NRR E-mail Capture - Acceptance Review of Relief Request Regarding Alternative to Utilize Code Case N-513-4
ML17242A068
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 08/30/2017
From: Sujata Goetz
Plant Licensing Branch III
To: Jonathan Haas
DTE Energy Services
References
Download: ML17242A068 (3)


Text

NRR-PMDAPEm Resource From: Goetz, Sujata Sent: Wednesday, August 30, 2017 9:10 AM To: Jason R Haas

Subject:

Acceptance Review of Relief Request Regarding Alternative to Utilize Code Case N-513-4

Dear Mr. Haas,

By letter dated August 15, 2017, (Agencywide Documents and Access Management System (ADAMS)

Accession No. ML17228A080), DTE submitted a relief request for Fermi 2. The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this relief request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed relief request in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

Based on the information provided in your submittal, the NRC staff has estimated that this licensing request will take approximately 200 hours8.333 days <br />1.19 weeks <br />0.274 months <br /> to complete. The NRC staff expects to complete this review by August 2018. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager. These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities.

If you have any questions, please contact me at (301) 415-8004.

Sujata Goetz Project Manager, Fermi, Unit 2 Nuclear Regulatory Commission 11555 Rockville Pike Office of the Nuclear Reactor Regulation NRC/NRR/DORL/LP3 Office O8F2 Mailroom O8-B1A Rockville, MD 20852-2738 Washington, DC 20555-0001 1

(o) 301.415.8004 (fax) 301.415.3313 (fax)

Mail Stop 08A1A 2

Hearing Identifier: NRR_PMDA Email Number: 3699 Mail Envelope Properties (Sujata.Goetz@nrc.gov20170830091000)

Subject:

Acceptance Review of Relief Request Regarding Alternative to Utilize Code Case N-513-4 Sent Date: 8/30/2017 9:10:18 AM Received Date: 8/30/2017 9:10:00 AM From: Goetz, Sujata Created By: Sujata.Goetz@nrc.gov Recipients:

"Jason R Haas" <haasj@dteenergy.com>

Tracking Status: None Post Office:

Files Size Date & Time MESSAGE 2725 8/30/2017 9:10:00 AM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received: