ACCELERATED DISTRIBUTION DEMONSTRATION SYSTEM REGULAT(
INFORMATION DISTRIBUTION+STEM (RIDE)
ACCESSION NBR:9206240172 DOC.DATE: 92/05/31 NOTARIZED: NO DOCKET ¹ FACIL 50-.244 Robert Emmet Ginna Nuclear Plant, Unit 1, Rochester G
05000244 AUTII. NAME AUTHOR AFFILIATION DODGE,R.E.
Rochester Gas a Electric Corp.
MECREDY,R.C.
Rochester Gas 6 Electric Corp.
RECIP.NAME RECIPIENT AFFILIATION
SUBJECT:
Monthly operating rept for June 1992 for RE Ginna NPP.W/
920616 ltr.
DISTRIBUTION CODE:
ZE24D COPIES RECEIVED:LTR i ENCL i SIZE:
TITLE: Monthly Operating Report (per Tech Specs)
NOTES:License Exp date in accordance with 10CFR2,2.109(9/19/72).
R D
05000244
/
RECIPIENT ID CODE/NAME PDl-3 LA JOHNSON,A INTERNAL: AEOD/DOA NRQQD BEB10 EG FILE 01 EXTERNAL: EGGG BRYCE,J.H NSIC COPIES LTTR ENCL 3
3 1
1 1
1 1
1 1
1 1
1 1
1 RECIPIENT ID CODE/NAME PD1-3 PD AEOD/DSP/TPAB NRR/DOEA/OEAB RGNl NRC PDR COPIES LTTR ENCL 1
1 1
1 D
D
~
jt 7)e'f79'P(l D
NOTE fO ALL"RIDS" RECIPIENTS:
D D
PLEASE HELP US TO REDUCE WASTE! CONTACT THE DOCUMENT CONTROL DESK, ROOM Pl-37 (EXT. 20079) TO ELIMINATEYOUR NAMEFROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED!
TOTAL NUMBER OF COPIES REQUIRED:
LTTR 14 ENCL 14
0 P
I'
rtt ZNFIIZg I/SIC q/ PIE/gli/ rrm r'////Su I
//ZIF//ri'OCHESTER GAS AND ELECTRIC CORPORATION ROBERT C. MECREDY Vlcc President Clnna Nudear Production 89 EAST AVENUE, ROCHESTER N. K 14649-0001 TELEPHONE AltEACODE 71B 546 2700 GINNA STATION June 16, 1992 US Nuclear Regulatory Commission Document Control Desk Washington, DC 20555
Subject:
Monthly Report for May 1992 Operating Status Information R. E. Ginna Nuclear Power Plant Docket No. 50-244
Dear Sir:
Pursuant to our Technical Specification 6.9.1, attached herewith is the monthly operating status report for Ginna Station for the month of May 1992.
Very truly yours, Robert C. Mecredy Attachments c:
Mr. Thorn s T. Martin NRC (1) gu N4~~
9 6,0~0.4.
920b240i72 920b'ib PDR'"'ADQCK 05000244 R
PDR.
II II I,
S II II.
Il h
OPERATING DATA REPORT DOCKET HO.
50-244 DATE June 5
1992 COMPLETED BY Robert E. Dodge OPERATING STATUS TELEPHOHE 315 524.4446 ext. 396 1 ~
2.
3.
4.
5.
6.
74 8.
Unit Name:
R.E.
GINNA NUCLEAR POWER PLANT Reporting Period:
Ma 1992 Licensed Thermal Power (MWt):
Nameplate Rating (Gross MWe):
Design Electrical Rating (Net MWe):
Maximm DependableCapacity (Gross MWe):
Maximm Dependable Capacity (Net MWe):
If Changes Occur in Capacity Ratings (Items Notes:
The unit was placed on the line on May 11, 1992 at 2212 and remained there at the end of the report period.
1520 490 470 490 470 Nunber 3 Through 7) Since Last Report, Give Reasons:
9.
Power Level to Which Restricted, If Any (Net MWe):
10.
Reasons For Restrictions, If Any:
This Month Yr. ~ to-Date Cwaiative 11
'2.
