ML17251A605

From kanterella
Jump to navigation Jump to search
Insp Rept 50-244/86-02 on 860127-31.Violation Noted: Inadequate Corrective Action for Audit Findings Applicable to Insp of Lifting Rigs for Reactor Vessel Head & Internals & Use of out-of-calibr Meggering Device
ML17251A605
Person / Time
Site: Ginna Constellation icon.png
Issue date: 03/04/1986
From: Bettenhausen L, Eapen P, Eichenholz H, Kim T, Paulitz F, Winters R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML17251A603 List:
References
50-244-86-02, 50-244-86-2, NUDOCS 8603170341
Download: ML17251A605 (59)


See also: IR 05000244/1986002

Text

U.S.

NUCLEAR REGULATORY COMMISSION

Region I

Report

No.

50-244/86-02

Docket

No

50-244

License

No.

DPR-18

Licensee:

Rochester

Gas

and Electric Cor oration

49 East Avenue

Rochester

New York

14649

Facility Name:

Inspection At:

R.

E. Ginna Station

Ontario and Rochester

New York

Inspection

Conducted:

Inspectors:

H

Dr.

P.

Januar

27

31

1986

K.

E

en,

ief,

QA Section

Team Leader)

g

d te

H.

ic enholz,

i

Resident

Inspector

d te

Kim,

R

'

t

nspector

Trainee

da

e

F.

P. Paulitz,

Reactor

Engineer

date

Approved By:

R.

W. Winters,

Reactor

Engineer

Dr. L. H. Bettenha'usen,

Chief, Operations

Branch,

DRS

date

date

Ins ection

Summar

Routine

announced

ins ection

on Januar

27 - 31

1986

Ins ection

Re ort No.50-244/86-02

Areas Ins ected:

Effectiveness

of Quality Assurance

and Quality Control activ-

ities in Electrical, Mechanical,

Operations,

Instrumentation

5 Controls

and

Health Physics

areas.

The inspection

involved 152 hours0.00176 days <br />0.0422 hours <br />2.513228e-4 weeks <br />5.7836e-5 months <br /> onsite

by 2 region

based

inspectors,

2 resident

inspectors

and

one supervisor.

Results:

Four violations were identified (Inadequate

corrective action for

audit findings applicable to the inspection of lifting rigs for reactor

vessel

head

and internals;

Inadequate

receipt

and traceability of safety related stain-

less

steel wire rope for auxiliary building crane;

Inadequate

independent verif-

ication for safety related electrical circuit schedules;

and use of out-of-cali-

bration meggering device to megger circuit breakers

for component cooling water

system

pump)

and two unresolved

item (correction factors for battery specific

gravity; and programmatic

concerns

in receipt inspection).

8SOSl7OS4i

ahOSfl

!

PDR

ADOCK OSOOO244

TABLE OF CONTENTS

~Pa

e

1.

Persons

Contacted

2.

Introduction,

Summary

and Conclusion.

3.

Operations

and Instrumentation

5 Control Activities...

4.

Mechanical Activities...............................

13

5.

Electrical Activities

17

6.

Health Physics

and

Chemi stry Activities..

22

'

7.

Licensee Action on Previous

NRC Identified Items.......

8.

Unresolved Items...

~

\\

\\

\\

0

'I

~

~

~

~

~

25

9.

Exit Interview

25

Attachment 1........Details

of the Reactor

Vessel

Head

and Internals

Liftings Rigs Inspection

DETAILS

1.0

Persons

Contacted

Rochester

Gas

and Electric Cor oration

1.2

H. Saddock,

Executive .Vice President

  • R. Kober, Vice President,

Electric 4 Steam Production

~ B.

Snow, Superintendent,

Nuclear Production

  • S. Spector,

Superintendent,

Ginna Production

T. Meyer, Superintendent,

Ginna Support Services

~

R. Mecredy, Director of Engineering Services

~ R. Vanderweel,

Manager,

Project Modifications

  • T. Schuler,

Manager,

Operations

" C. Anderson,

Manager, Quality Assurance

  • J.

Bodine,

Manager,

Nuclear Assurance

  • T. Marlow, Manager,

Maintenance

  • A. Curtis, III, Manager,

Material Engineering

D. Fi lkins, Manager,

Health Physics

5. Chemistry

L. Boutwell, Supervisor,

Maintenance

  • E.

Edger,

Supervisor,

Instrument,

Control

and Electrical

D. Gent,

Supervisor,

Results

and Test

K. Nassauer,

Supervisor,

Quality Control

R. Latz,

Foreman,

Electrical

G.

Foss,

Foreman,

Results

and Test

~ D. VanDorn,

Foreman,

Mechanical

Handling Equipment

N. Goodenough,

Engineer,

Project Quality Control

W. Stiewe,

Engineer,

Quality Control

F. St. Martin, Liaison Coordinator

'. Saporito, Materials Engineering

Laboratory

F. Mis, Health Physicist

US Nuclear

Re viator

Commission

~ W. Cook, Senior Resident

Inspector

  • Denotes

those present at exit meeting.

2.0

Introduction

Summar

and Conclusions

2.1

Introduction

On February

25,

1985,

the

NRC Systematic Appraisal of Licensee

Per-

formance

assessed

the Quality Assurance

(QA) and Quality Control

(QC)

area for the Ginna Station

as Category

3.

In response

to this as-

sessment,

the licensee

established

a task force to review the area

and provide recommendations

to ensure

continued effectiveness

of QA

and

QC activities at the site.

The task force 'completed

an in-depth

study

and

made the following nine recommendations

in November

1985:

1.

Nake Quality Assurance

Accountable to the Executive Vice

President with Chief Engineer providing day-to-day direction

2.

Establish

a Formal Objective

Program for QA Group

3.

Establish

a Priority System (ie Severity Level) for Audit Findings

4.

Continue

Task Force Overview for QA and

QC as Subcommittee

of

NSARB (the off-site-review committee)

5.

Simplify paper

system

and streamline

reporting

6.

Develop education

and information program

on importance of QA/QC

7.

Formalize the interface

between divisions

8.

Specify responsibility for program

and implementation

9.

Review manpower

requirements

and establish

a program to provide

proper people to do job

The licensee

provided

a status of the implementation of the above

task force recommendations

to a regional

supervisor

and

NRR personnel

on December

4,

1985.

2.2

Pur ose of the Ins ection

The purpose of this inspection

was to assess

the overall effectiveness

of the licensee's

QA and

QC activities with special

emphasis

on the

status

and effectiveness

of the implementation of the licensee's

QA/QC task force recommendations.

2.3

Ins ection Methodolo

The effectiveness

of the licensee's

QA and

QC activities was assessed

by reviewing design

changes,

procedure

changes,

maintenance

and surveil-

lance activities and

QA and

QC overview of various activities.

The

QA

audit findings and

QC surveillance

reports

were also reviewed for

adequacy.

The impact of the licensee's

QA/QC task force recommenda-

tions were reviewed in several

areas.

The findings of this inspec-

tion are detailed in paragraphs

3, 4,

5 and

6 and

summarized

below:

Ly

2.4

Summar

of Findin

s

a.

0 erations

and Instrumentation

& Control

(Paragraph

3)

1.

Reactor

Vessel

Head

and Internals Lift Violation

Reactor

Vessel

Head was lifted on May 1,

1983

and

April ll, 1984 without completely inspecting all critical

welds of the lifting rig prior to lift as required

by pro-

cedures.

Reactor Internals

were lifted in 1983,

1984

and

1985 without completely visually inspecting

the critical

welds of the lifting rig prior to lift.

gA Audits 84-15

and 85-11 identified this concern.

gA Audit 85-11 did not

identify this as

a recurring problem.

Line and

gC personnel

signed off procedure

steps without adequate verification

that the required actions

were complete.

b.

Mechanical Activities

(Paragraph

4)

1.

Safety related stainless

steel

rope for auxiliary building

crane did not have documented traceability for chemical

analysis

and breaking strength.

(Example of a violation)

2.

Calibration services for direct readout

gauges for the hy-

draulic torque wrenches

were procured

from a supplier

who

was not evaluated

by Ginna Station,

General

Maintenance,

guality Assurance

and Electric Meter and Laboratory,

as

required

by the licensee's

gA program.

(Example of a vio-

lation)

Electrical Activities

(Paragraph

5)

1.

Circuit Schedules

(safety related drawings)

were improperly

independently

reviewed

by the originator (Violation).

2.

An out-of-calibration device

was

used to megger test the

'ircuit breakers for component cooling system 'B'ump.

Neither the workers nor the

gC inspector verified the

calibration of the meggering device (Violation).

