MONTHYEARIR 05000458/20240102024-10-31031 October 2024 Design Basis Assurance Inspection (Programs) Inspection Report 05000458/2024010 IR 05000458/20240032024-10-31031 October 2024 Integrated Inspection Report 05000458/2024003 RBG-48315, Reply to a Notice of Violation, NRC Inspection Report 05000458/2023003 Supplement2024-09-24024 September 2024 Reply to a Notice of Violation, NRC Inspection Report 05000458/2023003 Supplement RBG-48306, Report of Changes and Errors to 10CFR50.462024-09-24024 September 2024 Report of Changes and Errors to 10CFR50.46 ML24263A2712024-09-19019 September 2024 Application to Revise Technical Specifications to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements ML24255A1192024-09-16016 September 2024 Notification of NRC Follow Up Inspection for One Severity Level (SL) III and Two SL IV or Three or More SL IV Violations and Request for Additional Information RBG-48311, Reply to a Notice of Violation, NRC Inspection Report 05000458/20240022024-08-28028 August 2024 Reply to a Notice of Violation, NRC Inspection Report 05000458/2024002 IR 05000458/20240052024-08-22022 August 2024 Updated Inspection Plan for River Bend Station (Report 05000458/2024005) ML24220A2642024-08-20020 August 2024 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment ML24185A1522024-08-13013 August 2024 Issuance of Amendment Nos. 334, 235, and 215, Respectively, to Revise TSs to Adopt TSTF-205 ML24214A2752024-08-0202 August 2024 Acknowledgement of Readiness for Supplemental Inspection RBG-48308, Notification of Readiness for Supplemental Inspection2024-07-31031 July 2024 Notification of Readiness for Supplemental Inspection IR 05000458/20240022024-07-30030 July 2024 Integrated Inspection Report 05000458/2024002 and Notice of Violation ML24164A0862024-06-12012 June 2024 Notification of Commercial Grade Dedication Inspection (05000458/2024010) and Request for Information 05000458/LER-2023-005-01, Manual Reactor Scram Due to Lowering Feedwater Temperature Following an Automatic Isolation of Feedwater Heater String2024-06-0404 June 2024 Manual Reactor Scram Due to Lowering Feedwater Temperature Following an Automatic Isolation of Feedwater Heater String ML24060A2192024-05-30030 May 2024 Authorization of Alternative to Use EN-RR-01 Concerning Proposed Alternative to Adopt Code Case N-752 ML24081A0072024-05-16016 May 2024 Issuance of Amendment No. 213 Revision to Technical Specifications to Adopt TSTF 505, Revision 2, Provide Risk-Informed Extended Completion Times – RITSTF Initiative 4b ML24093A0892024-05-16016 May 2024 Issuance of Amendment No. 214 Adoption of 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors IR 05000458/20240012024-05-14014 May 2024 Integrated Inspection Report 05000458/2024001 ML24128A0422024-05-0707 May 2024 License Amendment Request to Remove Obsolete License Conditions ML24102A2842024-05-0707 May 2024 Summary of Regulatory Audit in Support of LARs to Revise Technical Specifications to Adopt Risk-Informed Completion Times and Implement the Provisions of 10 CFR 50.69 RBG-48276, 2023 Annual Radioactive Effluent Release Report2024-04-23023 April 2024 2023 Annual Radioactive Effluent Release Report RBG-48288, Louisiana Pollutant Discharge Elimination System Permit Renewal2024-04-15015 April 2024 Louisiana Pollutant Discharge Elimination System Permit Renewal IR 05000458/20244022024-04-15015 April 2024 Security Baseline Inspection Report 05000458/2024402 (Full Report) ML24106A0432024-04-11011 April 2024 June 2024 Emergency Preparedness Exercise Inspection Request for Information ML24101A3882024-04-10010 April 2024 Response to Request for Confirmation of Information by the Office of Nuclear Reactor Regulation Proposed Alternative Request EN-RR-22-001 Risk-Informed Categorization and Treatment for Repair RBG-48277, 2023 Annual Radiological Environmental Operating Report2024-04-10010 April 2024 2023 Annual Radiological Environmental Operating Report IR 05000458/20243012024-04-0202 April 2024 Notification of NRC Initial Operator Licensing Examination 05000458/2024301 ML24089A2262024-03-29029 March 2024 Entergy Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Exams ML24075A1712024-03-15015 March 2024 Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3)) IR 05000458/20240402024-03-15015 March 2024 – 95001 Supplemental Inspection Report 05000458/2024040 and Follow-Up Assessment ML24074A2892024-03-14014 March 2024 Proof of Financial Protection (10 CFR 140.15) ML24066A1802024-03-0707 March 2024 Notification of NRC Follow-Up Inspection for Any Severity Level I or II Traditional Enforcement Violation IR 05000458/20230062024-02-28028 February 2024 Annual Assessment Letter for River Bend Station - Report 05000458/2023006 RBG-48278, 2023 Spent Fuel Storage Radioactive Effluent Release Report2024-02-27027 February 2024 2023 Spent Fuel Storage Radioactive Effluent Release Report RBG-48286, Revision to Owners Activity Report Form (OAR) for Cycle 222024-02-27027 February 2024 Revision to Owners Activity Report Form (OAR) for Cycle 22 ML24031A0042024-02-21021 February 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0052 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) 05000458/LER-2023-006, Automatic Reactor Scram Due to a Turbine Trip Following a Disconnect Failure at Switchyard2024-02-0808 February 2024 Automatic Reactor Scram Due to a Turbine Trip Following a Disconnect Failure at Switchyard RBG-48274, Notification of Readiness for Supplemental Inspection2024-02-0505 February 2024 Notification of Readiness for Supplemental Inspection IR 05000458/20230042024-01-30030 January 