ML17254A542

From kanterella
Jump to navigation Jump to search
Insp Rept 50-244/85-04 on 850205-15.Violation Noted:Failure to Accomplish Preventive Maint Reviews on Valves.Weaknesses Noted:Untimely or Incomplete Documentation of Maint Activities
ML17254A542
Person / Time
Site: Ginna 
Issue date: 08/30/1985
From: Bettenhausen L, Bissett P, Dragoun T, Ebneter S, Napuda G, Shaeffer M, Wen P
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML17254A539 List:
References
50-244-85-04, 50-244-85-4, NUDOCS 8509100110
Download: ML17254A542 (39)


See also: IR 05000244/1985004

Text

U.S.

NUCLEAR REGULATORY COMMISSION

REGION I

Report No.

50-244/84-04

Docket No.

50-244

License

No.

DPR-18

Licensee:

Rochester

Gas 5 Electric Co.

49 East Avenue

Rochester

New York

14649

Facility Name:

R.

E. Ginna Station

Inspection At:

Ontario and Rochester,

New York

Inspection

Conducted:

February

5-15,

1985

Inspectors:

Paul Bissett,

Reactor

Engineer

ate

Thomas

Drag

n,

a iatio

Specialist

PWR-RPS,

EPRPB,

DRSS

date

eorg

Napuda,

Lead Reactor

Engineer

Michael Schaeffer,

Reactor

Engineer

ate

date

Peter

Wen, Reactor

Engineer

date

Lee H. Bettenhausen,

Chief,

Operations

Branch,

DRS

Branch

date

Approved by:

S.

D. Ebneter,

Director,

Division of Reactor Safety

d te

EI509f00110 860830

PDR

ADOCN, 05000240

8',

PDR:

TABLE OF CONTENTS

1.0

Inspection

Summary

1. 1

Summary

1.2

Inspection Objectives

1.3

Inspection

Findings

1.4

Persons

Contacted

~Pa

e

2.0

Maintenance

2. 1

Mechanical

Maintenance

2.2

Electrical Maintenance

2.3

Instrumentation

and Control Activities

5

8

11

3.0

Surveillance

3. 1

Operations

3.2

Results

and Test Group

3.3

Reactor Engineering

12

13

14

16

4.0

Radiological

Controls

equality Assurance

Program

5. 1

Audits and Vendor Surveillance

5.2

equality Control

5.3

Warehouse Activities

16

19

19

21

22

6.0

Other Organizations

and Activities

6.1

Offsite Safety

Review Committee

6.2

Engineering

Support

6.3

Trending

and Reporting

7.0

Management

Meetings

22

22

23

23

~y

1. 0

SUMMARY AND INTRODUCTION

1

~ 1

Ins ection Summar:

Ins ection

Conducted

Februar

5-15

1985

Re ort No. 50-244/85-04

I

d:

i

t

i

A

T

maintenance activities and

such related activities

as quality control,

quality assurance,

radiological protection

and engineering

support.

The

inspection

involved 397 hours0.00459 days <br />0.11 hours <br />6.564153e-4 weeks <br />1.510585e-4 months <br /> onsite

by six region-based

inspectors.

Results:

One violation was identified (fai lure to accomplish preventive

maintenance

reviews

on valves).

Three weaknesses

were found (documenta-

tion of maintenance activities,

slow implementation of maintenanch train-

ing programs

and deficiencies

in the control

and calibration of measuring

and test equipment).

Three notable strengths

of licensee

programs

were

identified (a strong

commitment to ALARA, thorough

and safety-conscious

reviews

by the Nuclear Safety

and Review Board and e'xperienced,

well-

qualified plant staff members).

1.2

INSPECTION OBJECTIVES

This inspection

involved

a multidisciplinary examination of maintenance

and surveillance activities.

In each functional

area

inspected,

the con-

duct of act'ivities, the qualification of staff members,

the interactions

with other functional areas,

the development of and adherence

to work

procedures

and the documentation

and analysis of trends

and data

were

examined.

Mechanical, electrical

and instrument/control

maintenance

and

surveillance activities conducted

by operations

and results

and test

personnel

were selected

for inspections

Personnel

were interviewed; pro-

cedures

were reviewed

and examined in use;

on-going activities were

inspected;

and,

documents,

training data,

and qualifications were reviewed.

The information gathered

was then

assembled

by inspection

team

members

to

obtain the basis for an operational

assessment

of the conduct of

maintenance

and surveillance at Ginna Station.

1. 3

INSPECTION FINDINGS

Safety-related

maintenance

is performed expeditiously

and

conscientiously

by well-qualified personnel.

(Strength)

Recordkeeping

in several

areas of maintenance

- Maintenance

Work

Requests,

maintenance

history files and closeout of quality control

surveillance

findings - is incomplete

and not timely.

(Weakness)

Preventive

maintenance

for rotating equipment

and for valves

was

being controlled,

performed

and documented.

However,

the review

functions of A-1015 for valves were not being done.

(Violation)

A well-defined training program for maintenance

staff has

been

developed,

but has not been

implemented.

(Weakness)

Calibration

and control of mechanical

measuring

and test equipment

was adequate.

Discrepancies

in the calibration procedures

were

noted.

Several

discrepancies

in the calibration

and control of

electrical

measuring

and test equipment were identified.

(Weakness)

Reactor trip breaker testing

was performed with no difficulties.

Plant personnel

were familiar with procedures

and results.

However,

there

was

no procedural

requirement for trending data

as

had been

committed to in a licensee letter.

(Unresolved

Item)

Information exchanges,

meetings

and informal communications

were

observed

to be viable and effective.

Test result data

and trending information was readily available to

Results

and Test staff.

Outage radiation exposure

planning is thorough,

although

accomplished

informally.

A strong

commitment to radiation safety

and

ALARA is evident.

(Strength)

Acceptability of audit finding invalidations for the triennial fire

protection audit will be examined

by NRC.

(Unresolved

Item)

Onsite inspection

and surveillance

exceeds

QA program requirements.

Nuclear Safety Audit and Review Board overviews are thorough,

detailed,

well-planned

and competent.

(Strength)

An ambitious flow diagram

upgrade

program using

a computer-based

drawing and data

base

system is nearing completion.

This is one

measure of strong engineering

support for plant activities.

Trending, analysis

and reporting for station

events

done under

supervision of the Operational

Assurance

Engineer are thorough

and

provide useful outputs.

Deficiencies in reporting of data for the Nuclear Plant Reliability

Data System

have

been

recognized

and are being addressed.

In sum, the team found maintenance

and surveillance activities at

Ginna Station to be conducted

by an experienced,

well-qualified staff

through

a thorough

and controlled management

system.

Some minor

deficiencies

in review of preventive maintenance,

recordkeeping

and

record handling

and responses

to quality control reports

were identi-

fied in the course of this inspection,

as well as the notable

licensee

strengths

mentioned

above.

PERSONS

CONTACTED

~C. Anderson,

QA Manager

J.

Bodine, Administrative Manager

"L. Boutwell, Maintenance

Manager

  • C. Edgar,

18C Supervisor

  • D. Fi lkins, Manager

HP 5 Chemistry

  • J. Hutton, Mechanical

Engineer

  • R. Kober, V.P. Electric and

Steam Production

  • J. Larizza, Operations

Manager

"T. Marlow, Steam Generator

Project Manager

  • R. Mecredy,

Manager Nuclear Engineering

  • K. Nassauer,

QC Inspection

Supervisor

"C. Peck,

Nuclear

Assurance

Manager

"J. St. Martin, Station

Engineer

'T. Schuler,

Maintenance

Manager

"B. Snow, Superintendent

Nuclear Production

  • S. Spector,

Assistant Superintendent

  • W. Stiewe,

QC Engineer

NRC

  • W. Cook, Senior

Resident

Inspector

The personnel

identified with a asterisk(~)

attended

the exit interview

on February

15,

1985.,

Other managers,

supervisors,

corporate

and plant

personnel

were contacted

during the course of the inspection

as

activities involved their areas.