3.

The battery surveillance

procedure did not provide accept-

ance criteria for level

and temperature

checks.

As

a result,

corrections

to electrolyte specific gravity were not made

(Unresolved Item).

C(

C I

1.

Procedure

steps

for radwaste

shipment 85-84 were signed off

by a health physicist

and not by the worker who conducted

the actual

work.

2.

QC signed off the hold point without verifying the accept-

ance

and accuracy of the instrument readings

obtained

from

the steps

QC witnessed.

2.5

Status of the Licensee's

Initiatives to Im lement

A/

C Task Force

Recommendation

1.

The management initiatives to improve quality of safety related

activities

had been recently developed

from the recommendations

of the

QA/QC Task Force.

2.

As of January

27,

1986,

the following actions

were taken

by the

licensee

Goals

and actions

are developed for the Executive Vice

President

(EVP), Vice President

(VP) and Chief Engineer.

The goals

and Action Plans

are being developed for the mid

management

levels (i.e.,

QA Manager,

Superintendent

etc.).

Reorganization

to relieve the Chief Engineer

from immediate

responsibility for dispositioning corrective action requests

generated

by the

QA manager

who reports directly to the

Chief Engineer.

Better

involvement, control

and overview of QA activities

by

EVP as indicated

by the

EYP's review of recent

QA acti-

vities and audit findings.

Appointment of a

new Nuclear Assurance

Manager to enhance

the effectiveness

and credibility of site

QC.

Hiring of experienced

Contract

QC personnel

to site

QC

staff.

Initiation of back-to-the-basics

training program at working

level to enhance

Quality and safety

awareness

(two sessions

conducted to date).

Implementation of the task force recommendation

to categor-

ize

QA findings in accordance

with the severity level

and

use

these findings for management

decision

making and control.

~i/

2.6.

Conclusions

1.

Enhancement

of

quality and safety

awareness

at the Ginna

Station working level is

a slow process.

2.

The licensee

uses

informal means to arrange

non-destructive

examination of critical welds

on lifting rigs for the reactor

vessel

head

and internals

and to provide technical

information

to the maintenance

mechanics.

3.

The licensee's

data

base

supporting

the Vendor Manual

System

is not controlled in accordance

with licensee's

QA Program

requirements.

4.

The activities for the upcoming outage

appeared

to be unaffected

by the task force recommendations.

3.

0 erations

and Instrumentation

8 Control Activities

The effectiveness

of the licensee's

activities in Operation

and Instrumen-

tation 5 Control Areas

was assessed

by reviewing selected

QA audits, refuel-

ing outage activities

and survei llances tests,

as detailed

below:

3. 1

Audits

In order to determine

the adequacy

and effectiveness

of the license

audits,

two selected

1985

QA audits

were reviewed.

These audits in-

volved Maintenance,

Surveillance,

and Operational activities.

The

purposes

of this review were to:

1) ascertain

the nature

and extent

of the licensee's

auditing effort, 2) determine

the manner

in which

the audit findings were dispositioned,

3) identify to what extent the

corrective actions associated

with the audit findings were tracked

for completion,

and 4) determine

whether identified discrepancies

were repetitive

and

how the licensee

had addressed

this aspect of the

audit.

The details of this review are given below:

Audit 85-07:CA, Ginna Station Maintenance Activities, was performed

during the period of February

12-22,

1985.

All audit findings were

satisfactorily

di spositioned

by the licensee

and the Audit was closed

on July 19,

1985.

There were

no

NRC identified deficiencies

as

a

result of reviewing this audit.

Audit 85-11:JB,

Ginna Station Refueling Activities, was performed dur-

ing the period of March

11 through April 9,

1985.

The

QA manager

was

one of the auditors.

At the time of NRC review, thi s audit was still

open.

There

was only one audit finding.

The Audit Finding Corrective

Action Report

(AFCAR), Finding No.

1, stated that the Reactor

Vessel

Head Lifting Device

(RVHLD) and the Reactor

Vessel

Internals Lifting

Device (RVILD) had not received

an annual

visual inspection of welds

as required

by licensee

Procedure

MHE-1100-1, Inspection

and Mainten-

ance of Special Lifting Devices.

This was identified during

an audit

of activities involving "control of heavy loads".

lj

,O'I

I

'h

,IU <

l

'I

AFCAR Finding No.

1, to Audit 85-11:JB stated:

1) The Material

Hand-

ling Equipment

(MHE) Group's procedure

referenced

above required

two

types of inspections

to be performed at specific intervals for the

RVHLD and

RVILD; 2) The

NOE was completed in 1983, but annual

visual

inspections

of specified welds

on these

two devices

were not performed

as required (only partial inspections

were done

due to inaccessibility

of the welds caused

by 1'ead shielding

and constructions);

3) The

RVILD

was not inspected at all in 1985;

and 4) Since the requirement

went

into effect in 1983,

the

RVHLD and

RYILO have never received

a com-

plete visual inspection of the welds

as required (this is based

upon

a review of completed records).

The audit's

"Recommended

Actions" for disposition of this finding

stated

..."An equitable

understanding

of the requirement for inspec-

tion, together with the scheduling

and maintenance

problems involved,

should

be reached

by the various personnel

concerned.

This under-

standing

should then result in complete

and comprehensive

compliance

with the inspection required."

The audit was transmitted to the

Superintendent,

Ginna Station

and Superintendent,

General

Maintenance

on April 22,

1985 following approval of the audit report by the

Manager,

gA.

On May 3,

1985,

a corrective

action response

to the above

recommenda-

tion was received

by gA.

This response

was prepared

by the cognizant

MHE Foreman

involved in the

1985 inspection

and approved

by the Super-

intendent,

General

Maintenance.

It stated

..."These

inspections

were

not done

as

scheduled

due to

a misunderstanding

of inspection require-

ment's.

Materials Engineering

personnel

have

met with responsible

structural

engineering

personnel

and

have concluded that all inspec-

tion requirements

can

be met with present

equipment configuration.

Therefore,

at the next refueling outage,

these

inspections will be

done."

The stated target completion date for the corrective action

was February

26,

1986.

Based

upon the importance of the

AFCAR finding, and the fact that the

established

target completion date for the corrective actions

was

after the

commencement

of the next Refueling Outage that was scheduled

to begin

on February 8,

1986,

a detailed inspection

was conducted

by

the

NRC to review the licensee's

plans

and schedules

for performing

the required inspections.

The inspector

reviewed all applicable

licensee

procedures

related to the inspections

and the stipulated

sequence

of activities;

and all scheduling related

documents

to ensure

that the inspections

were identified for performance.

Cognizant

licensee

scheduling

and inspection

personnel

were interviewed to

ascertain

that these

personnel

were aware of all stipulated require-

ments

and that the corrective action

was adequate

to preclude recur-

rence.

The following items were identified:

1

0

There were

no formal scheduling

mechanisms

identified by the

Re-

fueling Outage

Planning

Group and the

MHE Group that specifically

identified the performance

of the visual weld inspection or the

required

sequence

of the inspection activity as stipulated in the

applicable

licensee

procedures.

Informally, the

MHE Foreman

had arranged for Nondestructive

Exa-

mination

(NDE) personnel

to perform the weld inspections

on the

RVHLD as

soon

as the containment

was

open for personnel

access

and prior to assembly of the

RVHLD.

Since the disposition for AFCAR, Finding No.

1, for Audit 85-11:JB

was assigned

to the licensee's

General

Maintenance

Organization

the station's

Corrective Action Tracking System did not identify

this item and track it on the Task Assignment

System.

A status

file is maintained

in the office of the Manager,

Nuclear Assur-

ance for each audit report finding that results

in a Task Assign-

ment at the station.

This file and the computerized

tracking

data

base

showed

no information on the above

AFCAR item.

Speci-

fic licensee

action is required to provide adequate

tracking of

corrective actions

assigned

to organizations

outside

Ginna

Station.

The licensee's

action to resolve this issue will be

followed in a future inspection

(50-244/86-02-01).

A licensee

procedure

RF-9. 10,

Head Lifting Rig Operating Instruc-

tion,

Rev.

5 dated July 2,

1984, requires

a visual inspection

by

MHE personnel.

However, this procedure

step is not required

to be signed off.

No corrective action was specified for proce-

dure RF-9. 10 in the response

to AFCAR Finding No.

1,

as this

procedure

would not be used during this refueling outage.

A

contractor-developed

procedure will be used in place of RF-9. 10.

Licensee action is required to assure

that the contractor proce-

dures

adequately

address

the requirements

of all licensee

proce-

dures

applicable to the contacted activity.

