ML17219A329

From kanterella
Jump to navigation Jump to search
Forwards Request for Addl Info Re 860702 Submittal on Transferring Spent Fuel.Response,Including Structural Data on Spent Fuel Shipping Cask Used to Transfer Spent Fuel Assemblies,Requested within 30 Days of Ltr Receipt
ML17219A329
Person / Time
Site: Saint Lucie 
Issue date: 01/23/1987
From: Tourigny E
Office of Nuclear Reactor Regulation
To: Woody C
FLORIDA POWER & LIGHT CO.
References
NUDOCS 8702030123
Download: ML17219A329 (12)


Text

JAN 23 1987 z>HB ~/4 Docket No. 50-389 Mr. C. 0.

Moody Group Vice President Nuclear Energy Florida Power lm Light Company P. 0.

Box 14000 Juno

Beach, Florida 33408

Dear Mr. Woody:

In conducting our review of your July 2, 1986 submittal relating to transferring spent fuel at the St. Lucie Plant, Unit No. 2, we have determined that we will need additional information identified in the enclosure to continue our review.

In order for us. to maintain our review schedule, your response is requested within 30 days of vour receipt of this letter.

The reporting and/or recordkeeping requirements contained in this letter affect fewer than 10 respondents; therefore, OMB clearance is not required under P.L.96-511.

Please contact me at (301) 492-8007 if you have any questions concerning this letter.

Sincerely,

Enclosure:

Request for Additional Information cc w/enclosure:

See next page ANginal signed by E.

G. Tourigny, Project Manager PWR Project Directorate ¹8 Division of PHR Licensing-B PBD¹8~~

ETourfanv;cf I/8 /87 PBD¹ 1/0 /87 87P<oaoi a3-- ---- =

PPDR ADO 87pi23 ll---

. Qgooog89 PDR oc et UTION NR PDR L PDR PBD-8 Rdg FMiraglia OGC-Bethesda EJordan PWR-B:EB TMarsh 1/ j)/87 ACRS-10 TMarsh BGrimes JPartlow ETourigny PKreutzer Gray File NThompson DCrutchfield NL fiel d If2b/87 PBD¹8 AThadani 1/

/86

~0 4

0 4

0

Mr. C. 0.

Woody Florida Power 5 Light Company St. Lucie Plant CC:

Mr. Jack Shreve Office of the Public Counsel Room 4, Holland Building Tallahassee, Florida 32304 Resident Inspector c/o U.S.

NRC 7585 S.

Hwy A1A Jensen

Beach, Florida 33457 State Planning 5 Development Clearinghouse Office of Planning 8 Budget Executive Office of the Governor The Capitol Building Tallahassee, Florida 32301 Harold F. Reis, Esq.

Newman E Holtzinger 1615 L Street, N.W.

Washington, DC 20036 Norman A. Coll, Esq.

McCarthy, Steel, Hector and Davis 14th Floor, First National Bank Building Miami, Florida 33131 Administrator Department of Environmental Regulation Power Plant Siting Section State of Florida 2600 Blair Stone Road Tallahassee, Florida 32301 Mr. Weldon B. Lewis, County Admini.strator St. Lucie County 2300 Virginia Avenue, Room 104 Fort Pierce, Florida 33450 Mr. Charles B. Brinkman; Manager Washington - Nuclear Operations Combustion Engineering, Inc.

7910 Woodmont Avenue

Bethesda, Maryland 20814 Mr. Allan Schubert, Manager Public Health Phvsicist Department of Health and Rehabilitative Services 1323 Winewood Blvd.

Tallahassee, Florida 32301 Regional Administrator, Region II U.S. Nuclear Regulatorv Commission Executive Director for Operations 101 Marietta Street N.W., Suite 2900 Atlanta, Georgia 30323

0 I

f g

Request for Additional Information Proposed License Ammendment Spent Fuel Transfer St. Lucie Unit 2

The following requests pertain to Florida Power

& Light Company's submittal to the NRC staff dated July 2, 1986 [1].

The Licensee is asked to respond to the following items regarding details of spent fuel transfer from St. Lucie Unit 1 to St. Lucie Unit 2 as described in their "Safety Evaluation/No Significant Hazards Consideration" report, [1].

