Notice of Violation from Insp on 920128-0224.Violation Noted:Plastic Pint Spray Bottles of 91% Isopropyl Alcohol Observed Stored Unattended in Open Crew Box in Unit 1 Cable Spreading Room
ML17227A376
Person / Time
Site: Saint Lucie NextEra Energy icon.png
Issue date: 03/13/1992
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML17227A375 List:
References
50-335-92-04, 50-335-92-4, NUDOCS 9204080037
Download: ML17227A376 (2)


Text

ENCLOSURE 1

NOTICE. OF VIOLATION Florida Power 8 Light Company St. Lucie 1

Docket Nos.

50-335 License Nos.

DPR-67 During an

.NRC inspection conducted on January 28 - February 24,

1992, a

violation of NRC requirements was identified.

In accordance with the, "General Statement of Policy and Procedure for NRC Enforcement Actions," 10 CFR Part 2, Appendix C (1991), the violation is listed below:

l'nit 1

Technical Specification (TS) 6.8. l.f requires that wr,itten procedures shall be established, implemented, and maintained covering fire protection program implementation.

This requirement is implemented in part by site administrative procedure AP 0010434, Rev 23, Plant -Fire Protection Guidelines.

AP 0010434 paragraph 8.2.3 listed the safety-related areas where combustibles may be stored.

Storage of combus'tibles in the cable spreading rooms was not included.

Contrary to the above, on January 28,

1992, two plastic pint spray bottles of 91 percent isopropyl alcohol were observed. stored unattended in-an open crew box in the Unit 1 cable spreading room'.

These spray bottles had attached material safety data sheets numbered "1552.500, 1549" stating that the material was 'flammable and must be transferred to a safety can and stored in a

flame-proof cabinet.

When notified, the licensee immediately removed the alcohol to a non-safety-related area.

This is a Severity Level IV violation (Supplement I).

Pursuant to the provisions of 10 CFR 2.201, the Florida Power

& Light Company is hereby required to submit a written statement or explanation to the U.S.

Nuclear Regulatory Commission, ATTN: Document Control

Desk, Washington, D.C.

20555, with a copy to the Regional Administrator, Region II, and a copy to the NRC Resident Inspector, within 30 days of the date of the letter transmitting this Notice of Violation (Notice).

-This reply should be clearly marked as a

"Reply to a Notice of Violation" and shoul'd include for each violation:

( 1) the reason for the violation, or, if contested, the basis for disputing the violation, (2) the corrective steps that have been taken and the results

achieved, (3) the corrective steps that will be taken to avoid further violations, and (4) the date when full compliance will be achieved.

If an adequate reply is not received within the time specified in this Notice, an

, order may be issued to show cause why the license should not be modified, suspended, or revoked or why such other action as may be proper should not be taken.

Where good cause is shown, consideration will be given to extending the response time.

Dated at Atlanta, Georgia this 13th day of March 1992 9204080037 9203l3 PDR ADOCK 05000335 Q