ML17262A330

From kanterella
Jump to navigation Jump to search
Insp Rept 50-244/91-01 on 910107-10.Five Out of Seven Open Items Closed.Major Areas Inspected:Deficiencies Identified During EOP Team Insp Rept 50-244/89-80 Conducted 890925-1004
ML17262A330
Person / Time
Site: Ginna Constellation icon.png
Issue date: 01/23/1991
From: Bonnett F, Eselgroth P
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML17262A331 List:
References
50-244-91-01, 50-244-91-1, NUDOCS 9102010081
Download: ML17262A330 (16)


See also: IR 05000244/1991001

Text

U.S.

NUCLEAR REGULATORY COMMISSION

REGION I

R.

E.

GINNA NUCLEAR POWER

STATION

EMERGENCY OPERATING PROCEDURE

INSPECTION

REPORT NO.:

FACILITY DOCKET NO.:

91-01

50-244

FACILITY LICENSE NO.:

DPR" 18

LICENSEE:

FACILITY:

INSPECTION DATES:

INSPECTOR:

Rochester

Gas

and Electric Company

49 East Avenue

Rochester,

New York 14649

R.

E. Ginna Nuclear

Power Plant

1503

Lake Road

Ontario,

New York

14519

January

7 - 10,

1991

P. Bonnett, Operations

Engineer

LEAD INSPECTOR:

F.

Paul

Bo

, Opera

Engineer

Date

APPROVED BY:

Peter

selgr

, Chief

PWR Sectio

Operations

Branch

Division of Reactor Safety

/- zs-'P/

Date

INSPECTION SUMMARY:

Inspection

on January

7 - 10,

1991 (Report 50-244/91-01)

AREAS INSPECTED:

Routine,

announced

inspection of the corrective actions

taken

to address

deficiencies identified during the

EOP Team Inspection

(Report

50-244/89-80)

conducted

September

25 through October 4, 1989.

RESULTS:

Of the seven (7) items reviewed by the inspector five (5) items were

closed.

The two (2) items remaining

open

have

some corrective actions to be

taken 'for full closure.

Corporate

Engineering action is required to close

one

(1) of these

items

and site action is necessary

to close the last item.

Signi-

ficant improvement in the usability of these

procedures

was observed

during

procedure

walk-downs.

9loaOi008l

910la~

PDR

ADOCK OS000244

9

PDR

~

1

r

I

DETAILS

1.0

PERSONS

CONTACTED

U.S. Nuclear

Re ulator

Commission

  • P. Bonnett,

Operations

Engineer,

T. Moslak, Sr.

Resident

Inspector

  • N. Perry,

Resident

Inspector

1'.2

R.

E. Ginna

2.0

S.

Adams, Technical

Manager

T. Alexander,

gC Engineer

Operations

"R. Carroll, Ginna Training Manager

M. Cavanaugh,

Fire Protection

~F. Maciuska,

Supervisor

License Training

  • T. Schuler,

Operations

Manager

J. St. Martin, Corrective Action Coordinator

"S. Spector,

Plant Manager

"T. White,

Emergency

Procedure

Coordinator

J. Widay, Superintendent

Ginna Production

  • Denotes those

present at the exit interview on January

10,

1991.

J

REVIEW OF

EOP

TEAM INSPECTION

50-244/89-80

OPEN

ITEMS

2.1

~Sco

e

The inspection

was conducted to determine

the adequacy of the licensee's

corrective actions

taken to address

the findings of the

EOP

Team Inspec-

tion conducted

September

25 through October

4,

1989.

To evaluate

the

licensee's

action the inspector

reviewed the

EOP Writer's and User's

Guide and specific

EOPs

and performed

a walk-down of selected

EOPs

and

EOP

Attachments.

The walk-downs were conducted with the assistance

of the

EOP

Coordinator.

2.2

~Findin

s

CLOSED (244/89-80-01):

Development of a Ginna procedure

in accordance

with the

WOG

ERG for "Natural Circulation Cooldown With Steam Void in

Vessel

(without RVLIS)."

