Forwards Joint Ebasco & C-E Task Force Engineering Verification Program Weekly Status Summary for 821108-13
ML17213A741
Person / Time
Site: Saint Lucie NextEra Energy icon.png
Issue date: 11/15/1982
From: Blodgett T
EBASCO SERVICES, INC.
To: Eisenhut D
Office of Nuclear Reactor Regulation
References
EVP-127-SL-2, NUDOCS 8211240049
Download: ML17213A741 (12)


Text

0 ~ 0 REGULATORY INFORMATION DISTRiBUTION SYSTEM (R IDS)

ACC'ES SION NBR; 82112<)0009 DOC ~ DATE: 82/11/15 NOTARIZED: NO DOCKET FACIL:50 389 St, Lucie Plant~ Unit 2, Florida Power 8 Light Co ~ 05000389

'AUTH, NAME AUTHOR AFFILIATION BLODGETTiT ~ HE Ebasco Services~ Ines of Ense> ch Corp,)

IP, NAME RECIPIENT AFFILIATION (sub'EC EISENHUT,DeG, Division of,Licensing

SUBJECT:

For wards joint Ebasco L C-E Task For ce engineering ver ification pr ogram weekly status s ummary for 821108-13 ~

DISTRIBUTION CODE e 8001S COPIES RECEIVED:LTR ENCL P s IZE:

TITLE: Licensing Submittal: PSAR/FSAR Amdts 8, Related Correspondence NOTES:

RECIPIENT COPIES RECIPIENT COP IFS IO CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL A/D LICENSNG 1 0 LIC BR N3 BC 0 LIC BR 03 LA 1 0 NERSESgV, 01 1 1 INTERNALS ELD/HDS2 1 0 IE FILE 1 1 IE/DEP EPDS 35 IE/DEP/EPLB 36 3 NRR/DE/AEAB NRR/DE/EQB 1

1 0 NRR/DE/CEB NRR/OE/GB ll 28 1

2 13 2 2 2 NRR/DE/HGEB 30 1 1 NRR/OE/MEB 18 1 1 NRR/DE/MTEB 17 1 1 NRR/DE/GAB 21 1 1 NRR/DE/SAB 2Q 1 1 NRR/DE/SES 25 1 1 NRR/DHFS/HFEBQO 1 1 NRR/DHFS/LQB 32 1 1 NRR/DHFS/OLB 30 1 NRR/DL/SSPB 1 0 NRR/DSI/AEB 26 1 NRR/DSI/CPB 10 1 NRR/DS I/CS8 09 1 1 NRR/OS I/ICSB 16 1 1 NRR/DS I/METB 12 1 1 NRR/OSI/f SB 1 SI/RA 8 22 1 1 NRR/DS I/RSB 23 1 1 REG FI QQ 1 RGN2 3 OAMI/MI8 0 EXTERNALS ACRS 6 6 BNL(AMDTS ONLY) 1 1 OMB/OSS (AMDTS) 1 1 FEMA REP OI V 39 1 1 1'

LPDR 03 1 1 NRC PDR 02 NSIC 05 1 1 NTIS 1 1 TOTAL NUMBER OF COPIES REQUIRED: LTTR 52 ENCL 45

(,'1

~ ~ <<) j ]I I 1 I i Ilr p I l

~ ~

f I>> -I y L t 'li 1 l,h '

'II/

, p ri ) f ttitlgy j lr) h t 1 i, ~ ro ~ p < g I'thi t t ~ / I

~

( gl t 5 >'tr) rt) ~ g>> jtjrh ) ~ i ~ f +Ir 'it ) f h/ t'tuh 4hh')I", .1>fl <j jl

~ th I111( 1 n'>I'l1 I q <r tt f,)f l leo,i( tfpftpt rit f ') t') if f ih,) ,I>> hatt Va t 1

'N f f*f r~ 7 ( '.( Irj .J l i 'lrII tit't f f I l,r n

ll'< l j

> "<<111 1

I ht l

II V I ti'I

'I L, l 1h~

P3I, I

,1 tt l i 1

1 'I" "if

<<1 f

ll I

Jt rt 1

e.

1 r

r

Engineering Verification Task Force Ebasco Services Incorporated Two World Trade Center-15th Floor New York, N. Y. 10048 November 15,1982 Ltr No. EVP-127/SL-2 Office of Nuclear Regulation Attention: Mr Darrell G Eisenhut, Director Division of Licensing U S Nuclear Regulatory Commission Washington, D.C. 20555

Dear Mr Eisenhut:

Re: ST. LUCIEN0.2 DOCKET NO. 50-389 ENGINEERING VERIFICATION PROGRAM WEEKLY STATUS

SUMMARY

FOR PERIOD'NOVEMBER 8 NOVEMBER 13 1982 Attached for your information is the Weekly Status Summary of the joint Ebasco and Combustion Engineering Task Force for the period November 8 through November 13,1982.

