Text
Appendix A
NOTICE OF VIOLATION Rochester Gas
& Electric Corporation R.
E. Ginna Nuclear Power Plant Docket No. 50-244 License No.
DPR-18 During the inspection conducted on March 15, 1987 through April 18,
- 1987, and in accordance with the General Statement of Policy and Procedure for NRC Enforcement Actions 10 CFR Part 2, Appendix C (Enforcement Policy 1986),
the following violations were identified:
A.
Technical Specification 3.3.2.2 states in part; "Prior to initiating repair s, all valves in the system that provide the duplicate function shall be tested to demonstrate operability".
Contrary to the above, on April 9, 1987, operability of duplicate valve MOV 860A was not demonstrated prior to ajusting the packing on MOV 860B in the containment spray system.
This is a Severity Level IV violation.
(Supplement I)
B.
Technical Specification
- 3. 14.3. 1 states in part: "If a spray/sprinkler system is inoperable, except for testing, within one hour, establish a
, continuous fire watch with backup fire suppression equipment in those areas in which redundant systems or components necessary for safe-shutdown could be damaged...".
Contrary to the above, on March 16, 1987, fire suppression systems in areas necessary for safe-shutdown were rendered inoperable for approximately one hour and twenty minutes without continuous fire watches with backup fire suppression equipment being stationed in these areas.
This is a Severity Level IV violation.
(Supplement I)
Pursuant to the provisions of 10 CFR 2.201, Rochester Gas and Electric Corporation is hereby required to submit to this office within 30 days of the date of the letter transmitting this Notice, a written statement or
'explanation in reply, including:
(1) the reason for the violation if
- admitted, (2) the corrective steps which have been taken and the results
- achieved, (3) the corrective steps which will be taken to avoid further violations, and (4) the date when full compliance will be achieved.
Where good cause is shown, consideration will be given to extending the response time.