Xtem No. 1:

Section 2.4 of the Licensee's submittal states that "Two transporter Vehicles were considered in the load path evaluation.

The maximum wheel loads for each of these transporters were found to be acceptable considering the

'effects on all surfaces including the roadway, missile protection slab, and underground facilities (i.e., pipes, electric conduit, manholes, and catch basins)."

Please provide the following structural details and data which support the above statement:

a.

Structural data of the spent fuel shipping cask which will be used to transfer spent fuel assemblies form Unit 1 to Unit 2 spent fuel pool (configu'ration and basic dimensions, total weight, shipping position..etc.)

~.

b.

Wheel arrangements, maximum recommended wheel loads and dead weight of the two transporter vehicles.

c.

Structural details and plan layouts of missile protection slab and underground -facilities to be

N

~

1

'L I

~

~

crossed by the transporter vehicles along the shipping load path.

d.

Results of stress analysis calculations indicating that every structural component listed in item c above shall withstand prescribed sustained and live loads with, acceptable margin of safety.

I Item No.

2 Please provide detailed description of how a spent fuel assembly of Unit l will be transferred safely from the shipping cask mounted on the transport vehicle to the designated spent fuel rack of Unit 2.

Item No.3 Please provide the basic mechanical design parameters of the fuel assemblies manufactured by Exxon Nuclear Company (ENC) since Unit l is scheduled to operate with ENC fuel only (cycle No.

8).

~

~

~

~

l

~

8 k

'I f

June 15, 1988 Docket No. 50-389 Mr.

W. F.

Conway Senior Vice President-Nuclear Nuclear Energy Department Florida Power and Light Company Post Office Box 14000 Juno

Beach, Florida 33408-0420 DISTRIBUTION

< Hocket F~'fe>

NRC 8 Local PDRs PDI I-2 Rdg.

SVarga, 14/E/4
GLainas, 14/H/3 DMi 1 1er MHum HBerkow ETourigny OGC
EJordan, 3302-f1NBB BGrimes 9/A/2 ACRS(10 Gray Fi1e

Dear Mr. Conway:

SUBJECT:

ST.

LUCIE PLANT - UNIT NO.

2 -

REQUEST FOR ADDITIONAL INFORMATIOf'1-USE OF INSTRUMENTED INSPECTION TECHflIQUE (TAC NO. 60890)

In conducting our review of your February 14, 1986 submittal relating to the above subject at the St. Lucie Plant, Unit No. 2, we have determined that we wi 11 need additional information identified in the enclosure to continue our review.

In order for us to maintain our review schedule, your response is requested within 45 days of the date of this letter.

If you cannot provide a full response within the requested time, please provide your full response schedule within 30 days of the date of this 'letter.

The reporting and/or recordkeeping requirements contained in th'is letter affect fewer than 10 respondents; therefore, Ol>ghouse Office of Planning

& Budget Executive Office of the Governor The Capitol Building Ta 1 1 aha s see, Florida 32301 Harold F. Reis, Esq.

Newman

& Holtzinger I615 L Street, N.W.

Washington, DC 20036 John T. Butler, Esq.

Steel, Hector and Davis 4000 Southeast Financial Center Miami, Florida 33131-2398 Adminisi.rator Department of Environmental Regulation Power Plant Siting Section State of Florida 2600 Blair Stone Road Ta 1 1 aha s see, F 1ori da 32301 fir. Weldon B. Lewis, County Administrator St. Lucie County 2300 Virginia Avenue, Room 104 Fort Pierce, Florida 33450 Mr. Charles B. Brinkman, Manager Washington - Nuclear Operations Combustion Engineering, Inc.

7910 Woodmont Avenue

Bethesda, Mary land 20814 Jacob Danie'I Nash Office of Radiation Control Department of Health and Rehabilitative Services 1317 Winewood Blvd.

Tallahassee, Florida 32399-0700 Regional Administrator, Region II U.S. Nuclear Regulatory Commission 101 Marietta Street N.W., Suite 2900 Atlanta, Georgia 30323