Discusses Engineering & Technical Support Insp Rept 50-244/92-01 on 920106-10 & Notice of Violation.Concerns Re Two Unresolved Issues Re Timeliness of Part 21 Rept on Loose Screws & Sockets & Timeliness of Corrective Actions
ML17262A800
Person / Time
Site: Ginna Constellation icon.png
Issue date: 03/30/1992
From: Durr J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Mecredy R
ROCHESTER GAS & ELECTRIC CORP.
Shared Package
ML17262A801 List:
References
REF-PT21-92 NUDOCS 9204070186
Download: ML17262A800 (6)


See also: IR 05000244/1992001

Text

Docket No. 50-244

Rochester

Gas and Electric Corporation

AKIN:

Dr. Robert C. Mecredy

Vice President

Ginna Nuclear Production

89 East Avenue

Rochester, New York 14649

Dear Dr. Mecredy:

Subject:

Inspection Report No. 50-244/92-01

This letter'efers to the engineering and technical support inspection conducted by

Messrs. A. Lohmeier, H. Gregg, and R. Mathew of this office at the Robert E. Ginna

Nuclear Power Plant, Ontario, New York and Nuclear Engineering Services (NES)

Department offices in Rochester,

New York during the period January 6-10, 1992.

Mr.

Lohmeier discussed

the results of the inspection with you and members of your staff at the

conclusion of the inspection.

Areas examined during the inspection included the effectiveness of the engineering and

technical support organization at the Ginna plant site and NES engineering offices in

Rochester.

Within these areas,

the inspector selectively examined engineering organization

management

procedures

and effectiveness toward implementation of modifications and

facility changes.

In these areas, it was observed that your engineering personnel

performance was commensurate

with the requirements of the Code of Federal Regulations,

Techriical Specifications, and Final Safety Analysis Report.

Based on the results of this inspection, it appears

that environmental qualification of Class 1E

electrical equipment (SMA type torque switches in motor operated valves (MOVs) 860 A, C

and D) was not conducted in full compliance with NRC requirements,

as set forth in the

Notice of Violation enclosed herewith as Appendix A. Instructions have been provided in

Appendix A for your response.

Furthermore, two unresolved

issues concerning the timeliness of your 10CFR 21 report

regarding loose screws and sockets and timeliness of corrective actions taken for unqualified

torque switches are called to your attention.

'V204070186

920330

PDR

ADOCK 05000244

G

PDR

t

~

'

~ '\\

Rochester

Gas and Electric

Corporation

Your cooperation with us in this matter is appreciated.

No other response to this letter is

required.

Sincerely,

Enclosure:

NRC 'Inspection Report No. 50-244/92-01

Jacque P. Durr, Chief

Engineering Branch

Division of Reactor Safety

r

cc w/encl:

R. Smith, Senior Vice President, Production and Engineering

Central Records (4 copies)

Director, Power Division

State of New York, Department of Law

N. Reynolds, Esquire

Public Document Room (PDR)

Local Public Document Room (LPDR)

Nuclear Safety Information Center (NSIC)

K. Abraham, PAO (2)

NRC Resident Inspector

State of New York, SLO Designee

bcc w/encl:

Region I Docket Room (with concurrences)

(w/cy of IFS Forms)

Management Assistant, DRMA (w/o encl)

DRS SALP Coordinator

J. Linville;DRP

W. Lazarus, DRP

T. Moslak, SRI - Ginna (w/cy of IFS Forms)

A. Johnson, PM, NRR

R. Lobel, OEDO

W. Lanning, DRS

I ~

8

Rochester

Gas and Electric

Corporation

RI:DRS

Lo

'er

03/ /92

RI:DRS

/f4

03/~I/92

RI:DRS

Durr

0387/92

OFFICIAL RECORD COPY

A:LOHMEIER