ML17251A552

From kanterella
Jump to navigation Jump to search
Responds to NRC Bulletin 88-008 Re Thermal Stresses in Piping Connected to Rcs.Program to Provide Continuing Assurance That Identified Unisolable Sections of Piping Attached to RCS Do Not Fail Initiated
ML17251A552
Person / Time
Site: Ginna Constellation icon.png
Issue date: 06/22/1989
From: Mecredy R
ROCHESTER GAS & ELECTRIC CORP.
To: Andrea Johnson
Office of Nuclear Reactor Regulation
References
IEB-88-008, IEB-88-8, NUDOCS 8906300219
Download: ML17251A552 (4)


Text

gC CEMRA,TED Dl B

RECIPIENT ID CODE/NAME PD1-3 LA JOHNSON,A COPIES LTTR ENCL 1

0 1

1 RECIPIENT ID CODE/NAME PD1-3 PD COPIES LTTR ENCL 1

1 REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)

ACCESSION 'NBR:8906300219 DOC.DATE: 89/06/22 NOTARIZED: NO FACIL:50-244 Robert, Emmet Ginna Nuclear Plant, Unit -1, Rochester G

AUTH.NAME

'UTHOR AFFILIATION MECREDY,R.C.

.Rochester Gas 6 Electric Corp.

RECIP.NAME 'ECIPIENT 'AFFILIATION JOHNSON,A.R.

Project Directorate I.-3 I

SUBJECT:

Responds to NRC Bulletin 88-008 re thermal stresses in piping connected to RCS.

DISTRIBUTION CODE:

IE16D COPIES RECEIVED:LTR ENCL SIZE:

TITLE: Bulletin Response 88-08 Thermal Stress in Piping to RCS.

NOTES:License Exp date in accordance with 10CFR2,2.109(9/19/72).

DOCKET 05000244 R

D

.S.

05000244 h

INTERNAL: AEOD/DOA NRR HARTZMAN,M NRR REEVES,E.A.

NRR/DEST/ADS 7E NRR/DOEA/EAB 11 NRR/DREP/EPB 10 NUDOCS-ABSTRACT RES/DSIR/EIB EXTERNAL:. LPDR NSIC 1

1 1

1 1

1 1

1 1

1 1

1 1'

1 1

1 1

1 1

AEOD/DSP/TPAB NRR HUM,M NRR/DEST/ADE 8H NRR/DEST/MEB 9H NRR/DOEA/GCB 11 NRRjPMAS/ILRB12

'XEE 02 RGNl IKE 01 NRC PDR 1

1 1

1 1

1 1

1 1

1 1

'1 1

1 1

1 1

1

~ po (39 ~'tab go

'h D

NOXZ 'IO ALL RIIS" RECIPXERIS:

PLEASE HELP US 'IO REOOCB %ASTE.'2KACI'IHE DQQ3NEÃZ CGÃlBOL DESKS RXN P1-37 (EXT. 20079) m EIZHEÃLTB ACR NAMB PKH DISTRISUTXCN

~ LXSTS FOR DOCUMEHIS YOU DOH~T NEED!

TOTAL'NUMBER OF COPIES REQUIRED:

LTTR 22 ENCL 21

ROCHESTER GAS AND ELECTRIC CORPORATION

~

/

TOPS SlsTT 89 EAST AVENUE, ROCHESTER, N.Y. 14649-0001 June 22, 1989 TcT.ce~ohc AecA coDE TTe 546.2700 U.S. Nuclear Regulatory Commission Document Control Desk Attn:

Allen R. Johnson Project Directorate I-3 Washington, D.C.

20555

Subject:

Response

to Bulletin 88-08 Thermal Stresses in Piping Connected to Reactor Coolant Systems;-

dated June 22, 1988 R.E.

Ginna Nuclear Power Plant Docket No. 50-244

Dear Mr. Johnson:

In response to the requirements of NRC Bulletin 88-08, the following information is provided.

NRC Re est Review systems connected to the RCS to determine whether unisolable sections of piping connected to the RCS can be subjected to stresses from temperature stratification or temperature oscillations that could be induced by leaking valves and that were not evaluated in the design analysis of the piping.

For those addressees who determine that there are no unisolable sections of piping that can be subjected to such stresses, no additional actions are requested except for the report required below.

~Res ense 1.

As described in the September 28, 1988 letter from Robert C. Mecredy to Carl Stahle, systems attached to the RCS'ave been reviewed and unisolable sections of piping which might be subject to adverse thermal conditions have been identified.

'+06~0+2( y ty~

~.

~DOCI." O-r>OCl-qq pfn

~~pg oe5dF~>

/(

Re est 2.

For any unisolable sections of piping connected to the RCS that may have been.subjected to excessive thermal stresses,'xamine nondestructively the

welds, heat-affected zones and -high stress locations, including geometric discontinuities, in that piping to provide assurance that there are no existing flaws.

R~es nse 2.

Three unisolable sections of piping connected to the RCS were previously determined to have the potential for thermal cycling.

These sections are:

i.

charging system to Loop B hot leg between check valve 393 and the RCS nozzle, ii.

alternate charging system to Loop A cold. leg between check valve 383A and the RCS nozzle, and iii. auxiliary pressurizer spray system between check valve 297 and the three inch tee which connects the auxiliary pressurizer spray to the main pressurizer spray line.

The inspection locations for nondestructive examination to provide assurance that there are no existing flaws were selected based on the following factors:

~ pipe geometry,

~ temperature difference between the pipe metal and the reactor coolant,

~ possible existence of valve leakage, and

~ industry pipe crack experience.

Examinations were performed at the most susceptible locations, as recommended by Westinghouse, on each of the three unisolable pipe sections.

All examination results were acceptable.

Re est 3.

Plan and implement a

program to provide continuing assurance that unisolable sections of all piping connected to the RCS will not be subjected to combined cyclic and static thermal and other stresses that could cause fatigue during the remaining life of the unit.

This assurance may be provided (1) redesigning and modifying these sections of piping to withstand combined stresses caused by various loads includ'ing temporal and spatial distributions of temperature resulting from leakage across valve seats, (2) instrumenting this piping to detect adverse temperature distributions and establishing appropriate limits on temperature distributions, (3) providing means for ensuring that pressure upstream from block valves which might leak is monito'red and does not exceed RCS pressure.

R~es onse 3 e A

program to provide continuing assurance that the identified unisolable sections of piping attached to the RCS do not fail, due to thermally initiated or advanced

fatigue, has been initiated.

This assurance is provided in part, by instrumenting the affected piping to detect adverse temperature conditions.

Appropriate guidelines have been developed to establish acceptance criteria for observed temperature distributions.

In addition to the temperature monitoring, -the affected piping will be subject to repeat nondestructive examinations during future refueling outages.

It is currently planned to provide the existing temperature monitoring at least until the 1990 refueling outage at which time nondestructive examinations will be repeated.

Based on the results of the temperature monitoring, nondestructive examinations and engineering analysis; the program may be restructured as necessary to provide continued assurance based on meaningful results.

Very truly yours, Robert C. Mecre General Manager Nuclear Production MPLK050 xc:

U.S. Nuclear Regulatory Commission Region I 475 Allendale Road King of Prussia, PA 19406 Ginna Senior Resident Inspector