2.0

MAINTENANCE

The Maintenance

Manager is responsible

for the overall conduct of

maintenance activities.

Fifty-three persons

assigned

to various

sections carry out these activities.

Maintenance activities at the Ginna station are conducted

by three func-

tional disciplines:

mechanical,

electrical

and instrumentation

and control

(I&C). These three disciplines

and the functional

and administrative

controls governing their activities were reviewed for conformance

to

applicable

codes,

standards

and procedures.

The paragraphs

which follow document

the inspector's

review of each of

these disciplines

and their integration into the operation of Ginna

station.

Procedure

A-1603, rev.

6, establishes

the system for initiating, priori-

tizing, scheduling

and controlling corrective maintenance.

Any person

can

initiate a Maintenance

Work Request

(MWR) and Trouble Report.

The Shift

Supervisor or his designee

reviews

MWR's to assess

impact

on plant opera-

tions, assigns

a sequential

number

and indicates

approval of the

MWR.

The

Maintenance

Manager or his designee

establishes

priority for the work and

assigns

the work group.

The work group supervisor is responsible

for the

coordination

necessary

to perform the work and to complete

the post-per-

formance activities.

This coordination

includes Shift Supervision,

a

Special

Work Permit or Radiation

Work Permit, Quality Control,

and Results

and Tests,

as applicable.

The inspector

reviewed the

MWR's initiated in 1985,

the

MWR's outstand-

ing from 1984 and

a random

sampling of completed

MWR's to assess

the

quantity of corrective maintenance,

priority and timeliness for safety

related work and the coordination before

and after work performance.

Approximately 4000

MWR's are initiated each year.

415

MWR's had been

initiated between

January

1 and February

7,

1985.

Several

of these

were

rewritten from previous

(1983)

MWR's as

a result of maintenance

super-

vision's annual

review as mandated

by section 3.5.2 of A-1603.

Of the

415

MWR's issued to date in 1985, only 6 were safety-related.

These

were

properly prioritized.

Informal communication

between

operations

and

maintenance

personnel

usually results

in work completion

contemporaneous

with MWR initiation for operational

or safety-related

work.

A review of

outstanding

(1984)

MWR's yielded about 600;

many of these

require plant

shutdown to accomplish

and are

scheduled

for the

1985 refueling outage.

Others are completed work, according to various supervisors

interviewed,

but administrative

review is not yet complete.

A review of 45 in-process

MWR's awaiting the Maintenance

Manager's

closeout,

the final step in the

MWR process,

showed

a typical time of

1 month from initiation to closeout

and 3-7 days

from initiation to work completion,

except that safety-

related work is completed

the day of initiation unless deferred until

plant conditions permit the work.

While no problems

were evident regarding safety-related activities,

the

large

number of open

and incomplete

MWR's, (several

hundred),

and the

tenuous tracking

system for MWR's contributes,

with other problems

identified later in this report,

to an assessment

of untimely and

incomplete

recordkeeping

for plant maintenance activities.

MECHANICAL MAINTENANCE

Mechanical

maintenance activities include preventative

and corrective

maintenance

for pumps,

piping and supports

and valves.

The majority of

work is accomplished

by the mechanical,

pipe

and day/night maintenance

shops.

Each of these

shops

has

an assigned staff headed

by a

shop foreman.

The foremen report to the Mechanical

Maintenance

Supervisor.

Mechanical

maintenance activities were reviewed to ensure that

safety-related

work is conducted

in accordance

with approved plant

procedures.

Maintenance activities are

cont, rolled through the

use

of administrative

(A) procedures

describing

programs

and controls

and

maintenance

(M) procedures

giving detailed work instructions.

Corrective

maintenance,

either safety or non-safety-related,

is initiated by use of

the

MWR.

The inspector

reviewed several

hundred

MWR's to verify

completeness

and ascertain

the extent of safety-related

maintenance.

It

was evident

from this review that the majority of safety-related

mainte-

nance is routine scheduled

preventative

maintenance

(PM)

~

Administratively, mechanical

PM activities are governed

by A-1010,

Mechanical

Preventative

Maintenance

Program;

A-1011,

Equipment Inspection

Period

and Lubrication List; A-1015, Three Month Lubrication and Mainte-

nance

Inspection;

A-1020, Valve Preventative

Maintenance

Program;

and

A-1021, Safety

and Relief Valve Testing

Program.

The conduct of safety-

related maintenance,

whether preventative

or corrective, is controlled

through the

use of detailed

procedures.

The inspector

reviewed the per-

formance of several

maintenance activities completed during 1984.

These

included major/minor inspections of pumps;

removal

and installation of

seismic pipe supports;

installation of valve packing'; inspection

and

testing of valves;

and inspection of heat exchangers.

Within each proce-

dure, certain provisions are to be met prior to commencing or continuing

work. These provisions include:

~

Quality Control(QC) notification prior to start

~

Limiting Conditions for Operation evaluation

(A-52.4)

~

Equipment Tagging (A-1401)

~

Health Physics

work permit issued if applicable

~

QC hold points

~

Notification of Results

and Test group for possible

post-maintenance

testing

~

Replacement

part,s, if necessary

(A-801)-

~

Housekeeping

and cleanliness

requirements

For those

maintenance activities reviewed

by the inspector,

a sampling of

procedural

provisions

was reviewed to verify that all work had

been

completed

as required.

The inspector

found all work to be complete

and

well documented.

The Results

and Test

(R&T) group performs post-maintenance

testing

following completion of maintenance

on safety-related

equipment

in

order to verify equipment operability and develop baseline

operating

characteristics.

No safety-related

mechanical

maintenance

was conducted

during this inspection,

so the inspector

was unable to observe

post-main-

tenance testing.

All procedures

reviewed

had adequate

provision for

0

hi

'

post-maintenance

testing.

The inspector did observe

the monthly survei l-

lance test

and transfer of operations for the component cooling water

pumps.

The inspector

noted that

R&T personnel

performed the test in

accordance

with a current approved

procedure,

with an issued

Radiation

Work Permit

(RWP) and with a

gC inspector present.

Appropriate super-

visory reviews were performed following completion of the test.

A review of calibration

and control of measuring

and test equipment

(M&TE)

used

by mechanical

maintenance

personnel

was performed to verify the

adequacy of the

M&TE program in the conduct of maintenance

and adherence

to applicable

procedures.

Torque wrenches

are maintained,

controlled and

calibrated

by the mechanic

shop.

All other

M&TE, i.e., micrometers,

vernier calipers, etc.,

are calibrated

by gC, but assigned

to individuals

within the various mechanical

shops; it is the responsibility of these

individuals to maintain

and control the instruments.

The inspector

reviewed the

1984 usage

log and calibration records for torque wrenches

and noted that torque wrenches

were always tested for acceptability prior

to use.

Other areas verified were:

storage

and labeling of test equip-

ment; certification records for calibration of test equipment,

including

torque wrench

bench tester;

test equipment

denoted

as

used in various

completed

M-procedures calibrated

when in use.

The inspector witnessed

calibrations

by gC for several

inside

and outside micrometers,

depth

micrometers

and vernier calipers.

All calibrations

were performed using

appropriate

approved

procedures.

A number. of problems with the control

and calibration of meausuring

and

test equipment

were identified in the licensee's

audit 84-05:SB conducted

in the spring of 1984.