This action will

be reviewed in a future

NRC inspection

(50-244/86-02-02).

This concern

was discussed

with cognizant

QA and

QC personnel.

The

QA

Manager stated that the failure to perform the required inspections

of

special lifting devices

was identified in

a

1984

QA audit report.

A

detailed

review was then conducted

by the

NRC of all applicable licen-

sing commitments,

procedures,

and inspection

records that per tain to

the conduct of weld inspections

on the

RVHLD and

RVILD from 1983

through

1985,

as discussed

in Attachment

1 to this report.

10

3.2. 1.

Summar

Ins ection Findin

s Relatin

to Ins ection of the

RVHLD

and

RVILD

The following deficiencies

were identified by the

NRC:

The licensee

was not effective in implementing the commit-

ment in their letter of March 2,

1983 to an annual

inspec-

tion program for special lifting devices.

The weld inspection

requirements

of procedure

MHE-1100-1,

Rev.

0 were not adhered

to by the licensee

during the

1983

and

1984

RVHLD and

RVILD weld inspections.

The

RVHLD weld inspection

requirements

of procedure

MHE-

1100-1,

Rev.

1 were only partially completed

by the licen-

see during the

1985 refueling outage.

Additionally, the

licensee's

activities during this refueling were contrary

to the requi rements of procedure

A-1011, Revision 7.

During the

1983,

1984,

and

1985 refueling outages,

the

gC

hold point in procedures

RF-58,

RF-59,

and RF-60, respec-

tively, to verify the structural integrity checks of RVILO

were complete,

were signed off as complete

when

such checks

were not accomplished

due to

a misunderstanding

of the

requirements

by gC personnel

During the

1985 refueling outage

procedure

RF-60 contained

a requirement that all applicable

steps of procedure

MHE-

1100-1

have

been satisfactorily completed for the

RVHLD and

RVILD.

This requirement

was signed off as accomplished

when in fact it was not fully performed

as required.

The corrective action for a

1984

gA Audit Report was inef-

fective to preclude repetition of a failure to perform in-

spections

of welds

on the

RVHLD and

RVILD as specified in

the licensee's

written commitments to the

NRC and establish-

ed procedural

requirements.

The

1985

gA Audit Report

and

corrective actions did not assure

that the conditions that

lead to this issue

would be corrected

by the licensee.

3.2.2.

Items

1 through

6 constitute

a violation (50-244/86-02-03)

Immediate Actions Taken

b

the Licensee

The following immediate actions

were taken

by the licensee prior

to lifting of the reactor

vessel

head

and internals during the

refueling outage

commenced

on February 8,

1986.

Cl

11

1.

Revise the refueling procedure

and the material

handling

procedure

NHE-1100-1 to require

QC hold point for the

visual inspection of critical welds

on the reactor

vessel

head

and internals lifting rigs.

2.

Train material

handling

and

QC personnel

in their responsi-

bilities for the inspection of critical welds

on the reactor

vessel

head

and internal lifting rigs and the effective dis-

position of identified nonconformances

and audit findings.

3.

Emphasize

the importance of completing all actions prior to

signing off a procedure

step

and the role of QC in verifying

these

actions

by senior licensee

management

to all personnel

involved in the upcoming outage.

Subsequent

to this inspection period,

on February

10,

1986,

the

NRC Senior Resident

Inspector verified that the licensee

had

completed

the above actions.

3.3

Surveillance Activities

The

NRC reviewed selected

Instrumentation

8 Control (IEC) and Opera-

tions related surveillance activities to ascer tain whether these acti-

vities were performed in accordance

with the requirements

of Technical

Specifications

(TS) and implementing procedures

as detailed below:

A review of the current surveillance test

schedule

was conducted.

This document is generated

by the Results'nd

Test

(RET) Supervisor,

who is also responsible

for review and evaluation of the timeliness

and accuracy of completed tests.

Based

upon review of this document,

which captured

the status

of both scheduled

and completed testing,

and discussions. with the

R&T Supervisor, it was concluded that effec-

tive management

controls were in-place to ensure

the timely perform-

ance of required surveillance testing.

The

TS Section 4.0 Surveillance

requirement,

states

that surveillance

intervals

may be adjusted

plus or minus

25%.

Licensee

Procedure

A-1101,

Rev. 8, Performance

of Tests,

Paragraph

3. 1.8.3. 1 states

that

a maximum allowable extension

not to exceed

25% of the surveillance

interval is permissible.

No mention of the

TS restriction of a minus

25% interval adjustment is made in this procedure.

However, both the

plus and minus

25% interval adjustment restrictions

are contained

in

the following procedures

-1) A-1105,

Rev.

19, Calibration and/or Test

Surveillance

Program for instrumentation/Equipment

or Safety Related

Components,

and 2) A-1106,

Rev.

6, Ginna Station Surveillance

Schedule.

Additionally, it was noted that the A-1101 procedure

contains

a licen-

see administrative limit wnich states

that the combined interval for

3 consecutive

surveillances

should not exceed

3.25 single surveillance

intervals.

This condition is not stated

in either procedure

A-1105

or A-1106.

V

1

4

12

Because

the licensee's

procedures

for performance

intervals are not

consistent either

among themselves

or with the

TS, the inspector re-

viewed the implementation of minus

25% interval adjustment limita-

tions with the licensee.

The

R&T Supervisor indicated that

he did

not consider

the

TS specified limitation as applicable

when it became

necessary

to adjust the surveillance

schedule

due to equipment avail-

ability constraints

during plant operations.

The

NRC was not aware

of any specific instances

in which the licensee

did not meet the

minus

25% TS limit on required survei llances.

The licensee

representatives

acknowledged

the above

and stated that

the appropriateness

of a

TS change

request

to address

this concern

will be reviewed.

The only other item in this area requiring licen-

see attention is an apparent

need to provide consistent

instructions

for surveillance testing interval constraints

in procedures

A-1101,

A-1105 and A-1106.

The inspector

reviewed the licensee's

implementation of TS Section

3. 10.2.6 requirement

to verify hot channel

factors against

the limits

provided in Specification

3. 10.2.2 every full power month.

This rou-

tine surveillance

is identified in the Limiting Conditions of Opera-

tions

(LCO) section of the

TS.

NRC review identified no other sur-

veillancee

tests

in the

LCO section of the

TS.

This routine survei 1-

lance is controlled in part,

by procedure

S-15. 1,

Rev.

27,

Flux Map-

ping Normal Procedure.

It was noted that the current Surveillance

Schedule

incorporated

the performance

of the flux mapping per proce-

dure S-15. 1.

However,

procedure

A-1104,

Rev.

10, Ginna Station Tech-

nical Specification Surveillance

Program,

which is used

by the licen-

see to define, categorize,

and list the procedures

that encompass

the

program,

did not include the S-15. 1 in the program.

The

R&T Super-

visor,

when questioned

by the

NRC on this condition, indicated that

this was

an apparent

oversight

and would provide

a procedure

update

to resolve this item.

Other than the minor deficiency identified

above,

the

NRC had

no further questions

or comments

on the licensee's

activity associated

with flux mapping.

A review was conducted of the licensee's

performance of TS Section

4,

Table 4. 1-1, required monthly functional testing of the

Power

Range

Nuclear

Instrumentation

System

Channels

41-44 (PT-6.3. 1 through

PT-6.3.4).

The required monthly functional tests

were conducted

as

scheduled.

The inspector

had

no further questions.

3.4

ualit

Assurance

and

ualit

Control Activities in Surveillance

Area

The

NRC witnessed

the conduct of procedures

PT-6.3. 1 through PT-6.3.4

during back shift and noted that there

was

no

gC involvement

or over-

view of these

routine surveillance

testing activities. It was noted

that these

procedures

did not contain

an "Initial Condition" to con-

tact the

gC Group prior to start of the activity as is the case

in

13

most surveillance

procedures.

As

a result of discussions

with Opera-

tions Department representatives,

the

NRC learned that the

QC Group

does

not witness routine surveillance activities conducted

on the

backshift.

This apparent

lack of

QC coverage

merits further review

by the licensee

management.

4.

Mechanical Activities

In order to assess

the the effectiveness

of the

QA and

QC activities in

Mechanical

area,

the inspectors

reviewed selected

Safety-Related

Procure-

ment,

Survei llances

and Maintenance activities.

The details of this

review are given below:

Procurement

Material Control

and Identification

The licensee's

procurement,

material control

and identification activ-

ities were reviewed to verify that the requirements

of 10 CFR 50, Ap-

pendix

B, Criteria IV, VII, VIII and XII, were adequately

implemented.