The original justification for the exclusion of ES-0.4,

"Natural Circula-

tion Cooldown With Steam Void in Vessel

(without RVLIS)," was based

on the

fact that

RVLIS was

a requirement of the Ginna Technical Specifications;

therefore the procedure

was not necessary.

This justification was not

considered

adequate

due to the possibility that

RVLIS could become in-

operable.

The licensee

modified procedure

ES-0.3 to provide guidance for

3

rapid cooldown and depressurization

with and without.RVLIS available.

The

modified procedure

combines

the guidance

given in.ES-0.3

and ES-0.4.

The

WOG Background

Document allows

a plant to use the natural circulation

guidance

provided by ES-0.2,

0.3 and 0.4 in

a manner that is most appro-

priate.

This includes combining the g'uidance into one procedure.

The

modified ES-0.3

was titled, "Natural Circulation Cooldown With Steam Void

in Vessel."

Further,

the licensee

employed

VOLIAN Enterprises

to perform

an independent

evaluation of the procedures

The inspector

reviewed the

results of the independent

evaluation

and the

new justification/deviation

documentation.

Further,

the inspector walked down this procedure

in the

control

room and reviewed the scenarios

used to verify and validate it on

the simulator.

The information provided to the inspector

was found to be

acceptable

and comprehensive.

The Justification/Deviation

Document

contained

a detailed explanation of the differences

between

the .generic

ES-0.3/ES-0.4

and the modified ES-0.3.

CLOSED (244/89-80-04):

Resolution of concern that the Hain Steam

Line

Radiation Monitor does not function until an alarm condition is reached.

The initial concern

was that the R-31 and

R-32 radiation monitor pen

recorders

did not start tracing until

a predetermined

setpoint

was

reached.

This also presented

a problem to the operators

trying to read or

trend the parameter

for the first five minutes of an event.

The inspector

reviewed Engineering

Work Request

(EWR) No.

5161 which modifies R-31 and

R-32 to provide continuous indication and alarm function.

This change

allows the operator to read,

trend

and evaluate

steamline radiation

conditions continuously.

It is scheduled

to be completed

by May 1993.

1

CLOSED (244/89-80-05):

Resolution of generic

weaknesses

and specific

weaknesses

related to the emergency

procedures.

Five generic

weaknesses

were identified in the team inspection.

They were

1) the level of detail

was not consistent

between

the attachments

to the

EOPs

and the'OPs

themselves;

2) procedures

did not specify the need for a

special

key when it was required;

3) minor labeling problems;

4) the word

"normal" was excessively

used

and not clearly defined;

and 5) there

was

no

identification by which the operators

could determine

which main control

board valves indicate mid-position with both lights lit or extinguished.

Specific procedure

weaknesses

were listed in Attachment

2 of Report

No.

50-244/89-80.

The inspector discussed

with the

EOP coordinator the

corrective actions

made

by the licensee to address

the generic

weaknesses.

A review of the corrective actions regarding the specific weaknesses

identified in Report

No. 50-244/89-80,

Attachment

2 was performed.

Further,

the inspector walked down selected

procedures,

accompanied

by a

licensee

representative,

to verify licensee's

corrective action.

The

licensee's

corrections

were adequate.

The

EOPs

and

EOP Attachments

reviewed by the inspector contained

the appropriate

level of detail,

specified

when special

keys were required,

and correctly utilized the word

"normal."

The usability of the procedures

was very much improved,

enhanced

with correct

component locations.

Valve and component labeling

~ t,

f

was in agreement

with procedural

steps.

Further,

the inspector

reviewed

an inter-office memo addressing

how operators

determine

the mid-position

indication for specific valves.

Based

on the

number

and type of valves

involved and the operators training and experience

the inspector deter-

mined that the present

system in place is adequate.

CLOSED (244/89-80-07):

Resolution of weaknesses

observed

during simulator

exercises'everal

weaknesses

were identified during the

team inspection.

Of these

weaknesses,

some simulator differences

were noted.

The inspector

noted

the corrections

made

and reviewed the status of the

one remaining

upgrade

item that is in the process of being incorporated into the simulator.

The

upgrade effects the Fire Status

Panel.

It wi 11 function with the proper

alarms

and strobe light as in the control

room.