Corrective actions

on several

of these

problem

areas

had

been

taken

and others

were under way at the time of this

inspection.

One of these,

a major revision to procedure

A-1201, Calibra-

tion and Control of Measuring

and Test Equipment,

was

made

and approved in

January,

1985.

During the witnessing of calibrations,

the inspector

noted

several

discrepancies

between

A-1201 and the individual calibration procedures

(CP's).

The CP's in question

include

CP 80.0,

80. 1, 80.2, 80.3, 80.4,

81.0

and 81. 1.

The discrepancies

included incorrect or deleted

references

and incorrect equipment classifications.

These discrepancies

and other

minor problems with the CP's were discussed

with the

gC Supervisor.

This

supervisor

was

aware of the problems

and of the

need to review and correct

the CP's.

The fact that this had not been

accomplished

at the time of

this inspection contributes to assessment

of a weakness

in control

and

calibration of M&TE as further discussed

later in this report.

The maintenance

history program is described

in procedure

A-1705 '

review of files kept for this program

showed that the procedure

was

complied with in that the Maintenance

Manager determined

those entries to

be made.

The usefulness

of the existing history file is very questionable

because

of these observations:

the last inspection

noted for the manip-

ulator crane

was 2/22/79 but the crane

had since

been

used for several

refuelings;

the history for safety injection

pump

1C only covered

the

interval 4/22/75 to 10/30/81; entries for snubbers

ranged

from 5/7/75 to

8/30/83.

In contrast,

selected

entries

in pump histories

were current.

The

'l

L

out-of-date entries

and the sheer bulk of these files make it difficult to

place reliance

on this history information for trending or tracking.

This

is regarded

as another

example of weakness

in maintenance

recordkeeping.

Procedures

A-1010 and A-1020 outline the preventive maintenance

program

for rotating equipment

and for valves.

The inspector

reviewed these

procedures

to verify that inspection

frequencies

had been established,

desired

maintenance

was being performed

and this work was being adequately

documented.

Discussions

were held with the responsible

foremen,

the

mechanical

maintenance

supervisor

and the maintenance

manager

regarding

their involvement by scheduling,

supervising

and reviewing the

PM program.

Documentation of completed

PM'

is accomplished

by using appropriate

pro-

cedures

and/or annotating

equipment history cards.

A computerized

main-

tenance

tracking

and scheduling

system

(COMMS) is in trial use

and will

eventually document the

PM program.

During reviews of the scheduled

and completed

PM on valves

and discussion

with foremen

and supervisors,

the inspector

determined that many aspects

of A-1015 were not being accomplished.

The Maintenance

Supervisor

was

not performing the procedurally required monthly schedule

reviews to

ensure that scheduled activities were being accomplished

nor was

he

reviewing the program annually for improvements,

changes

or updates.

Valve inspections

were not being done within the inspection intervals

specified

by the procedure.

Failure to adhere

to an approved

procedure is

a violation (50-244/85-04-01).

The mechanical

maintenance

section is made

up of well-qualified and experi-

enced personnel.

A well-defined training program

has

been developed,

but

has not yet been fully implemented.

Management control

and coordination is

accomplished

formally through

a weekly interdepartmental

meeting

among the

discipline foremen

and supervisors

and informally through

many other means.

With the exception of the

PM program for valves, identified as

a violation

above,

mechanical

maintenance activities are accomplished

as

scheduled

and

are well controlled through the

use of detailed

maintenance

procedures.

Weaknesses

in maintenance

recordkeeping

(Inspector

Followup Item

50-244/85-04-04)

and calibration

and control of measuring

and test equip-

ment were noted.

2.2

ELECTRICAL MAINTENANCE

The Maintenance

Manager is responsible

for electrical

maintenance.

Performance

of day-to-day activities is supervised

by the IEC/Electrical

Supervisor

and the

shop foremen. Staffing of this activity was reviewed by

the inspector

and appeared

adequate

to handle

the work load.

Electrical

maintenance

personnel,

including the foreman,

had documented

evidence of

training and qualification appropriate

to their function.

The inspector

assessed

performance

of these activities by observation

of work in

progress,

review of completed

work and discussions

with workers

and

supervisors.

These activities were directly witnessed:

~

Calibration

and maintenance

of the turbine-driven auxiliary feed-

water

pump discharge

flow loop 2032;

performance of CP-2032,

rev.

3.

~

Performance

of PT-5. 10, rev.

25,

Process

Instrumentation

Reactor

Protection

Channel Trip Test (Channel

1).

~

Periodic testing

and maintenance

of the security emergency

diesel

generator

per PT-12.3,

rev.

5.

Each of these activities was performed in accordance

with adequate

procedures.

1

In performing IEC/Electrical maintenance activities,

review is required

for failure analysis

and reporting (A-25.2). These reports

are initiated

by IKC/Elect staff any time that

a failure is identified in a safety-

related activity.

Mhen

a failure report is generated

in this manner,

it,

is evaluated

by the

18C supervisor

for appropriate corrective action.

The

inspector

reviewed these failure reports:

Item:

FQ-619

Function:

power supply,

comp.

cool

loop 619

Failure:

voltage out of

tolerance

Corrective Action:

replacement

RMS R-2

.

LT-2044

TT-401

power supply

sump

A level

Tave

Ch

1 dual

current

source

HV below spec

failed high

capacitors

5

potentiometer

replacement

ordered,

replaced

replaced

parts

These specific reports

and

a sampling of about

50 others

generated

in the

period 1982-1985

were reviewed by the inspector for adherence

to the

administrative

procedure,

proper identification of failures

and

use in

trending failures.

No problems

were identified.

No trends

were observed.

The inspector

reviewed the use of M&TE by electrical

maintenance

personnel

to verify adherence

with procedure

A-1201.

The results of this review

were:

Digital multimeter Fluke model

8200A, s/n 75949,

was not on

a shop

recall list for February

1985 as required

by section

3. 1.2.3 of

A-1201.

This discrepancy

was corrected during the inspection.

Digital multimeter

HP mode 3466A, s/n

15926,

was not calibrated

on

its mi lliamp range.

Section

3. 1.2.5 of A-1201 requires

labels to

indicate restrictions.

Upon questioning,

licensee staff were aware

of the restriction

and

showed the inspector

the restriction label.

Cl

,>1

10

~

AMP electrical

crimping tool, s/n B-43,

was noted to be past

due for

calibration.

The due date

was 11/24/84

as penciled in Scotch tape

on

the tool handle, with no calibration date.

The inspecto}

examined

the

electrical tool calibration log maintained

by the

R&T group

and noted

seven

crimping tools were listed as missing:

B-2, B-9, B-ll, B-43,

B-47, B-51,

and B-52.

The inspector

informed this group that

he found

B-43.

No explanation

could be given to determine

what circuits may

have

been

crimped with the tools listed as missing.

~

Multi-Amp test set

model

CB-7150,

s/n

18553,

was identified by

QC

surveillance

not to have

been calibrated.

Corrective Action Report

(CAR) 1595 dated

10/24/84 stated that the test set

had not been

calibrated

since

purchase

in 1971.

The inspector

reviewed the cali-

bration report generated

by the vendor as part of this corrective

action.

The calibration

was done

on 1/23/85. llhile the vendor found

the test set out of tolerance

as found,

an analysis of the

as found

and as left values

performed

by the inspector concluded that the

'ifferences

were not significant (maximum

3% on one range).

The inspector

noted

no case of performance of safety-related activity

performed with improperly calibrated

instruments.

However,

the discre-

pancies

noted above,

along with those

noted elsewhere

in this report,

result in an assessment

of weakness

in the oversight

and control of M&TE.