2024 Integrated Inspection Report 05000458/2023004 IR 05000458/20230402024-01-18018 January 2024 – 95001 Supplemental Inspection Supplemental Report 05000458/2023040 and Follow-Up Assessment Letter 05000458/LER-2023-005, Manual Reactor Scram Due to Lowering Feedwater Temperature Following an Automatic Isolation of Feedwater Heater String2024-01-16016 January 2024 Manual Reactor Scram Due to Lowering Feedwater Temperature Following an Automatic Isolation of Feedwater Heater String RBG-48271, Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times – RITSTF Initiative 4b and Application to Adopt 10 CFR 50.69, Risk2024-01-12012 January 2024 Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times – RITSTF Initiative 4b and Application to Adopt 10 CFR 50.69, Risk ML24012A1962024-01-12012 January 2024 Response to 2nd Round Request for Additional Information Concerning Relief Request Number EN-RR-22-001 – Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and ML24011A1742024-01-11011 January 2024 Security Baseline Inspection Report (Cover Letter) 05000458/LER-2023-004, Drywall Post Accident Radiation Monitor Inoperable Due to Unrecognized Surveillance Failure2023-12-28028 December 2023 Drywall Post Accident Radiation Monitor Inoperable Due to Unrecognized Surveillance Failure ML23349A1672023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23348A3572023-12-14014 December 2023 Application to Revise Technical Specifications to Use Online Monitoring Methodology – Slides and Affidavit for Pre-Submittal Meeting ML23352A0292023-12-13013 December 2023 Entergy - 2024 Nuclear Energy Liability Evidence of Financial Protection ML23340A1592023-12-13013 December 2023 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment 2024-09-24
[Table view] |
Text
J. Barb UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 September 15, 2017 Mr. Reid Nelson, Director Office of Federal Agency Programs Advisory Council on Historic Preservation 401 F Street NW, Suite 308 Washington, DC 20001-2637
SUBJECT:
RIVER BEND STATION, UNIT 1, LICENSE RENEWAL REVIEW
Dear Mr. Nelson:
The U.S. Nuclear Regulatory Commission (NRC) is conducting a review of the environmental effects of renewing the operating license for River Bend Station, Unit 1 (RBS). RBS is operated by Entergy Operations, Inc. (Entergy) and is located in West Feliciana Parish, Louisiana, approximately 24 miles north-northwest of Baton Rouge, LA (see Enclosure 1). Entergy submitted an application for the renewal of the RBS operating license in a letter dated May 31, 2017, pursuant to Title 10 of the Code of Federal Regulations Part 54 (10 CFR Part 54). Under NRC regulations, the operating license for a nuclear power plant is issued for up to 40 years and may be renewed for up to an additional 20 years. The current operating license for RBS will expire on August 29, 2025.
As part of the NRCs license renewal review, a site-specific Supplemental Environmental Impact Statement (SEIS) to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants, NUREG-1437, is prepared under 10 CFR Part 51, the NRCs environmental protection regulations for domestic licensing and related regulatory functions. These regulations also implement Section 102(2) of the National Environment Policy Act of 1969, as amended (NEPA). In accordance with 36 CFR 800.8(c), the NRC intends to comply with Section 106 of the National Historic Preservation Act of 1966, as amended (NHPA), through the NEPA process.
For the purposes of analysis, the NRC has defined the area of potential effects (APE) for the RBS license renewal undertaking as the area at the power plant site and its immediate environs that may be impacted by ongoing routine maintenance and operations activities during the license renewal term (see Enclosure 2). The APE may extend beyond the immediate RBS environs if Entergys maintenance and operations activities affect offsite historic properties (see ). This determination is made irrespective of ownership or control of the lands of interest.
R. Nelson Please submit any comments that you may have on the scope of the environmental review by October 23, 2017. Written comments should be submitted by mail to:
Cindy Bladey, Chief Rules, Announcements, and Directives Branch (RADB)
Office of Administration, Mailstop TWFN-8-E21 U.S. Nuclear Regulatory Commission Washington, DC 20555 Electronic comments may be submitted to the NRC by accessing www.regulations.gov and searching for Docket ID NRC-2017-0141. The RBS license renewal application is available at:
http://www.nrc.gov/reactors/operating/licensing/renewal/applications/river-bend.html.
The NRC expects to publish the draft SEIS in April 2018. A copy of the document will be sent to you for your review and comment. After consideration of public comments received, the NRC will prepare a final SEIS, which is scheduled to be issued in November 2018.
If you have any questions concerning the NRCs license renewal review, please contact Robert Hoffman, Environmental Scientist, at 301-415-1107 or by e-mail at Robert.Hoffman@nrc.gov.
Sincerely,
/RA/
Benjamin G. Beasley, Chief Environmental Review and Project Management Branch Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-458
Enclosures:
- 1. Area Map, 50-mile radius
- 2. Area Map, 6-mile radius
- 3. RPS Site Area Map cc w/encls: Listserv
ML17255A023 (Pkg), ML17255A036 (Ltr) *concurred via email OFFICE PM:DLR:RERB LA:DLR:RPGB PM:DLR:RERB BC:DLR:RERB NAME RHoffman YEdmonds EKeegan BBeasley DATE 9/15/2017 9/15/2017 9/15/2017 9/15/2017
Area Map, 50-mile radius Enclosure 1
Area Map, 6-mile radius Enclosure 2