This change

is scheduled

to be completed

by 4/30/91.

Another weakness

observed

during the

EOP

inspection

involved the criteria used to employ the proper methodology

in

training revised

EOPs.

The inspector

reviewed training procedure

TR-2.2,

"Instructional Setting,

Methods,

and Aids."

This procedure

contains

the

guidance

used to determine

the level

and type of operations training

'equired

to address

EOP changes.

Simulated communications with Auxiliary

Operators

(AO) using radios

and the proper time duration for the

AO to

complete the simulated task were corrected

in the simulator.

Radios

and

a

book that gives approximate, times for AOs to perform specific functions

are

used

by the simulator staff.

Lastly, the lack of crew training with

an actual

STA has

been corrected

by scheduling

STA training with all

crews.

CLOSED (244/89-80-08):

Resolution of weaknesses

related to the Writer'

Guide and User's

Guide.=

This item concerned initial weaknesses

with the Writer's and User's

Guides.

The inspector discussed

with the

EOP Coordinator the actions that

were taken to correct these

weaknesses.

The inspector

reviewed both the

Writer's Guide (A-502. 1) and User's

Guide (A-503.1).

Both procedures

were

subsequently

revised to reflect those actions.

The inspector

found these

procedure

changes

adequate.

OPEN (244/89-80-03):

Evaluation of accessibility of valves required to be

manipulated during implementation of the emergency

procedures,

and

installation of improvements,

as required.

The

EOP Coordinator provided the results of an evaluation that was

conducted

on all local operations

performed

by Auxiliary Operators

during

the implementation of the emergency

procedures.

This review identified

three areas

where operator accessibility

was less

than optimal.

They are

I) the isolation of main steamline

upstream traps;

2) operation of the

S/G

ARVs; and 3) the isolation of the

TDAFW Pump

steam

supply valves.

In

regard to the main steamline

upstream traps,

the licensee

has initiated

a

Technical

Support

Request

(TSR) No.91-003

and

a Maintenance

Work Request

~t

U

f

(MWR) No.

9024172 for the installation of two (2)

new valves downstream of

the existing valves.

For the actions involving the S/G ARVs and

TDAFW

pump steam

supply valves,

Engineering

Work Request

No.

S277

has

been

submitted to evaluate,

design

and install platforms to allow easy

access

to these

valves.

The inspector

reques'ted

documentation

to show when these

items would be completed.

The

EOP coordinator informed the inspector that

the requested

documents

are currently in the corporate

design

and review

process

and not yet available.

A completion date

has not been establi-

shed.

The inspector

has determined that this item will remain

open until

the corporate

documents that address

the installation of these

items are

reviewed by the

NRC.

3.0

Open (244/89-80-06):

Evaluation of Site Contingency procedures

related to

firefighting.

The fire procedures

of Ginna are contained within the series of site

contingency procedures.

The team inspection identified that due to the

vast

number of Site Contingency

(SC) procedures

and the complex index, the

operators

generally ignored them.

The licensee

agreed to evaluate

the

current organization of these

procedures.

The lice'nsee

determined that

the procedures

relating to firefighting plans

and strategies

do not have

to be maintained

in the current format and would be improved by

reformatting for simplicity.

The inspector

met with a licensee

representative

responsible

for reformatting the

SC procedures.

He informed

the inspector that

a sub-committee

has

been established

to develop the

new

Site Contingency plan.

They determined that procedures

relating to

firefighting plans

and strategies

do not have to be maintained

in the

current format.

All SC procedures,

except those that relate to

10 CFR 50,

Appendix

R, are being reformatted.

The

new format is to be

a

map of

specific areas

and

a one-page

data

sheet for that

arear'he

map details

the location of emergency

and safety equipment,

potential

hazards,

fire

barriers,

and major components.

This format would reduce

the size of

usable

information into a single binder.

Copies of the binder would be

kept in the control

room and fire brigade locker.

The prototype

has

been

completed

and reviewed

by the appropriate

departments.

It has received

positive appraisals

and work has started'to

complete

a map of an entire

area.

The committee plans to have this task completed

on or before

12-31-92.