In following QC surveillance of electrical activities,

the inspector

reviewed Quality Control Surveillance

Report

(QCSR) 85-0013 which

described cutting of a ring tongue terminal attached

to alarm bistable

PC-937 A/B used for control

room annunciation if pressure

transmitter

PT-937 failed. This transmitter is one of two measuring

Accumulator Tank 2

pressure.

The

QCSR was dated

1/18/85

when

QC witnessed

performance

of

CP-939.

The 1&C/Elec maintenance

foreman

who dispositioned

the

QCSR did

not recommend

any corrective action.

QC rejected this disposition

and

generated

Nonconformance

Report G-85-013 dated

1/28/85 requesting

a cor-

porate engineering disposition.

The engineering disposition

was "use

as

is" on the basis that Specification

EE-29, rev.

6 dated

12/20/83,

states

that

a ring tongue terminal shall

be used unless

an alternate

tongue is

approved

by engineering.

The inspector questioned

the specific applica-

tion and examined

the installation in the presence

of a licensee

repre-

sentative

in the relay room cabinets

in order to verify that the Ll hot

leg on the bistable

was for annunciation

only and that

a separate

power

supply fed the loop for PT-937

so that the accumulator

pressure

channel

would function as designed

in event of loss of L1. This was verified by

the inspector

and satisfied his question.

The inspector

reviewed procedure

M32.2, rev. 4,"DB-50 Reactor Trip Circuit

Breaker Inspection,

Maintenance

and Test" to verify that the testing

provisions of NRC Generic Letter 83-28,

"Required Actions Bases

on Generic

Implications of Salem

ATWS Events",have

been

implemented at Ginna.

Review

of the completed

procedures

and discussions

with responsible

staff

revealed

no difficulties in performing this maintenance

and testing.

However,

the licensee's

response

letter dated

11/4/83 stated that trending

the performance of the reactor trip breakers

started with the

1983

refueling outage.

Staff members

were familiar with test results

and

trends,

but there

was

no procedural

requirement for trending.

Since the

procedure

is being revised to incorporate other

NRC comments

regarding

vendor owners'roup

recommendations,

an Unresolved

Item (50-244/85-04-02)

results until all commitments

are incorporated

in plant procedures.

Control

and availability of vendor manuals,

vendor information and

use of

this information in maintenance

and procurement activities was reviewed

by the inspector.

No discrepanices

were identified.

2.3

Corrective

and preventive I&C/Electrical maintenance activities were

performed

by experienced,

adequately

trained, qualified personnel.

Pro-

cedures

used

were adequate

for controlling activities. guality control

hold points were established

where required,

observed

and documented.

Additional problems in calibration

and control of measuring

and test

equipment

were noted, further substantiating

the assessment

of weakness.

( Inspector

Followup, Item 85-04-05).

INSTRUMENTATION AND CONTROL ACTIVITIES

Under the Maintenance

Manager,

the

ILC Supervisor is responsible

for

overall supervision of the

I&C group

and the plant electrician group.

Each

group

has

a forema'n responsible

for the

group's activities.

The inspec-

tor noted that the staffing level in the

I&C group is adequate,

with

twelve regular technicians

reporting to the

I&C foreman

and three

temporary helpers reporting'irectly to the

I&C Supervisor;

the group has

a very low turnover rate.

Training provided by the licensee

was primarily

vendor-information oriented.

The inspector

lear'ned that plant systems

training for the technicians

is planned;

the individuals expressed

a

desire for this training, particularly if it emphasizes

reactor control

and protection.

The inspector

selectively followed up on the licensee's

review of IE

Information Notice 84-70,

Reliance

on Mater

Level Instrumentation with a

Common Reference

Leg, to determine

the adequacy of review and incorpora-

tion of operating

experience.

This information notice was handled through

the plant's task assignment

system

and jointly reviewed

by I&C and Opera-

tions staffs.

The conclusion

reached

by these

groups that

no similar event

is likely to occur in this plant was forwarded to the Assistant Superin-

tendent.

Based

on document review and discussions

with cognizant

personnel,

the inspector determined that the review was timely and

technically sound.

The inspector

observed

on-going

I&C calibration

and surveillance

activities to verify the following:

~

Required

procedures

were available,

in use

and followed.

,X,tt

4+

t

Cl

12

~

Special test equipment

was calibrated

and in use.

~

Test prerequisites

were met and initial conditions were

pr operly observed.

~

Technical

content of procedures

was adequate

to result in

satisfactory

component or system calibration

and test.

Calibration,

maintenance

and surveillance tests

observed

in addition to

those previously noted included:

~

CP-2019, Calibration and/or Maintenance of Turbine Driven

Auxiliary Feedwater

Pump Discharge

Pressure

Loop 2019

The inspector

noted that these activities were being performed in

accordance

with approved

procedures

by qualified personnel

using

calibrated

instruments.

CONCLUSIONS

Maintenance

is performed

by an experienced,

well'-qualified staff who follow

approved

procedures.

A well-defined training program for this experienced

staff has

been developed,

but not fully implemented.

(Inspector

Followup

Item 50-244/85-04-06).

One instance of failure to adhere

to

a procedure

for preventive maintenance

of valves

was noted.

A procedural

weakness

in

trending reactor trip breaker test results

was in the process

of being

addressed.

Maintenance

Mork Requests

and other documents

were complete;

however

a large

number were outstanding

and administrative closeout

was

slow, leading to an assessment

of weakness

in documentation

of maintenance

activities.

This assessment

is further borne out by the incompleteness

and out-of-date entries

in the maintenance

history file.

Problem areas

were also noted in the calibration

and control of measuring

and test equip

ment, but no safety-related

work appeared

to be affected

by these

problems.

3.0

SURVEILLANCE

Various groups perform surveillances

depending

upon the type needed.

Several

surveillance activities

have

been discussed

in preceeding

sections

of this report.

The performance

type of surveillance

(PT series)

is

scheduled

by the

R&T group in accordance

with the time interval specified

in Technical Specifications

(TS).

This schedule

is then transmitted to

the appropriate

groups through the weekly plant interface meeting.

The

R&T

Supervisor

has the overall responsibility to ensure that all

PT survei 1-

lance tests

are properly performed,

evaluated

and documented.

Operational

survei llances

such

as daily thermal

power calculation,

nuclear

instrumen-

tation response

and reactor coolant

system

(RCS) leak rate are conducted

by operations

personnel.

Observation of conduct

and discussion

of methods

and results

in the areas of Operations,

Results

and Tests

and Reactor

Engineering

were carried out by the inspector during this inspection.

13

3.1

OPERATIONS

The safe

and efficient operation of the plant is the primary responsi-

bility of the Operations

Manager,

who reports directly to the Assistant

Superintendent.

An Operations

Supervisor

provides the manager with a

comprehensive

day-to-day review of plant activities.

There are five

shifts in plant operations,

with one shift rotating into the office for a

six-month in-office duty schedule.

Activities and interfaces affecting

maintenance

were discussed

with various

members of the operating staff by

the inspectors

All shift supervisors

interviewed stated that they were given very good

support

from the maintenance

group.

The normal

channel

for requesting

maintenance

work is the

MWR (A-1603).

However,

when

a problem necessi-

tates

expedited solution,

informal methods

are also

used.

An example oc-

curred during this inspection.

On February

6,

1985, at about

4: 15

pm,

minutes before the regular quitting time, the control

room operator

noted

that the Tavg circuit exhibited erratic behavior which caused

unwanted

control rod motion,

an alarm

on Tavg deviation

and

an increase

in charging

pump speed.

The

IEC group was notified by telephone

and quickly responded.