The licensee

commitment to these

requi rements i s in Technical

Supple-

ment IV to the operating license.

Technical

Supplement

IV requires:

"Evidence of review and approval of procurement

documents is recorded

on the documents

or on the attached

control form.

The attached

con-

trol form identifies to Purchasing

a procurement

method which will

ensure

that the selected

supplier is capable of providing the item or

service

in accordance

with the requirements

of the procurement

docu-

ments."

"Other off-the-shelf items, that are manufactured

to industry stand-

ards, that are typically utilized in applications other than nuclear,

and for which item acceptance

is based exclusively

on receipt inspec-

tion may be purchased

from sources

other than the approved

suppliers

list.

These other sources

may include the manufacturer

of the re-

placement part, authorized distributor for the manufacturer's

replace-

ment parts

and distributor of catalog

items which satisfy the'guide-

lines of not requiring status

on the approved suppliers list."

"Ginna Station,

General

Maintenance,

Quality Assurance

and Electric

Meter and Laboratory evaluate

the suppliers of inspection, test,

and

calibration services

which they intend to use."

To verify conformance

to the above,

the inspector

reviewed the receiv-

ing operations,

warehouse,

and purchasing activities.

All material arriving by truck is unloaded

and sorted in a small area

of the receiving building.

Here it is sorted

by reference

to the

purchase

order.

Safety-related

material is tagged with a white "Hold

for

QA Inspection" tag

and placed in the

QC inspection

room.

Items

too large for this

room o. that ar rive when the receiving area is

L

1

if

)4k

1f

lt

14

overcrowded

are sent directly to the warehouse

and receiving inspec-

tion is performed there.

It was observed that in the

gC inspection

area all items were tagged.

However,

due to the lack of space,

items

awaiting inspection,

accepted,

and

on hold were not segregated.

The

inspector did not identify any concerns

resulting

from this lack of

adequate

segregation.

4. 1. 1.

Stainless

Wire

Ro

e for Auxiliar

Bui ldin

Crane

(Purchase

Order

Nos:

10205-B-JO

and

NEG 50942)

In reviewing documentation

of recently received material, it was

noted that two coils of stainless

steel wire rope

had been re-

ceived but were not present

in the receiving area.

In reviewing

the documentation

received with the wire rope,

the following was

noted:

1.

Neither the supplier

nor the manufacturer

was

on the qualif-

ied suppliers list.

3.

The certificate

from the manufacturer

stating the product

was

undamaged

referenced

an incorrect, purchase

order number.

The manufacturer's

Test Certificates

(T-10196 dated 5/21/85)

for Chemical Analysis and Breaking Strength

referenced

the

supplier's

purchase

order to the manufacturer.

They did

not have traceability to the product (Heat,

Lot or Serial

Numbers)

or to the licensee's

purchase

order.

Observation of this wire rope in the warehouse

showed that the

only identification was

a reference

to the licensee

purchase

order

on the address

label.

The material

was not identified

with any tags

when observed

by the

NRC inspector.

A "Hold" tag

was attached

during the inspection.

Processing

of the purchase

order

was in accordance

with the

requirements

except that the control

form was not attached

to

any copy of the purchase

order.

It was available,

however.

To determine if the wire rope presently

in use

on the crane

had

been

processed

in accordance

with the requirements,

the inspector

reviewed the documentation

associated

with that purchase

order

(NEG 50942).

Neither the material

supplier

nor the manufacturer

was listed

on the gualified Suppliers List. It should

be noted

that the material

supplier

was not the

same

on P.O.

NEG 50942

as

on P.O.

NG 10205-B-JD but the manufacturer

was.

The following deficiencies

were noted:

1.

There

was

no evidence of purchase

order review and approval

as required

by the Technical

Supplement

IY to the operating

license.

~.

'4

0

2.

No certification was received stating the product was un-

damaged,

as required

by the purchase

order.

3.

The Manufacturer's

Test Certificates

(T-10196 dated 5/21/85,

the

same

number

as received with P.O.

No.

10205-B-JD) for

chemical

analysis

and breakin'g strength

referenced

the sup-

plier's purchase

order number to the manufacturer.

They did

not have traceabi lity to the product (Heat,

Lot or Serial

Number) or to the licensee's

purchase

order.

4.

There

was

no statement that the oil free requirement of the

purchase

order had

been

inspected

at receiving.

4. 1.2.

Calibration Data for Tor ue Wrench

Gau

es (Purchase

Order

NEG 49841)

There

was

no evidence that the vendor

had been evaluated for the

calibration services

provided,

as required

by Technical

Supple-

ment IV to the operating license.

Purchasing

had

no record of

a gA review of this purchase

order prior to placing

and the

vendor was not on the gualified Suppliers List.

The deficiencies identified in the paragraphs

above constitute

a vio-

lation (50-244/86-02-04).

Additionally, these deficiencies

indicate

a weakness

in the licensee's

overall procurement,

receipt

and storage

programs.

The warehouse

is used for storage,

issue of relatively large

par ts

and for stock of items not immediately

needed for issue

from other

issue stations.

Safety-related

equipment is clearly identified with

"Accept" or "Hold" tags.

Only two snubbers

were not segregated

but

were clearly identified.

No attendant

is stationed

in the area.

Access is limited to the receiving

and storeroom

personnel.

This

area

meets

the requirements

of ANSI N45

~ 2.2 for Level

B storage.

4.2

Surveillance

and Maintenance Activities

The inspector

witnessed

part of the final maintenance

check of the

"D" service water

pump.

This operation

was being performed in accord-

ance with Procedure

M11. 10, Revision

14, Major Inspection of Service

Water

Pump.

(}uality Control inspectors

were performing surveillance

inspection during this operation.

Inspector

observations

were as

follows:

1.

The procedure (Mll.10, Revision

14) was available

and being

followed.

2.

Signatures

for opera-ions

were

up to date through the operation

being performed.

16

The

pump repair data

package

was available.

Procedure

M11.10. Revision

14, indicated that the "D" pump

had

been

removed,

repaired

and replaced.

However,

review of the

maintenance

data

package

showed it was the

pump previously

removed

from the "C" loop and repaired that had

been

placed in the "D"

loop.

This was verified by comparing the

pump serial

number

on

the repair data with the

pump installed in "D" loop.

This p'rac-

tice increases

the availability of this safety-related

system

and in case of pump failure, provides

a backup that can

be quickly

installed.

The "Dimension Data Sheet" in the data

package

was reviewed.

This data

sheet listed the impeller, casing ring and bearing

diameters

and clearances.

The following deficiencies

in the

data

sheet

were noted:

There

was

no traceabi lity to the product

measured;

the individual performing the measurements

was not

identified;

and the measuring

devices

used

were not identified.

However,

on the "Fabrication

Route Card" used

by the Maintenance

Repair

Shop contained

the information above for the impeller

and casing.

In his handwritten instructions to the Maintenance

Repair Shop,

the cognizant Maintenance

Engineer specified

a clearance

of

0.012"-0.0)5"

between

the impeller and casing.

The

NRC inspec-

tor interpreted this as meaning 0.012"-0.015"

on each

side (a

difference in diameters

of 0.024"-0.030").

The engineer

and

Maintenance staff both interpreted this as

a difference in dia-

meter of 0.012-0.015 resulting in a clearance

of 0.006 per side.

Reference

to the manufacturer's

drawing confirmed that

a differ-

ence in diameter of 0.012-0.015

was correct.

This informal ap-

proach to specifying dimensions

and tolerances

indicated

a poten-

tial weakness

in the

system

used to provide technical

data to

the individuals performing operations.

The lack of formality in specifying dimensions

and tolerances

and

adequate

documentation

in mechanical

surveillance

and maintenance

records is an unresolved

item (50-244/86-02-04).

4.3

Vendor Manual Control

In paragraph

2.2.2 of the Letter to Director of Nuclear Reactor

Regu-

lation from Vice President,

Rochester

Gas

and Electric Corporation

dated

November 4,

1983 (Subject:

Generic Letter 83-28,

R.

E. Ginna

Nuclear

Power Plant,

Docket

No. 50-244) it states:

f

l,

L~

17

"Within the administrative

computer,

a vendor manual's

data

base exists which contains all of the plant's

vendor

information that is located at the station.

This data

base

will be refined to remove duplicate

and outdated

manuals.

A complete

program of vendor interface will be established

following receipt of the

INPO NUTAC report

on this issue."

When the inspector

asked to see

information from the computer data.

base,

he was informed that it was not being used,

had not been refin-

ed to remove duplicate

and outdated

manuals,

and it did contain irre-

levant information such

as standard

parts catalogs,

drawings

and pro-

cedures.