This item will remain

open until formal documentation of the

proposed

reformatted plan is provided to the

NRC.

EXIT MEETING

At the conclusion of the site inspection,

on- January

10.,

1991,

an exit

meeting

was held with the licensee's

senior available representatives

(denoted in Paragraph

1.0) to discuss

the

scope

and findings as detailed

in this report.

-v

VO

Written material

was not provided to the licensee

by the inspector at any

time during this inspection.

Based

on the

NRC Region I review of this

report and discussions

held with the licensee

representatives

during this

inspection, it was determined that this report does not contain informa-

tion subject to

10 CFR 2.790 restrictions.

I'

Document

Document

Number

Title

ATTACHMENT 1

DOCUMENTS'REVIEWED

Rev No./Date

WESTINGHOUSE

OWNERS

GROUP:

WOG Emergency

Response

Guidelines

lA

EMERGENCY

E-0

E-1

E-2

E-3

OPERATING PROCEDURES:

Reactor Trip or Safety Injection

Loss of Reactor

or Secondary

Coolant

Faulted

Steam Generator Isolation

Steam Generator

Tube Rupture

14/12-19-90

9/O4-O9-9O

4/04'-09-90

10/04-09-90

EMERGENCY CONTINGENCY ACTIONS PROCEDURES:

ECA-1.2

LOCA Outside Containment

ECA-2. 1

Uncontrolled Depressurization

of Both Steam

Generators

ECA-3. 1

SGTR with Loss of Reactor Coolant-Subcooled

Recovery Desired

SGTR,with Loss of Reactor Coolant-Saturated

Recovery Desired

SGTR without Pressurizer

Pressure

Control

ECA-3.2

ECA-3.3

EMERGENCY SUB-PROCEDURES:

ES-l.l

SI Termination

ES-3.1

Post-SGTR

Cooldown Using Backfill

ES-3.3

Post-SGTR

Cooldown Using Steam

Dumps

CRITICAL SAFETY FUNCTION STATUS TREES:

F-0.3

Heat Sink. CSFST

F-0.4

Integrity CSFST

ABNORMAL PROCEDURES:

AP-CCW.2

Loss of CCW During Power Operation

AP-CCW.3

Loss of

CCW Plant Shutdown

AP-CR. 1

Control

Room Inaccessibility

AP-IA.1

Loss of Instrument Air

AP-RHR. 1

Loss of

RHR

FUNCTIONAL RESTORATION GUIDELINES PROCEDURE:

FR-H.1

Response

to Loss of Secondary

Heat Sink

FR-P. 1

Response

to Imminent Pressurized

Thermal

Shock

Condition

FR-P.2

Response

to Anticipated Pressurized

Thermal

Shock Condition

FR-S.1

Response

to Nuclear

Power Generation/ATWS

2/04-09-90

5/04-09-90

6/O4-O9-9O

8/04-09-90

5/04-09-90

6/04-09"90

2/07-21-89

4/04-09"90

2/01-12-90

1/07-21-89

9/09-04-90

5/04-09"90

2/04"09-90

4/04"09-90

8/12-19"89

7/12-19-89

10/06-27-90

4/12-19-89

8/06-01-90

f

Jl

ATTACHMENT 1

DOCUMENTS REVIEWED

Document

Document

Number

Title

E UIPMENT RESTORATION PROCEDURES:

ER-ELEC.4

TSC D/G Feed to Bus

16 to Supply Charging

Pumps

ER-INST.2 Loss of Annunciator

ER-NIS. 1

SR Malfunction

ADMINISTRATIVE PROCEDURES:

A-502. 1

Emergency

& Abnormal Operating

Procedures

Writer'

Guide

A"503. 1

Emergency

5 Abnormal Operating

Procedures

User's

Guide

EOP

ATTACHMENTS:

CV/CVI

DC Loads

D/G Stop

Letdown

N2

PORV

RCP Start

SD-1

Rev No./Date

2/09-28"89

1/05-13-89

5/04-18-90

6/05"31-90

9/05-31-90

1/04"04-90

1/04-04-90

1/04-04"90

2/06-20"90

1/04-04-90

1/01-04"90

2/06-20-90

P'