The cause

was identified as

a bad switch contact

and was corrected

by

about 6:30

pm when the plant returned to normal operation.

Discussion with

the

IKC foreman revealed that

no followup paperwork

was generated

in this

case

because

a similar problem occurred earlier in the week and it was

being tracked with MWR 85-374.

The inspector

observed

plant operations

during the course of the inspec-

tion.

Control

room and shift manning were observed for conformance with

TS and administrative

procedures.

Various alarm conditions which were

acknowledged

were discussed

with shift personnel

to verify that the rea-

sons for the alarms

were understood

and corrective action, if required,

was being taken.

The inspector

reviewed results

and performance of several

operational

sur-

veillancee

procedures.

S-12.4,

"RCS Leakage Surveillance

Record Instructions",

rev.

15, describes

methods

for

RCS leak rate determination.

These consist

of radiation monitoring of containment air particulate

and radiogas,

humi-

dity in containment,

containment

sump

pump actuation

and

RCS system inven-

tory.

Indication of leakage

by any monitoring method exceeding

a pre-de-

termined value constitutes

a significant increase

in leak rate.

Operators

are then required to initiate action per procedure

S-12.2

and report the

results

through the Operations

Manager to the Plant Operations

Review Com-

mittee

(PORC).

The inspector

reviewed

a two-month sample,

October

1 to

November 30,

1984,

and noted that there were

47 S-12.2 reports

(33 due to

R-11 radioparticulate,

2 due to R-12 radiogas,

4 due to

sump

pump actuations

and 8 due to humidity) which triggered

a significant leak rate investiga-

tion. In none of these

cases

was there

a true

RCS leak.

Much operator time

was diverted to performing and documenting

these

unwarranted

investigation's.

I

I

14

The inspector

reviewed the

system inventory method

used in S-12.4 for

technical

adequacy.

The accuracy of the current method is adequate if it

is employed with no change

in pressurizer

level

and Tavg for a reasonable

test duration.

None of these conditions are given as precautions

or

limitations in the procedure.

Interviews with operations

personnel

indicate that they are

aware of the limitations and

have not experienced

difficulty in executing

the procedure

when the unit was in steady state

conditions.

There were times,

however,

when the test

had to be repeated

to meet acceptance

criteria, especially

when

power level

was changed.

The licensee

is in the process

of evaluating data obtained

from these

tests

in an effort to improve the procedures

and reduce

the

number of

unwarranted

leak rate investigations.

During control

room observation,

the inspector

noted that level indication

from both accumulator

tanks

was irregular.

Both accumulators

were exper-

iencing leaks.

The leak pathway is believed to be through the liquid fill

isolation valves,

V-835A and B, into the 3/4" safety injection test line

and then through the test line safety relief valve SRV-887 to the Pressur-

izer Relief Tank (PRT).

The inspector

made

independent

observations

and

calculations to verify that the inventory loss

from the accumulators

is

approximately

equal

to the

PRT inventory gain.

TS limits for accumulator

water volumes are

maximum,

82% and minimum ,50%.

Alarm setpoints

are

high,

75% and low,

57%.

As a result of existing leakage,

the accumulators

have to be charged

about twice per shift.

The inspector

noted that the

charging operation

was conducted

in accordance

with procedure

S-16. 13.

This problem was initially identified in May,

1984

and described

on MWR's

84-1351

and 84-1411;

these

MWR'

were still open at the time of this

inspection.

The rate of leakage

and the conduct of the charging operation

were familiar to maintenance

and operations

personnel

interviewed.

The

leakage

problem is being closely monitored

by operations

and maintenance

personnel.

Repair of the valves is scheduled

for the March,

1985 refuel-

ing outage.

The inspector

found that the plant was operated

by highly knowledgeable

personnel

in a concientious

manner.

Key positions

in the operations

group

are held by very experienced staff; most

have worked with the plant for

more than

10 years.

Information exchanges

include weekly discussion

sessions

and circulating memoranda for operations

personnel.

No unaccep-

table conditions were identified.

3.2

RESULTS

AND TEST

GROUP

The

R8T Supervisor is responsible

for all

TS surveillance

items.

Surveillance

schedules

are disseminated

at weekly plant interface

meetings.

There are

seven test technicians

in the group.

The

RAT

Supervisor reports to the Technical

Manager.

The inspector

verified that all test personnel

are qualified as

Level II inspectors

in

accordance

with procedure

A-1102.

Through staff discussions

and test

observations,

the inspector

determined that test personnel

were

know-

ledgeable

in their areas

of performance.

The inspector

observed

portions of these

surveillance

tests,

both

in the field and in the control

room:

~

PT-37.8,

1A 5 1B Vapor Container Auxiliary Filter Fans

Mass

Air Flow Check,

performed

February 6,

1985

~

PT-2.3. 1, Post Accident Charcoal Filter Dampers,

performed

February

6,

1985

~

PT-16, Auxiliary Feedwater

System,

performed

February

13,

1985

Reviews of the completed tests

were conducted

by the

R&T Supervisor.

The

inspector

found the tests

and post-test

reviews to be adequate.

While observing

PT-16, the inspector noticed that the manual isolation

valve,

V-4345,

from the service water line was closed

and padlocked;

how-

ever,

the Piping and Instrumentation

Drawing 33013-545,

rev.

3,

showed

a

normally open valve

on

a controlled copy dr awing.

In discussion with

control

room operators,

the inspector

learned that there is awareness

of

this information conflict.

The operations staff relies

on procedure

A-52.2. 1, "Inventory of Locks and Keys", rev.

4 for the proper locked

valve positions

and not on

PAID drawings.

A major drawing update

and

revision effort is nearly complete;

the inspector

examined

a draft P&ID

for the auxiliary feedwater

system,

33013-1237,

rev. 0,

and noted that the

correct, position is

shown for valve V-4345.

The drawing update

program is

discussed

elsewhere

in this report.

The inspector

had

no further

questions.

In the course of reviewing open

MWR's, two similar reports - 84-1351 dated

5/15/84 and 84-1411 dated 5/22/84 - identified a similar problem.

The

inspector ascertained

that the problem identified, possible

check valve

leakage

on the auxiliary feed

pumps,

was identified

as industry wide at

the time.

The approach

used at Ginna was to revise

Procedure

PT-16,

the

monthly surveillance test

on auxiliary feedwater,

to include

an additional

step 6.6. 18 to check that all discharge

piping returned to ambient temper-

ature at the conclusion of the surveillance.

The inspector verified in a

quarterly

sample that Revision

41 which contained this step

was performed

on 7/2/84, 8/6/84 and 9/14/84 and the step

was initialed and checked.

Maintenance

and Results

and Test staff interviewed were familiar with the

problem and solution.

On further inquiry, the inspector ascertained

that

the open

MWR's were in the possession

of the mechanical

maintenance

foreman,

who wanted to assure

himself during the March 1985 outage that

no

further problems

were associated

with these

check valves before closing

out the MWR's.

The inspector

had

no further questions.

Another function of the

R&T group is trending of test results to analyze

performance

and identify adverse

trends.

The inspector

reviewed

log-books

on valve stroke time tests,

plots of pump performance

data,

logs of containment penetration

leakage data,

monthly summaries of total

containment

leakage

and the reports of performance

of the program for

16

leakage

reduction outside containment.

The logs and plots noted

acceptable

ranges for the various parameters

and were kept in

a neat

and

logical manner which made it a simple task to identify adverse

trends.

The inspector

noted

no adverse

trends

in this review.

3.3

REACTOR ENGINEERING

Core performance

evaluation is the primary responsibility of the Reactor

Engineer.