Additionally, this data

base is not controlled in accordance

with the licensee's

own

QA program requirements.

From the above, it

is apparent

that this data

base is not established

and maintained

in

accordance

with the above

licensee letter.

The licensee

stated that

a consultant

has

been hired to establish

formal vendor manual control.

This consultant is to start work February

3,

1986 with completion

scheduled for the

end of June

1986.

The licensee's

vendor manual

control

remains

unresolved

pending licen-

see action to establish

and maintain

a reliable vendor manual

data

base

~

(50-244/86-02-06)

A previous unresolved

item (50-244/85-04-02)

to incorporate

vendor owner's

group recommendations

into plant

procedures

remains

open.

The observations

in receipt,

surveillance,

and vendor manual control

.

indicate that the licensee's

efforts to enhance

the effectiveness

of

Quality Assurance

and Quality Control activities did not reach day-

to-day activities in the mechanical

area.

5.0

Electrical Activities

Selected

surveillances,

maintenance activities

and modifications were re-

viewed to assess

the effectiveness

of the licensee's

QA and

QC activities

in the electrical

area.

The details of thi s review are given below:

5. 1

Electrical

Survei llances

The safety-related

"A" and "B" battery

systems

were selected

to deter-

mine if the licensee'

electrical

surveillance

program

was in accord-

ance with NRC requirement,

Technical Specifications

and license

com-

mitments.

The batteries

were originally placed in service

17 years

ago.

The

"A" battery was replaced

during the refueling outage of March 1985.

The "B" battery will be replaced

during the upcoming refueling outage

starting

February 8,

1986.

~

'

\\

6g

18

The following documents

were reviewed

or

used

as

a basis for this

inspection:

Final Draft FSAR, dated October

1984,

Section 8.3.2 Direct Current

Power

Systems,

Safety Evaluation Report,

dated October

1983,

NUREG-0944,

section

8.4 Station Battery Capacity Test Requirement,

section 8.5 D.C.

Power System

Bus Voltage Monitoring and Annunciation

Technical Specification,

Appendix

A

to Operating

License

No.

DPR-18,

dated

December

10, 1984,section

3.7 Auxiliary Electrical

Systems,

section 4.6 Emergency

Power System Periodic Tests 4.6.2

Station Batteries

Regulatory

Guide

1. 129,

Rev. 1, Maintenance,

Testing

and Replace-

ment of Large

Lead Storage Batteries for Nuclear

Power Plants

which endorses

IEEE STD 450-1975 with certain exceptions.

IEEE STD 450-1980

Station Battery Vendor Technical

Manual

IE Information Notice 84-83,

Various Battery Problems,

dated

November

14,

1984

IE Information Notice 85-74, Station Battery Problems

dated

August 29,

1985

Monthly and quarterly Survei llances

per

Procedure

PT-11 before

and after to Battery "A" replacement

Surveillance

Procedure,

PT-10.3, Station Battery "A" Load Tests

before

and after Battery "A" replacement,.

The inspector's

review of PT-10.3 load test for battery "A", prior to

replacement,

noted that terminal voltage

was 106.5 volts after 60

minutes.

This is 1.5 volts higher

than the minimum acceptance

value of

105 volts.

The licensee

noted under the

comment section of the pro-

cedure

"Readings indicate that this schedule

of change

out is con-

sistent with proper

operating practice."

This is an indication of

the licensee's

use of good operating practices.

The licensee

is revising the test procedure

to provide

a

2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> service

test instead of a

8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> service test at each refueling outage.

Also

a capacity test will be conducted

every five years.

These tests

are

in accordance

with the latest revision of IEEE standard

450.

This

is another indication of the licensee's

use of good industry practices

and latest technical

information.

~,

I

+1

19

The inspector's

review of the surveillance

procedures

PT-11 listed

above indicated that the licensee

was correcting the specific gravity

readings for neither temperature

deviations

from 77 degrees

F nor

level deviations

from the full electrolyte level.

Correction for

both temperature

and level are specified in the vendors instruction

manual for the

new

batteries.

The level correction

was not addressed

in the old battery vendor instruction manual.

The inspector discussed

this concern with the licensee's

representatives

and the licensee'

representatives

acknowledged

the inspector's

concern.

The load test PT-10.3 requires

the

gC be notified before the test is

conducted.

There are

no gC hold points or signoff within the procedure

to verify if gC personnel

was present during the test.

However, the

data of PT-11 is reviewed

by the Results

and Test Department.

The

test is reviewed by both the Electrical

Foreman

and the Results

and

Test Supervisor.

IEEE Standard

450 specifies

surveillance of battery cell connection

resistance

as

an industry-accepted

good practice for establishing

operability of station batteries.

However, this surveillance is not

included to the Licensee's

program.

The concerns of electrolyte temperature

and level corrections of the

specific gravity and surveillance for battery cell connection resis-

tance together constitute

an unresolved

item (50-244/86-02-07).

5.2

Electrical Maintenance

The inspector witnessed

the maintenance

of the "B" component cooling

pump,

480 volt, breaker to determine if the licensee's

electrical

main-

,tenance

program

was in accordance

with the

NRC requirements,

Technical

Specification

and license

commitments.

The following documents

were reviewed or used

as

a basis for this

inspection:

Final Draft FSAR, Section 8.3. 1. 1.3 The 480-Volt System

Technical Specification, Section 3.7 Auxiliary Electrical

Systems

Electrical Preventive

Maintenance

Program

Procedure

No A-1005,

Revision 0, Effective February

27,

1984 for 1984

Electrical Preventive

Maintenance

Program

Procedure

No. A-005,

Revision

1, Effective date January

11,

1985 for 1985

4

~

'~t

20

DB-25, DB-50,

and

DB-75 Circuit Breaker Maintenance

and Overcur-

rent Trip Device Test and/or Replacement,

Procedure

No. M-32. 1,

Revision 20, Effective date

February

5,

1985 for Standby Auxili-

ary Feed

Pump (dated

March 2,

1985)

and Charging

Pump

1A (dated

March 6,1985).

Nuclear

Power Experience

PWR Electrical

Systems

Ginna

1972 thru

1985

NRC Resident

Inspector Morning Reports

1978 thru 1985

Licensee

Event Reports

1978 thru 1985

There were only 19 electrical failures that required corrective main-

tenance,

including

2 loss of offsite power events,

during

a

13 year

period.

This low need for corrective maintenance

after failure in-

dicated that the licensee's

preventive

maintenance

program was effective.

The

1984 and

1985 electrical

preventive

programs

indicated that the

required maintenance

activities were conducted

as scheduled.

The inspector

observed

during the maintenance

of the "B" component

cooling

pump breaker that both the electrician

and the

gC personnel

failed to verify that the calibration period for the megger which was

used to determine

insulation resistance

of the breaker,

expired

on

April 27,

1984.

The procedure

did not require the measured

value to

be recorded.

It also did not specify the acceptance

criteria for the

resistance

measured.

The licensee

records

indicated that the

above

megger,

Biddle Cat.

No.

21805-1,

has

been missing since

1985.

However, this megger

was avai 1-

able for use

in. the auxiliary building.

This megger

was subsequently

removed

from the auxiliary building for recalibration.

A check of the

megger

was

made against

a standard

resistance,

Biddle Cat.

No. 72-6340.

The megger reading

between

1 and

10 megohms

read

15% lower.

This er-

ror is in the conservative direction.

The licensee

procedure for ca-

libration control

exempts

meggers

from calibration.

However, the in-

spector

noted that certain

meggers

were calibrated periodically.

This

indicates

an inconsistency

in the licensee's

calibration practices.

The omission of the minimum acceptable

resistance

value in procedure

M-32. 1 and the

use of test equipment that was not calibrated

since

1983 collectively constitute

a violation (50-244/86-02-08)

against

the acceptance

criteria requirements

of 10 CFR 50, Appendix B, Crite-

rion V. It should

be noted that the licensee's

overall calibration

and control

program for measuring

and test equipment

was identified

as

a licensee

weakness

in

NRC operational

assessment

team inspection

50-244/85-04.

'X,f e

~ ~s

~6

J

Rw

e

21

Upon identification of this calibration concern

by the

NRC, the per-

sonnel

repeated

the resistance

measurements

using

a meggering unit

whose calibration

was current.

The results

were acceptable.