13.
14.
15.
16.
17.
18.
19.
20.
21
~
22.
23.
Hours In Report Period Nunber of Hours Reactor Was Critical Reactor Reserve Shutdown Hours Hours Generator On-Line Unit Reserve Shutdown Hours Gross Thermal Energy Generated (MWH)
Gross Electrical Energy Generated (MWH)
Net Electrical Energy Generated (MWH)
Unit Service Factor Unit Availability Factor Unit Capacity Factor (Using MDC Net)
Unit Capacity Factor (Using DER Net)
Unit Forced Outage Rate 744 536.62 481.75 610 650 207 876 196 657 64.75%
64.75%
56.24%
56.24%
3647 2549.09 2465.50 3 367 002 1 139 604 1 079 684 67.60%
67.60%
62.%C 62.99/
3.58/
197 753.45 155 880.05 1 687.55 153 170.88 8.5 216 581 515 71 469 211 67 832 231 77.61%
74.34%
74.34%
6.01%
24.
Shutdowns Scheduled Over Next 6'Months (Type, Date and Duration of Each):
25.
If Shut Down At End Of Report Period, Estimated Date of Startup:
05-09.92 26.
Units In Test Status (Prior to Comnerclai Operation):
Forecast Achieved INITIAL CRITICALI7Y INITIAL ELECTRICITY COMMERCIAL OPERATION
- CUMULATIVETOTAL COMMENCING JANUARY 1, 1975
- CUMULATIVETOTAL COMMENCING NOVEMBER 8, 1969
0
/
t t
AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.
50-244 UNIT R.E.
Ginna Nuclear Power Plant DATE June 15 992 COMPLETED BY Robert E.
D dge TELEPHONE 1
315 524-4446
. ext.
396 MONTH Ma 1992 DAY AVERAGE DAILY POWER LEVEL (MWe-Net)
DAY AVERAGE DAILY POWER LEVEL (MWe-Net) 17.
451 2
~
18.
478 3
~
19'78 4 ~
20.
478 5.
-12 21.
477 6.
-15 22.
477 7 ~
-14 23.
476 8
~
-14 24.
474 9 ~
-14 25.
474 10.
-15 26.
477
-12 27.
478 12.
106 28.
480 13.
119 29.
479 14'57 30.
480 15.
275 31.
480 16.
294 INSTRUCTIONS On this format, list the average daily unit power level in MWe-Net for each day in the reporting month.
Compute to the nearest whole megawatt.
DO(:KI".I'O.
~0-244 IINI'INAMI: R.E. GINNA NVCLEAtc POWER PLANT~
~
UNIT SHUTDOWN AND POWER REDUCTIONS DA"I'
(:OMPLI:.TI-:D BY REPORT MONTH TI'.LI'.PIIONI: (315) 524-4446 Ext. 3)6 Ho.
Date c0 0l 0
C0 lO0O h
Ol ~0 S
M o > n'.
0 lb C
0 Cl Licensee Event Report cf EWh 0
0 Ol 0
%A (J CO tA 0c 0go 0
Cause gl Corrective Action to Prevent Recurrence The unit was.placed on the line May 11 at 2212 and remained on the line at the end of report period.
1 F: Forced S:
Scheduled REV. 4/8$ 4949 Reason:
A-Equipment Failure (Explain)
B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training & License Examination F-Administrative G-Operational Error (Explain)
Hither (Explain) 3 Method:
14fanual 2-Manual Scram.
3-Automatic Scram.
4-Ocher (Explain)
Exhibit G - Instructions for Preparation of Data Entry Sheets for Licensee Event Report (LER) File (NUREG-0161)
Exhibit 1 - Same Source
NARRATIVE
SUMMARY
OF OPERATING EXPERIENCE.
DOCKET NO.
50-244 UNIT R.E. Ginna Nuclear Power Plant DATE June 5
1992 COMPLETED BY Robert E.
Dodge TELEPHONE 1
315 524-4446 ext.
396 MONTH Ma 1992 The unit was placed on the line on May ll at 2212 following the Annual Refueling and Maintenance Outage.