He reports to the Technical

Manager.

The inspector

reviewed

several

aspects

of core performance.

Measured

values of the reactivity

anomolies plot maintained

since the beginning of this fuel cycle are in

good agreement

with predicted values.

The plant is now near its predicted

End-of-Cycle

(EOC) fuel burnup

and is undergoing

coastdown.

As of

February

12,

1985,

the cycle burnup value is 8660

MWD/MTU.

The reload

safety analysis

covers

burnup

up to 9700

MWD/MTU.

The coastdown

operation

is conducted

according to operations

procedure 0-6.2, Plant Operation

During Coastdown,

rev.

2.

Average

Tavg during this coastdown is planned

to decrease

about

3~F below T-reference.

A thorough study of plant

behavior resulting

from Tavg reduction

was conducted

on September

23,

1982

by actually reducing

Tavg by 15'F in a test.

The test demonstrated

no

operational difficulties.

During the course of this inspection,

control

room parameters

were

observed;

these

were closely monitored

by the operators

and printed

on the

trend typer.

Tavg was maintained within the intended

range.

Through

discussi,ons

with the reactor engineer

and control

room operators,

the

inspector determined that the plant staff was knowledgeable

in the

technical

issues

associated

with coastdown operations'o

deficiencies

were noted.

CONCLUSIONS:

No problems

were noted for the survei llances

observed

and reviewed.

The

Operations,

Results

and Test

and Reactor Engineering staff who performed

these

survei llances

were knowledgeable,

experienced

and qualified.

A

viable information exchange

process

was observed,

as well as

good working

relationships with the maintenance

staff.

A large

number of leak rate

investigations

per procedures

S-12.4 were identified by the plant staff

and discussed

in detail with the inspector;

evaluation

and possible

revision of procedures

is underway.

Trends of test results

were available

and analyzed appropriately

by Results

and Test Staff.

Control

Room opera-

tions were conducted

in conformance with regulatory requirements

and pro-

cedures.

4.0

RADIOLOGICAL CONTROLS

The Manager of Health Physics

(HP) and Chemistry is the responsible

manager for radiological controls.

He is

a member of the Plant Operations

Review Committee

(PORC).

In this capacity,

he participates

in the review

of safety-related

work and changes

to safety-related

procedures.

He also

participates

in station planning meetings

such

as daily and Outage

Planning meetings.

From these interactions,

the Manager of HP is made

17

aware of ongoing

and planned work.

The Manager

and the department staff

are well experienced

and highly qualified. All key positions are filled.

Turnover of personnel

has

been very low at all levels.

During the planning stages

for outages,

a major function of the station

radiation protection organization

is to provide reviews of planned work

for radiation exposure minimization (ALARA).

As specific work is

scheduled,

the

ALARA coordinator

arranges

for a formal review by the

ALARA

committee.

As the planning

and workload are developed

from these

analyses

and reviews,

the

HP staff arranges

for additional technician

support

and

material

and equipment

such

as protective clothing and radiation

survey

instruments

to support the outage.

The corporate

Health Physicist,

a position recently filled, is not

currently involved in outage

planning,

although

a large part of the outage

work involves modifications determined

by corporate

engineering.

The

corporate

HP has provided corporate

management,

including the Nuclear

Safety

And Review Board

(NSARB) with information reg'arding HP-related

performance

during past outages

and with impacts of regulatory changes.

The inspector

noted that

a position description for the corporate

HP had

not yet been developed.

The

HP department

'does not provide training for outage workers; this is

provided

by the Training Department.

The steam generator

repair group

provides its

own extensive training, including practical

work on two

mockup

steam generators

for workers assigned

to the testing

and repair of

the

steam generators.

A separate

building and staff are dedicated

to this

effort.

Other training in support of the

HP program

and outage prepar-

ations is determined

and provided by the Training Manager.

The Training

Department

provides this training at the Training Center adjacent to the

stat,ion.

The inspector

noted from review of reports

and records that, until the

year

1984,

accumulated

worker exposures

had been higher than average for

pressurized

water-reactor facilities.

A notable

change

occurred in 1984

when the exposure total

(380 man-Rem)

was less .than

40% of the exposure

total for 1983 (960 man-Rem).

The licensee

has been, trending

and analy-

zing the exposure

data.

The licensee

has concluded that most of the

personnel

exposure is associated

with two major outage activities,

steam

generator

inspection

and repair

and installation of seismic restraints

inside containment.

The sharp drop in exposure

from 1983 to 1984 was

attributed to the completion of major portions of these activities which

began

in 1977.

Further sizeable

decreases

in cumulative exposure

are not

anticipated.

An exposure

estimate

made prior to the

1983 outage

indicated that all work

scheduled for the

B steam generator

channel

head could not be completed.

As

a result,

the licensee

performed

a chemical

decontamination

of the

B

steam generator

using the

London Nuclear process.

An initial reduction

factor of 10 was obtained.

The dose rates

measured

during the

1984 outage

indicate that the radiation levels

have increased

only slightly.

The

18

result of the decontamination

was

a significant reduction in personnel

exposure

during work on the

B steam generator.

The licensee

has not

decontaminated

the

A steam generator

and

has

no current plan to do so.

Discussions

with the

steam generator repair group revealed that

an

aggressive

search

is underway to identify exposure

reduction techniques.

Several

of these

have

been identified, but there is no firm plan to

implement these

in the

1985 outage.

Funding for purchase

of a steam

generator

head

manway bolt detensioner

apparently

has

been

approved,

but

the equipment

has not yet been ordered.

A plan to purchase

a robot mani-

pulator

arm in 1986

has

been discussed.

Several

designs

have

been

reviewed

and experiences

of others

have

been

sought,

but

no selection

has

been

made.

The capital outlay associated

with this equipment is

a major

concern to the licensee

and has led to slow and cautious

progress.

Discussions with maintenance

foremen

and engineering

personnel

indicated

that

no major changes

to present practices

in order to reduce

exposure

were anticipated.

The widespread belief held by sev'eral

groups

was that

most work improvements

have already

been

incorporated

into procedures

and

practices

and that only experienced

workers are

used in radiation exposure

situations.

An estimate for th'e expected

exposure for the

1985 outage

scheduled

to

begin in early March was not available.

This was due,

in part, to the

fact that

a firm schedule

of outage work was not completed.

An Outage

Coordinator

was designated

during the inspection to oversee

outage

work

planning

and control of work during the outage.

However, this was done

only three

weeks prior to the outage.

Corporate

engineering direction of

their portion of the outage work schedule

was not firm and further re-

direction was possible.

The inspector

expressed

concern that the brief

time remaining

may not allow completion of thorough

ALARA reviews or the

implementation of the

recommended

ALARA controls.

The ALARA coordinator

advised that reviews were completed for work, although the jobs were not

yet scheduled.

If specific jobs are postponed

to the next outage,

the

ALARA review would be filed until needed.

Work that was not reviewed would

be controlled by withholding issuance

of a Radiation

Work Permit

(RWP).

The inspector

noted that the

ALARA committee consists

of supervisors

from

several

groups,

including HP.

This permits

a good exchange

of information

regarding

the work.

Cooperation

and coordination

between

the various groups

was excellent.

All supervisors

interviewed were knowledgeable

of the

HP requirements

and

displayed

a good understanding

of the

ALARA concept.

The

HP Manager

, his

staff and the

ALARA coordinator were fully knowledgeable

of the status of

outage

planning,

including ongoing changes.

There

was

much informal com-

munication

between

groups.

Formal information such

as the outage

schedule

was generally

sparse

and outdated

due to rapid and frequent changes.

A review of procedures

showed that all repetitive maintenance

is controlled

by procedure.