5.3

Electrical Nodifications

Selected electrical modification activities were reviewed to ascertain

that these activities were in conformance with the requirements

of the

Technical Specifications

and

10 CFR 50.59.

The electrical modifica-

tions that the licensee

planned for this refueling outage were:

Replace

the "B" safety related battery

and install

a

new 200

ampere

charger

Remove the

115KV lines control

benchboard

from the control

room

and install the Safety Parameter

Display System

Install

new control

panel

for the "A" emergency diesel

generator

in the diesel

generator

room.

Switches

on the panel will provide

electrical isolation

and control during certain fire conditions.

The design

package for the "A diesel

generator

emergency control panel,

EWR 4136,

was reviewed.

The general

design criteria, safety evalua-

tion and drawing were found acceptable.

The inspector

observed

the work associated

with the Replacement

of

115KV Benchboard

Sections,

EWR 4067.

This work

was done by a con-

tractor.

The calibration for termination tools were current.

The

inspector

noted that the wire termination

sheets

(Circuit Schedule)

which were part of the design

change

package

had the

same signature

for both the preparer

and the reviewer.

This is contrary to the

requirements

of procedure

No.

QE303,

Revision 8,

November

12,

1985

"Preparation,

Review and Approval of Engineering

Drawings" for inde-

pendent verification of safety related

design

and construction

draw-

ings

and this is

a violation (50-244/86-02-09).

5.4

A/

C Involvement in Electrical Area

The inspector

observed that

QC personnel

were verifying wiring changes

that were being

made in the control

room,

as part of Engineering

Work Request 4067 for the

115KV benchboard

replacement.

The work activity

and

QC inspection

were being

done

by contract personnel.

Discussions

with the

QC personnel

indicated that they had adequate

work experi-

ence, training and understanding

of job function.

The inspector

also

noted that other contract

QC personnel

were witnessing cable pulling

activities in the relay

room and concluded that the

QC coverage

was

evident.

e

22

As stated previously,

the contract

QC inspector

assigned

to breaker

maintenance

did not observe

the

use of an uncalibrated

megger.

This

QC inspector

had previous work experience

in the electrical control

area

and the experience

was adequate

for the

QC inspection function.

However,

the

QC inspector did not use

separate

lists of inspection

attributes

to provide

an independent

auditable

QC record of the main-

tenance activity.

The licensee

QC personnel

received instructions

in

fundamentals

of electrical

engineering.

However, the application of

this theoretical

instruction to routine

QC activities was still being

formulated.

The inspector

reviewed the latest

QC surveillance report for the im-

plementation of procedure,

A 1201,

Instrument,

Control

and Electrical

Maintenance

and Test Equipment

(MME) scheduled recall for calibration.

This audit indicated that the MME was being calibrated

as

shown

on

the schedule.

This was further verified by the inspector

as discussed

in Section

7.0 during the closure of the inspector followup item

50-244/85-04-05.

The findings in paragraphs

5. 1, 5.2 and 5.3 above indicate that the

licensee's

efforts to enhance

the effectiveness

of QA and

QC activi-

ties

have not reached

the day-to-day activities in electrical

area.

6.0

Health

Ph sics

and Chemistr

Activities

To assure

the effectiveness

of Quality Assurance

and Quality Control acti-

vities in Health Physics

and Chemistry areas,

the inspector

reviewed the

following activities:

1.

Routine Health Physics

Surveys

and monitoring

2.

Low level radwaste

shipment

3.

Primary Chemistry analyses

The procedures

and records

reviewed included:

Logs of chemistry

and health physics activities

Procedure

No. PC-1.3,

Revision

16, Daily Chemistry Analysis

Results

Procedure

No.

PC-25. 1. 1, Revision 3, Operation of Post Accident

Sampling

System

under

normal conditions

HP-7.31,

Revision 4. Daily Instrument

Source

Checks

I

~

a '

23

RD-10.4. 1,

US Ecology Radioactive

Shipment

Record

RD-10.6, Revision

16, Shipping of Low Level Radioactive

Waste

RD 10.8,

10 CFR 61,

Compliance

The details of the review are given below:

Routine Health

Ph sics

and Chemistr

Activities

The inspector

reviewed the daily logs of Health Physics

and Chemistry

activities to determine

the problem identification and solution in

these

areas.

The problems identified in each shift were adequately

discussed

and recurring problems were highlighted.

Problems identi-

fied during health physics

surveys

were promptly reported

and forward-

ed for action to the appropriate

organizations

through the initiation

of trouble report.

For example,

on September

9,

1985,

the Health

Physics

survey around the boric acid filters indicated

above

normal

readings.

A trouble report (85-2647)

was issued

on September ll,

1985 and the filters were replaced

on September

18,

1985.

The inspector

noted that the daily Chemistry analyses

were conducted

in accordance

with procedure

PC-1.3

and reported in the daily morning

meeting

by Hanager,

Health Physics

and Chemistry.

The personnel

per-

forming Health Physics

and Chemistry were knowledgeable

in the tech-

nical

and procedural

requirements.

The results

were trended to iden-

tify anomalies.

When anomalies

were detected,

efforts were initiated

to investigate

and correct the conditions that led to the anomaly.

The inspector

noted that

a technician

made

a data entry correction in

the isotopic analysis of the reactor coolant by crossing

out the

wrong entry, entering

the correct entry and initialing in accordance

with the procedure

requirement for such error correction.

Technicians

are solely responsible

for the accuracy of the data taken.

Supervision

reviews the record

and depends

on trend for detecting

errors

and deviations.

The licensee

does

not consider it necessary

to use verification of data

by another technician or gC to minimize

personnel

error.

The health physics

and chemistry personnel

stated

that the activities could be benefited

by the survei llances of know-

ledgeable

gC technicians.

The inspector

noted that

some of the

(}C

technicians

did not verify the adequacy

of the actions

they witnessed

as discussed

in paragraph

6.2 below.

The

gC organization is address-

ing this concern

by recruiting technically competent

technicians

and

providing necessary

training to the existing technicians

to increase

the subject matter expertise.

Cl

i C'

11

0

6.2

Low Level

Radwaste

Shi

ment

The inspector

reviewed activities associated

with shipment

No. 85-84.

.The shipment

was processed

in accordance

with procedure

RD-10.6.

The

required

dose

surveys

were done

by a technician

and witnessed

by a

gC

technician.

However,

the procedure

steps

were signed off by a health

physicist

who was not present

when these

surveys

were made.

The health

physicist stated that his initials indicate that the step

was executed

by someone

under his cognizance.

Similarly, the

gC technician

stated

that his hold point sign-off merely indicates that the action was

com-

pleted

by the technican while the

gC technican

was physically present.

The hold point sign-off does

not assure

the technical

accuracy of the

'survey.

The health physicist stated that

he holds the technician

solely responsible

for the reading.

Neither the health physicist nor

the

gC technician

had any responsibility to verify the accuracy of

the readings

recorded

by the technican.

The

gC supervisor

stated

that

he expected

his technicians

to verify the accuracy of any readings

taken while

QC was present.

However,

in this case,

the

gC technician

stated that

he did not verify the accuracy of the reading

recorded.

The inspector discussed

the matter with licensee

management.

A licen-

see supervisor

stated that they were aware of the lack of technical

knowledge

in some

gC technicians

and they expect to correct this situ-

ation by hiring technically competent

gC technicians

and using "back-

to-the basics" training sessions.

As

a result of a recent

NRC violation and problems identified in low

level radwaste

shipments,

the overall health physics

and chemistry

activities were conducted with noticeable

awareness

to the require-

ments

and attention to details.

A recent technically oriented

gA

audit in health physics

area

was well received; it assisted

the

health physics organization

to realize its weaknesses

and take actions

to strengthen

the weaknesses.

Except for the level of gC involvement

and verification of measurements

taken

by technicians,

the inspector

found the health physics

and chemistry activities to be conducted

in

accordance

with the licensee

procedures

and applicable regulatory

requirements.

No violations were identified.

As in other

areas

of this inspection,

the inspector

noted that the

licensee's

efforts to enhance

the effectiveness

of gA and

gC activ-

ities did not reach the working level.

The Health Physics

and

Chemistry staff acknowledged this observation.

7.0

Licensee Action on Previous Identified Items

Closed

Ins ector Follow Item

85-04-05

Calibration

and Control of

Measurin

and Test

E ui ment

MKTE

The

the

ing

ing

inspector

reviewed

METE as required

by procedure

A-1201 and found that

calibration of those ATE identified in Inspection

Report 85-04 as be-

out of calibrations

were current.

The inspector

reviewed the follow-

calibration test reports:

~

5 ~

~

25

Circuit Breaker Test Set (Mulit-Amp) Model

No.

CB-7150 Serial

No.

