Duration 39 da

25. IfShutdown At End of Report Period, Estimate Date of Startup:
26. Units In Test Status (Prior to Commercial Operation):

Forcast INITIALCRITICALITY INITIALELECTRICITY COMMERCIALOPERATION

'UMULATIVETOTALCOMMENCINGJANUARY1 ~ 1975

'*CUMULATIVETOTALCOMMENCINGNOVEMBER8, 1969

'NITIN REFUELING SHUTDOWN

AVERAGE DAILY UNIT POWER LEVEL DOCKET NO: 50-244 UNIT: R.E.

Ginna Nuclear Power Plant DATE: Ma 9

1995 COMPLETED BY:

John Walden TELEPHONE:

315 524-4446 Ext.

588 MONTH A ril 1995 DAY AVERAGE DAILY POWER LEVEL (MWe-Net) 1 ~

2 ~

3

~

4 ~

5.

6.

7 ~

8.

9.

10

'AY AVERAGE DAILY POWER LEVEL (MWe-Net) 17

'8.

19.

20.

21 ~

22

'3

'4.

25.

26.

12.

13

'4.

15.

16.

27.

28.

29.

30.

31 ~

INSTRUCTIONS On this format, list the average daily unit power level in MWe-Net for each day in reporting month.

Compute to the nearest whole megawatt.

REPORT MONTH 1995 UNIT SHUTDOWN AND POWER REDUCTIONS DO(:KET NO.

UNlTNAhfE R.E. GINNA NUCLEAR POWER PLANT DATE 9

1995

(:OhfPLETED l3Y ohn V. Walden TELEPllON.

588 Ho.

Date 0

o a

0 n ~

e4 C0 o

Cl Pl Ol s-0 c

u oo m 0 own c X

0n Licensee Event Report ll Ew O

Cl 0

EA a

Cl EO e

Q o0 Cause L Corrective Action to Prevent Recurrence 95-03 3/26/95 S

852.0 C

Annual Refueling 1

F: Forced S:

Scheduled REV. 4/85 4949 Reason:

A-Equipment Failure (Explain)

B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training 8c License Examination F-Administrative G-Operational Error (Explain)

H-Ocher (Explain) hfethod:

1-hfanual 2-hfanual Scram.

3-Automatic Scram.

lf-Other (Explain)

Fxhibit G - Instructions for Preparation of Data Entry Sheets for Licensee Event Report (LER) File (NUREG-0161)

Exhibit 1 - Same Source

NARRATXVE

SUMMARY

OP OPERATING EXPERIENCE DOCKET NO: 50-244 UNIT: R.E.

Ginna Nuclear Power Plant DATE: Ma 9

1995 COMPLETED BY:

John Walden TELEPHONE:

315 24-4446 Ext.

588 MONTH A ril 1995 On March 26, the unit was taken off line as scheduled for its annual maintenance and refueling outage.

The unit remained off line during the entire month of April.