These

procedures

contain hold points that ensure

the

necessary

radiological precautions

are taken.

Due to this good control,

Ji

h

19

only new maintenance

and non-recurring

work are afforded

a formal

ALARA

review.

Changes

in scope that occur while a job is in progress

due to

unanticipated

situations

are controlled by issuance

of a Procedure

Change

Notice (PCN).

HP personnel

participate

in the review prior to issuance

of

a

PCN to ensure that the radiological controls are adjusted

or an

ALARA

rereview is performed.

During an outage,

foremen are provided the

exposure

status of their personnel

on

a weekly basis.

Post-job reviews are conducted

by the

ALARA committee to review exposure

estimates

which were in error by 25% or more

and also

by maintenance

personnel

to document

any lessons

learned.

Significant concerns identified

during the post-job reviews are brought to the Post-Outage

Review meeting.

Any improvements

or suggestions

are documented

for use during subsequent

outages.

CONCLUSIONS:

Outage radiation exposure

planning at Ginna station 'is competent

and

thorough,

although

much is accomplished

on

an informal basis.

Workers

will be protected

adequately

by the various controls that are in

placebo

All levels of management

exhibit a strong

commitment to radiation safety

and the

ALARA program.

The various

programs

and procedures

receive

frequent attention in order to identify areas for improvement.

Channels

of communication

and cooperation

to effect changes

are very good.

These

excellent indicators are

somewhat

shadowed

by

some complacency

and accep-

tance of current levels of personnel

exposure

rather than setting

improvement goals

and

ALARA target reductions.

The review of station

safety

programs

by NSARB are rigorous.

5.0

QUALITY ASSURANCE

PROGRAM OVERVIEW

The Manager of Quality Assurance

reports

through the Chief Engineer to

the Senior

Vice President

Operations.

The Manager of Quality Assurance

and his staff are located at the corporate

engineering offices.

In addi-

tion,

a Nuclear Assurance

Manager

on the staff of Ginna Station oversees

the work of the onsite Quality Control Engineer

and his group.

There is

also

an interface with Project Quality Control inspectors

who do on-site

inspections

of contractor

work.

The inspection

reviewed efforts of all of

these

groups

and their interfaces with maintenance

and surveillance

activities.

5.1

AUDITS AND VENDOR SURVEILLANCE

The Quality Assurance

(QA) group has

been delegated

the responsibility

to

conduct those audits required

by 10CFR50,

Appendix B, and

TS.

These

responsibilities

include evaluation

and surveillance of suppliers

and

vendors

and also trending of quality program elements.

20

The group consists

of a

QA Manager

and four

QA inspectors,

with one vacant

position.

The manager

stated that recruitment is ongoing to fill the

vacancy.

The

QA inspector hired within the past year has

been attending

training cour ses to fulfillhis auditor qualification requirements.

The

remainder of the staff are

long term employees

who had completed

these

requirements.

There are

no formal refresher training programs

and

none

are anticipated.

The experience

level

and training provided meet

QA

program commitments.

The

1985 audit schedule lists two semiannual,

three triennial

and forty

annual

audits.

The matrix format of the schedule

also identifies organi-

zations to be audited (Engineering,

Purchasing,

Service Contractors,

Ginna Station)

and the functional activities to be audited within those

organizations.

The

1984 audit schedule

was similarly constructed.

Vendors are evaluated prior to their classification

as suppliers of

certain products. Evaluations of acceptable

vendors

are

done biennially and

an onsite audit of each acceptable

vendor is conduct'ed triennially.

The vendor audit schedule lists seventeen

audits for 1985.

Vendor sur-

veillances

are conducted

as

needed.

Participation

in and

use of the

industry

CASE audits represents

the basic tool for vendor evaluation;

considerable

use of consultants

is made to conduct the

CASE audits.

The majority of audits were conducted

by one person

and averaged

three

days. It was noted that the

QA Manager

was designated

lead auditor for 12

of the scheduled

1985 internal audits

and would participate

in a number of

others,

in addition to his managerial

duties.

Checklists

were standar-

dized, but

showed evidence of slight modification from year to year.

The

seven audit checklists

reviewed in depth

by the

NRC inspector

ranged

from

marginal

adequacy

to comprehensive

overviews.

Examples of the former were

85-04

CA, Corrective Actions,

and 84-08

CA, Maintenance Activities; these

checklists did not provide guidance

or instruction to the auditor to

sample

both existing

QC Survei llence

Logs for the status of open findings

nor an adequate

sampling technique for maintenance activities.

As a

consequence,

the auditor failed to identify a buildup of open

QC survei 1-

lance findings (see Section 5.2.2)

and to note the deficiencies

in per-

formance of

PM on valves (Section

2. 1) since only 8 pumps were

sampled

from a potential

population of 5000 specific maintenance activities.

On

the other hand, checklists

and manual

tracking matrices for audit of TS

requirements

assured

that each individual

TS item would be

sampled during

a given time period.

The failure of the corrective action audit described

above to identify the

backlog

and buildup of open

QC surveillance findings indicated that the

actions described

in the licensee's

August 9,

1984 response

to Item A of

the Notice of Violation attached

to the

NRC

Region I letter of July 16,

1984 were not fully effective. This noncompliance

(50-244/84-13-01)

remains

open for further review of the effectiveness

of the proposed

corrective action.

(t}

21

In the course of reviewing audit 84-30

SB, Triennial Fire Protection,

the

inspector

noted that many of the findings were invalidated by the

QA

Manager during his review of the audit.

Upon questioning,

the manager

stated that the auditor did not understand

the relief requests

made to

NRR

for exception

and relief from certain requi rements

in this area.

The

acceptability of these invalidations is an unresolved

item (50-244/85-

04-03)

and will be examined

in a future

NRC inspections

Trend analysis

conducted

by the

QA group, including the formal report, is

quantitative only.

No effort is made to present

analyses

or statements

of

significance of trends.

On the whole, the

QA group meets its functional

and performance

respon-

sibilitiess.

5.2

QUALITY CONTROL

The onsite

group assigned

the inspection

and surveillance

or monitoring of

ongoing activities is designated

Quality Control

(QC).

Six plant

QC

inspectors (five contract,

one

RG5E) report to the Plant

QC Supervisor.

Four contracted

Project

QC inspectors

report to

a Project

QC (contractor)

Supervisor.

Both supervisors

report to the Plant

QC Engineer.

Plant

QC

inspectors

generally overview operational activities, while Project

inspectors

generally overview contract work, mostly modification activi-

ties.

The Plant

QC Supervisor

reviews qualifications

and interviews

contractor

inspectors prior to their acceptance

for onsite

QC work.

He

also administers testing for certification as required

by the

QA program,

schedules

and coordinates

supplementary

training for inspectors.

All QC

inspectors

have taken

or are

scheduled

to take the licensee's

onsite

PWR

Systems

Course.

Supplementary

in-house

inspection

courses

and offsite

third party courses

are regularly provided to

QC inspectors.

A review of

several

inspector qualification folders indicated extensive

experience,

formal classroom training,

and proper certification, obtained for the most

part by examination.

A more formalized training program is under develop-

ment.

Plant

QC regularly conducts

surveillances

of ongoing activities. Project

QC conducts

surveillances

of contractor site

QA and

QC activities.

Plant

work procedures,

including maintenance

procedures,

are reviewed

by QC;

these

procedures

include inspection points.

There are also

a number of

instances

where licensee

witness or inspection points

have

been inserted

into contractor work procedures.

Approximately 120

QC hold points

have

been completed to date in addition to more than

1000

QC surveillances.