18553,

Cal.

1-18-86

Circuit Breaker Test Set (Multi-Amp) Model

No.

CB-8160 Serial

No.

34211,

Cal.

1-18-86

Relay Test Set (Multi-Amp) Model

No.

MS-2 Serial

No., 32471 Cal.

1-18-86

This item is closed.

8.0

Unresolved

Item

Unresolved

items are

items about which more information is required to as-

certain whether they are acceptable,

violations or deviations'nresolved

items identified during this inspection

are discussed

in paragraphs

4.2 and

5.1.

. 9.0

Exit Interview

The inspection

team met with licensee

representatives

denoted

in paragraph

1 at the conclusion of the inspection

on January

31,

1986.

The summarized

purpose,

scope

and findings were presented.

At no time was written mate-

rial provided by the inspector to the licensee.

l,>

~

%>i

1 VPf

"C

ATTACHMENT 1

DETAILS OF THE VESSEL HEAD AND INTERNALS LIFTING RIGS

INSPECTION

Licensin

Commitment

Licensing commitments

due to

NRC concerns

associated

with the issue of Con-

trol of Heavy Loads for Special Lifting Devices,

were

made

by the licensee

in it's letter to

NRC dated

March 2,

1983 which stated that

..."RGKE has

implemented

an inspection,

testing

and maintenance

program to insure con-

tinued compliance with ANSI N14.6-1978.

This program will require visual,

inspections

annually (not to exceed

15 months,

consistent with permissible

intentions for Technical Specification Surveillance).

Nondestructive

exa-

mination of critical welds will also

be done every ten years."

It appears

that the

above licensee

commitments

were to be achieved

by their develop-

ment and implementation of procedure

MHE-1100-1,

Rev.

0.

Additionally,

procedure

A-1011,

Rev.

5,

Equipment Inspection

Period

and Lubricant List,

required the

RVHLD and

RVILD to be inspected prior to refueling.

1983 Refuelin

Outa

e Activit

The licensee's

contractor for refueling developed

procedure

RF-58,

Rev.

0

dated

March 31,

1983 to cover Cycle XII-XIIIrefueling operations.

Step

7.2.30 of this procedure

indicated that the

RYHLD was installed

as per

paragraph

9.2.7,

and

was signed off as being complete

by

a licensee

con-

tractor

on April 28,

1983.

Paragraph

7.2.42 indicated that the reactor

vessel

head lift preparations

were complete

and

was signed off by the

same licensee

contractor

on May 1,

1983.

This was followed by gC Hold

Point No.

1 that referred to the Process

Control Sheet

in paragraph

8.2,

with the hold point attesting that the reactor vessel

head lift prepara-

tions were complete.

The hold point was signed

by

a licensee guality

Engineer

on May 1,

1983.

In procedure

RF-58,

paragraph

8.2, (}uality Assurance

Inspection

Program,

there were

two hold/witness

points that referred to procedure

paragraph

7.2.42.

The first stated that the reactor vessel

head lift preparations

were complete

and

was signed

by a gA representative

on May 1,

1983.

The

second

stated that the structural integrity test of reactor vessel

head

lifting devices

was performed

and results

were satisfactory.

This was to

be signed

by

a

gC representative.

This was also

signed

on

May 1,

1983 by

the

same

gA individual.

Paragraph

9.2.7.A.4 indicated that the step,

lifting of the reactor vessel

head

2 inches,

was completed

and signed off

on

May 1,

1983.

~

~ >

'

r,

4'll

e

Attachment

1

Procedure

MHE-1100-1,

Rev.

0 dated

March 25,

1983,

Inspection

and Mainten-

ance of Special Lifting Devices,

required in procedure

paragraph

5. 1.5

"... Inspecting

personnel

shall

use the instructions

and form( s) provided

in this instruction for the inspection of these Lifting Devices."

Proce-

dure paragraph

5.3. 1, required ..."Visual examination, prior to use.

a.

After re-assembly

of the "Reactor

Vessel

Head Lifting Device",

visually examine:

1.

The clevis plate to leg fillet welds at the bottom end of

the legs.

2.

The support lugs to ring girder fillet welds

on the platform.

b.

After checking all bolted connections

on the "Reactor

Vessel

Internal

Lifting Device" visually, examine:

1.

Bottom lugs to top of support plate fillet welds

on the support

plate assembly.

2.

Side lug to support pipe fillet welds

on the support pipe.

3.

Spreader

lug to leg assembly fillet welds."

In addition,

paragraph

5.3.2,

Visual Inspection

Upon Lifting, required the

Rigging Foreman

to perform

a visual inspection of the welds specified in

paragraph

5.3. 1 under load.

According to the procedure,

these

welds were

to be examined for cracks

using dye penetrant

or magnetic particle tests

every

10 years.

A review of the completed

records for the weld inspections

conducted

in

1983 indicated the following:

Prior to the reactor vessel

head lift on May 1,

1983,

the licensee

performed

a visual inspection of the

RVHLD on April 7,

1983.

The

completed

documentation

form for the Inspection of the

RVHLD con-

tained in procedure

MHE-1100-1 indicated that

1) visual inspection

was performed

from the operating level,

and 2) that the

NDE for welds

described

in a. 1 and a.2

above

were scheduled

to be performed later

in the outage.

According to the

MHE Foreman,

the visuals were essen-

tially bolting checks utilizing binoculars

from the operating level.

This indicated

a misunderstanding

of the procedure

requirements

by

the

MHE foreman.

The

HDE documentation

for RVHLD showed that

PT inspections

were per-

formed only on the Link Lugs to Sling Assembly welds

on May 12,

1983.

However,

these

welds were not incorporated

in MHE-1100-1 at that time.

~ ~

E

e.

Attachment

1

The above indicates that visual inspections

of specified welds were

not adequately

performed

by the licensee after the reassembly

of the

RVHLD, prior to use of the

RVHLD, and after lifting the

head utilizing

the

RVHLD, as required

by procedure

MHE-1100-1,

Rev.

0.

Regarding

the inspections

performed

on the RVILD, the completed

documentation

form for the inspection of the

RVILD contained

in

procedure

MHE-1100-1 indicated that 1)

a visual inspection

was

performed

from the operating level of bolted connections

on

April 7,

1983

and 2) that the

NDE for welds described

in b. 1,

b.2 and b.3 above were scheduled

to be performed later during

the outage.

A PT examination

record for the

RVILD documented

that the licensee

performed all weld

NDE inspections

(10 year)

stipulated

in procedure

MHE-1100-1 on May 27,

1983.

Prerequisites

for fuel movement were complete

on May 2,

1983.

This included

removal of the reactor vessel

upper internals uti-

lizing the

RVILD.

The records did not indicate that visual in-

spections

of specified welds were performed

by the licensee

either prior to use or upon lifting of the reactor. upper inter-

nals utilizing the

RVILD, as required

by procedure

MHE-1100-1,

Rev.

0.

As stated earlier,

there

was

a hold/witness point in procedure

RF-58

to confirm that the structural integrity of the

RVHLD was verified

with satisfactory results.

The fact that the hold/witness point was

signed off without comment

suggests

the lack of a proper review and

adequate

understanding

of the requirements

by

QC personnel.

QC did

not review and assure

that the structural integrity verification was

acceptable.

3.

1984 Refuelin

Outa

e Activit

The licensee's

refueling contractor developed

procedure

RF-59,

Rev.

0 dated

March 1,

1984 to cover

Cycle XIII-XIVRefueling Operations.

All reactor

disassembly

procedures

for the

RVHLD structural integrity check were iden-

tical to those

enumerated

above in procedure

RF-58.

During the

1984 re-

fueling outage,

the reactor vessel

head

and the upper internals

were lifted

on April 11,

1984.

As in 1983,

procedure

MHE-1100-1,

Rev. 0,

was to be uti-

lized for the weld inspections

to assure

the structural integrity of the

RVHLD and

RVILD. Therefore, all previously enumerated

requirements

of this

procedure

were applicable during the

1984 refueling outage.

~

~ >

Attachment

1

A review of the records

for the

1984 weld inspections identified the

following:

The form in MHE-1100-1 documenting

the visual inspection prior to

lifting the

RYHLD was signed-off

on March 9,

1984 by a Level II

Inspector

and the

MHE Foreman.

This form indicated that the visual

inspection

was not feasible

because:

1) the support lug to ring

girder fillet weld was not accessible

due to construction inter-

ferences

by an installed platform,

and 2) the clevis plate to leg

fillet welds were covered with lead blankets.

Another note

on the

same

form indicated that the inspection of the

RVHLD had

been can-

celled for the current outage,

and the Level II inspector

was in-

formed of this cancellation

on March 6,

1984.

Weld examination

records further indicated that

a visual examination

was performed

on

RVHLD Link Lugs to Sling Assembly

on March 6,

1984, although this

examination

was not required

by the current procedure.

The records

also

showed that visual

and

PT examinations of clevis plate to leg

fillet welds were performed

on April 12,

1984 after the reactor

vessel

head lift.

As in 1983, specified welds were not visually inspected

by the licen-

see after the reassembly

of the

RVHLD, prior to use of the

RVHLD, or

upon lifting of the

head utilizing the

RVHLD as required

by procedure

MHE-1100-1,

Rev.

0.

The completed documentation

form for the inspection of the RVILD,

which was signed

by the Level II inspector

and

MHE Foreman

on March

7,

1984 indicated that the bolted connections

were inspected

and

found acceptable.

As in 1983, it appeared

that visual inspections of specified welds

were not performed

by the licensee either prior to use or upon lift-

ing of the reactor

upper internals utilizing the RVILD, as required

by procedure

MHE-1100-1,

Rev.

0.

The

QC hold/witness point in procedure

RF-59, to confirm the struc-

tural integrity of the

RVHLD, was as ineffective as in 1983.

However,

a

QA Audit of refueling activities,

84-15:SB conducted

during the

period of March 15,

1984 to May 25,

1984 identified (AFCAR, Finding

No. 2), that the

RVHLD and

RYILD were not properly inspected

prior to

refueling in 1983

and

1984.

Additionally, it was identified that

QA

Hold Point Ho. 2, in procedure

RF-59,

paragraph

7.2.42,

which attest-

ed to the structural integrity of the

RVHLD, was inadequate

in that

procedure

MHE-1100-1 was not correctly utilized to accomplish

the

inspection.

l

)P,

Attachment

1

AFCAR, Finding No. 2, provided the following information:

1) the

MHE

Foreman

confirmed that

RVHLD inspections

could not be performed

as

noted

by Level II inspector

on the respective

form, 2) the inspec-

tions required

by procedure

RF-59,

paragraph

7.2.42,

was to be per-

formed by the

MHE group according to the Maintenance

Manager,

3) the

gC inspector

signing the hold point was not aware that the inspection

in question

was to be in accordance

with procedure

MHE-1100-1 and re-

lated to procedure

A-1011, 4) both procedures

RF-59 and A1011 did not

identify the

MHE Group's responsibility required

by procedure

MHE-

1101-1,

and 5) procedure

RF-59 did not require

an inspection of the

RVILO prior to lifting the reactor vessel

internals.

C

The Audit's "Recommended Actions" suggested

the following:

a

~

Revise procedure

A-1011 to properly address

ten-year

and annual

inspection

requirements

with reference

to procedure

MHE-1100-1

b.

Provide clarification in future

RF procedures

to assure

the

RVHLO and

RVILO inspections

are properly performed prior to

lifting the reactor vessel

head

and internals.

c.

Provide administrative controls to assure

appropriate

Ginna

personnel

are

aware of the status of lift rig inspections.

The recommendations

of the

AFCAR, Finding Ho. 2, of audit 84-15:SB

was assigned

to the Ginna Station organization for corrective action.

Station personnel

responded

with the following corrective actions:

a.

A procedure

change

notice to A-1011 has

been initiated.

This

will address

the

10 year

and yearly inspection

requirements

as

recommended.

A change

has

been drafted to be incorporated

into Cycle XIV-XV

Refueling Procedure

in Section

7

~ 0 "Performance".

The change

will read

as follows "All applicable

steps of procedure

MHE-

1100-1

have

been satisfactorily completed for the

RVHLD and

RVILD."

A note will be added that states

"Completion of MHE

-1100-1 will be verified by appropriate

MHE personnel".

c.

Future

RF procedures will be clarified to provide the necessary

administrative control to assure

that appropriate

Ginna person-

nel are

aware of lifting rig inspections.

"l

~ i

~

4

Attachment

1

It should

be noted that the

gA engineer

who prepared

the Audit Report

84-15:SB provided sufficient details to develop effective corrective

actions.

However, the corrective actions

by the Station were inef-

fective in that:

(1) item c was not implemented

and (2) item b did

not specify that the hold/witness point in paragraph

8.2.2. of the

RF

procedure

should confirm the completion of MHE-1100-1 procedure

steps.

From the above, it is apparent that the finding from Audit 85-11:JB

was

a repeat finding and the licensee's

corrective

measures

were not

effective to assure

that critical welds would be inspected.

4.

1985 Refuelin

Outa

e Activit

The licensee's

refueling contractor developed

procedure

RF-60,

Rev.

0 dated

March 4,

1985 to cover Cycle XIV-XV Refueling Operations.

All procedural

requirements

pertaining to the reactor disassembly

as they relate to the

performance

and verification of the

RVHLD and

RVILD structural integrity

checks

were identical to those

enumerated

above in procedures

RF-58 and

RF-59 for the

1983

and

1984 refueling outage,

respectively,

with the ex-

ception of a

new step 7.2.30a,

which states..."All applicable

steps of

procedure

MHE-1100-1 have

been satisfactory

completed for the Reactor

Ves-

sel

Head Lift Device and

and Upper Internals Lift Device.

Note:

Comple-

tion of MHE-1100-1 will be verified by appropriate

MHE personnel."

This

step

was signed

by the

MHE Foreman

on March 5,

1985.

On March 9,

1985 the

gA Hold Point No.

1 immediately after paragraph

7.2.42

was signed

and it

verified

that the reactor

vessel

head lift preparations

were complete.

(i.e., Structural integrity of reactor

vessel

head lifting devices

was

performed

and results

are satisfactory).

During this outage

Revision

1 to procedure

MHE-1100-1 was used.

This re-

vision of the procedure

required in paragraph

5.3. 1 ..."Visual examination

(annual) prior to use.

( Item numbers refer to weld groups

on respective

figures).

a.

After re-assembly

of the "Reactor Vessel

Head Lifting Device" (Figure

10) tripod assembly

to the lower platform assembly,

visually, examine:

1.

The clevis plate to leg fillet welds at the bottom end of the

legs.

2.

The support lugs to ring girder fillet welds

on the platform.

(Exposed Area)

3.

Link Lugs to Sling Assembly Melds.

b.

After checking all bolted connections

on the "Reactor Vessel

Internals

Lifting Device" (Figure 3) visually, examine:

i>

~i

a

Cl

r

I

Attachment

1

1.

Bottom lugs to top of support plate fillet welds

on the support

plate assembly.

2.

Side lug to support pipe fillet welds

on the support pipe.

3.

Spreader

lug to leg assembly fillet welds.

4.

Leg Assembly Outer Tube to Adapter Welds.

5.

Outer Tube to Guide Sleeve

Welds."

The requirement

to visually inspect the welds while lifting devices

were

under load was deleted

from the current revision of MHE-1100-1.

A review of the records for 1985 weld inspections

indicated:

The reassembly

of the

RVHLD and the reactor

vessel

head lift, were

done

on March 9,

1985.

The Link Lug to Sling Assembly Welds were

visually inspected

on March 5,

1985.

This represents

only 3 of the

9

welds required to be visually inspected.

Therefore, it appears

that

visual inspections

of all specified welds were not performed

by the

licensee either after reassembly

of the

RVHLD or prior to its use

as

required

by procedures

MHE-1100-1,

Rev.

1 and A-1011,

Rev.

7.

The licensee

provided

no records that would indicate that weld

inspections

were performed

on the

RVILD.

As in 1983

and

1984, all critical

RVHLD welds were not visually in-

spected

by the licensee prior to use of the

RVHLD as required

by

procedures

MHE-1100-1, .Rev.

1 and A-1011,

Rev.

7.

The hold/witness

point in procedure

RF-60, to confirm the structural integrity of the

RVHLD and

RVILD, appeared

to be almost

as ineffective as in 1983 and

1984.

QA Audit 85-11:JB

was reviewed

and it had the following

deficiencies:

The

AFCAR did not identify that this was

a recurring finding.

The lack of procedural

adherence

by the

MHE Group was not

addressed

in the recommendations

or corrective actions.

The ineffectiveness

of corrective action for the finding

in 1984 audit was also not addressed.

The continued ineffectiveness

of the

QC hold/witness points was

not addressed

by the

AFCAR.

The

QA organization

opted to rely on

an informal corrective

action statement

and tracking

system for this finding .

The findings detailed

in this attachment

are

summarized

in paragraph

3.2. 1 of the report.

4i uw