Deficiencies identified by these

survei llances

and inspections

are docu-

mented

and tracked for corrective action

on

QC Surveillance

Reports

(QCSR).

If the deficiency is significant, it can

be escalated

to

a

Corrective Action Request

(CAR) and resolved

by the mechanism of station

procedure

A-1601.

Review of the Plant

QC Surveillance

Log identified an

open backlog of over 50 QCSR's,

some dating to 1983.

The

NRC inspector

reviewed all open

QCSR's to ascertain their significance

and the effec-

tiveness of this corrective action

system.

The review yielded

12

QCSR'

22

of some safety significance;

these

were presented

to the licensee

to

determine

status prior to conclusion of the inspection.

The documented

status of all of these

reports (e.g.,

work orders written,

CAR's being

resolved,

engineering

requests

formulated) were reviewed in depth

by the

inspector

and it was determined that actual

or proposed corrective actions

had been

adequate

and timely.

The apparent

inattention to gCSR responses

was discussed

with licensee

management;

this management

had already

identified the problem and provided

a recent

procedure

change that estab-

lishes

response

times for gCSR's.

The large backlog

and

the lack of

attention to timely closure of gCSR's

are further indicators of the weak-

ness

in completion of maintenance

and surveillance

admi ni strative docu-

ments in

a timely manner,

as noted previously in Section

2.

5.3

WAREHOUSE ACTIVITIES

One of the in-plant storage

areas

was toured to determine that adequate

environmental,

cleanliness,

access,

shelf life and traceabi lity controls

had been

implemented.

The area

was temperature

controlled, clean,

locked

and not overcrowded.

Identification was

on items *and their location was accurately controlled

by the inventory log (a sample).

Several

items subject to deterioration

(i.e. shelf life) were

sampled

and found to be included in the shelf life

program.

Practices

in this particular area

were

deemed

to be in accordance

with gA

Program requirements.

CONCLUSION:

The onsite inspection

and surveillance effort exceeds

the licensee's

QA

program requirements,

particularly in areas

such

as inspector training and

qualification and inspection

scope

which includes non-safety-related

activities.

Lack of gCSR closeout contributes

to an assessment

of a weak-

ness

in timely documentation.

6.0

OTHER ORGANIZATIONS AND ACTIVITIES

6.1 OFFSITE

SAFETY REVIEW COMMITTEE

The Nuclear Safety Audit and Review Board

(NSARB) has the responsibility

to per form the corporate

overview function as established

in TS.

Member-

ship of the Board comprises

senior plant and corporate

managers.

This is

supplemented

by outside consultants

who have extensive

experience

and

expertise

in specific areas.

The personal

secretary

to the Vice President - Production

assembles

docu-

ments requiring Board review.

This secretary

forwards these

to the Board

members

and performs the other administrative duties associated

with the

Board's operation.

The Board members

review the information packages,

request additional

information and communicate with others.

The

NSARB

k

II

y,,

'gl

, ~ '

23

Secretary,

the Plant

gC Engineer,

develops

the meeting

agenda

and performs

other administrative duties.

No procedures

have

been formalized to des-

cribe these

functions.

Further,

the

NSARB charter

has not been

reviewed

nor updated

since

issuance

in 1978.

The inspector attended

a portion of a regularly scheduled

NSARB meeting.

The agenda

and the report were formatted to coincide with the responsi-

bilitiess

set forth in TS.

The agenda identifies the subjects

and the

speakers.

Individuals making technical

presentations

were identified and

scheduled.

Board members

were well prepared

and did participate

in dis-

cussions.

Technical

presentations

were well planned

and

used effective

visual aids.

This Board is executing its responsibilities

in an agressive

and competent

fashion.

However,

review of TS audit activities is not

so thorough

as

the Board's

involvement in other areas.

In sum, this Board is performing

in a manner that is

a strength of the licensee.

6.2

ENGINEERING SUPPORT

The inspector discussed

engineering

support with maintenance

supervisors

and

members of the onsite

and offsite engineering staff.

The engineering

personnel

were knowledgeable

of projects

supporting

Ginna.

Their involve-

ment fell into one of three categories

- support of ongoing maintenance

and operations,

modifications to meet regulatory requirements

and modi-

fications to improve plant performance.

Examples of all three types were

discussed.

One major project which touches

on all three categories

is the

computer-based

plant drawing and diagram program.

This project was in the

final stages

of verification with implementation

planned

upon restart

from

the March 1985 refueling outage.

The computer

based

drawings will replace

the original plant drawings at that time.

Some of the capabilities

demonstrated

to the inspector

included the uniformity of nomenclature,

lettering and symbology,

the design

and specification detail maintained

in

the computer data

base for components

such

as valves

and the ease of

revision under

a carefully controlled change

system.

Drawings were

available within minutes

from the computer plotter; it is planned to have

a plotter at the Ginna site

as well as the existing

one in the engineering

offices.

The inspector also

reviewed the drawing verification program

being conducted

by the Operations

Department.

An example of the detail

available is noted in Section

3.3 above.

6.3

The inspector

noted that there

was considerable

communication

between

the

engineering

department

and various Ginna Station staff which included

frequent meetings

on issues of interest engineering

reviews

and

recommen-

dations for events at Ginna and other plants.

TRENDING AND REPORTING

The Operational

Assurance

Engineer

(OAE) and Shift Technical Advisors

(STA) have

a responsibility to review the

many reports

and events

and

analyze

these for patterns

and trends.

Such items

as the A25.4 Post-Trip

Review, A52.4 Technical Specification Limiting Condition for Operation

Evaluation,

A25. 1 Plant Events,

Operations

Department

Reports

and Sur-

veillances

are gathered

reviewed,

analyzed

and reported

in a monthly

summary prepared

by an

STA and reviewed

and approved

by the

OAE.

The

inspector

reviewed several

of these

and noted that they were thorough.

The many leakage

investigation reports

per Procedure

Sly 2 identified by

the inspector

and discussed

in Section 3.3 were previously identified in

these

trend analyses;

the

OAE has

recommended

a review and change

in the

threshold for initiation of leakage

search to reduce, the

number of

unwarranted

leakage

investigations.

The review and analysis

done by this

group is technically adequate

and useful.

7.0

The inspector

reviewed the licensee's

data input to the Nuclear Plant

Reliability Data

System

(NPRDS) with the

NPRDS coordinator.

There were

approximately

2400 entries

made to NPRDS.

It was recognized

in December,

1984 that

a major effort would be

needed

to obtain

and enter

the addi-

tional

2500 items

needed

to bring the

system current

and meet commitments

in this area.

A staffing increase

to 5 persons

has been

approved;

2 are

presently at work, one is expected

soon

and two more have

been

approved.

The coordinator is required to submit monthly status

reports to the Vice

President'nd

Senior

Vice President.

The effort under way is designed

to

meet

a commitment of being

up to date with NPRDS entries

by October,

1985.

CONCLUSIONS:

The Offsite Safety Review Committee is

a strength of the licensee

in the

depth

and competence

of its reviews.

Strong engineering

support is evi-

dent

and closely integrated with maintenance,

operations

and modifica-

tions.

Nuclear assurance

trending

and analysis is thorough

and useful.

Deficiencies in reporting

NPRDS data were recognized

and efforts to reduce

the backlog

and

become current are underway.

MANAGEMENT MEETINGS

A meeting

was held

on February

5,

1985 to introduce the inspection

team

and to identify the

scope of the inspection.

Preliminary results of the

inspection

were presented

to station

management

on February 8,

1985.

An

exit management

meeting

was conducted

on February

15,

1985 to present

the

findings of the inspection.

Participants

are identified in Section

1.3

of this report.

No written material

was given to the licensee

in the

course of the inspections