Very truly yours, T H Blodgett Joint Task Force Chairman THB/rob Attachment cc: Robert E Uhrig, FPL w/att D L Christian, FPL w/att Sasci40049 S2<i<5 ADQCK 0500038'P

'DR R PDR

U 4 l

ENGINEERING VERIFICATION PROGRAM/SL-2 EBASCO TASK FORCE WEEKLY STATUS SUKiARY FOR PERIOD NOVEMBER 8 NOVEMBER 13,1982

1. Status of independent vs existing design comparisons for verification items 3 8:
a. Item 3 Cntrl Rm Emer enc Cleanu S stem Valve
1) Received electrical documentation to complete receipt of existing design information from Project Team.
2) Electrical comparison sheets were completed.
3) Applied Physics comparison essentially complete.
4) HVAC and I&C comparisons complete.
b. Item 4 H dro en Recombiner
1) Electrical comparison sheets were completed.
2) Final review of Radwaste comparison sheets in progress.
3) Civil, I&C, HVAC and Applied Physics comparisons complete.
c. Item 5 Area Radiation Monitor
1) Electrical comparison essentially complete.
2) Applied Physics comparison nearing completion.
3) I&C and Civil comparisons complete.
d. Item 6 Tornado Missile Shield Door
1) Part of the remaining needed existing design information was received Nov ll. Continuing to expedite receipt of the balance.
2) Preparation of Civil comparison sheets was active.
3) I&C and Plant Security comparisons are expected to start early in the week of Nov 15, and be completed by Nov 17 along with the Civildesign comparison.
e. Item 7 Main Steam Isolation Valve
1) Balance of previously requested existing design information was received from Project Team, and requests for additional information during the period were promptly processed.
2) Completion of design comparison is estimated by Nov 17.

c

f. Item 8 HEPA Filter for ECCS Area Ventilation S stem
1) All requests for existing design information have been addressed by Project Team.
2) HVAC comparison sheets were completed.
3) Applied Physics comparison substantially complete.
4) I&C comparison complete.
2. Status of work being performed by ETF as interface with C-E Task Force-re expansion of component boundaries for verification items 1 and 2:
a. Item 1 HPSI Pum
1) ETF questions regarding the elementary wiring diagram were resolved via discussions with C-E Task Force.
2) Electrical and I&C independent designs are expected to be completed Nov 17, following which they will be presented to the Review Committee for completeness review. Design comparisons will commence following Committee authorization/receipt of requested existing design documents.
3) Independent verifications of actual vs allowable pump nozzle loads and of pump foundation existing design are expected to be completed Nov 17.
b. Item 2 SIT Isolation Valve
1) Anticipate electrical and I&C independent design completions Nov 16, with Nov 17 presentation to Review Committee for completeness review.
2) Comparison of designs will proceed following Committee authorization/

receipt of requested existing design documents.

3. Unresolved item (discrepancy) reports resulting from design comparisons are being prepared and finalized. Those differences which cannot be resolved by the Task Force will be addressed in Review Committee meetings starting Nov 17.
4. Civil and I&C discipline work was active on Saturday, Nov 13.

A

0 II t I

ENGINEERING VERIFICATION PROGRAM WEEKLY STATUS

SUMMARY

C-E TASK FORCE NOVEMBER 8 NOVEMBER 12

1. SIT Isolation Valve piping installation drawings were requested and received for the purpose of determining exact elevation of motor operator.
2. Carried out additional interface d'iscussions with Ebasco Task Force regarding electrical Instrumentation 6 Control requirements for EVP Items 1 & 2.
3. Discrepancy reports resulting from independent design comparison are being finalized in preparation of the next Review Committee meeting.
4. Continuing to prepare on-site verification check-lists for EVP Items 162.

t O

0 ZELEPHONE CONVERSATION LOG ENGINEERING VERIFICATION PROGRAM SL2 WEEK OF DATE OF PARTICIPATING GENERAL SUBJECT PREPARER OF TELE CON ORGANIZATIONS OF TELECON TELECON RECORD November 8 C-E/Ebasco SIT Isolation Valve C-E EVP Task technical interface Force Mgr between C-E/Ebasco Task Forces November 9 C-E/FPL SIT Isolation Valve- C-E EVP Task review info Force Mgr November 9 C-E/Ebasco SIT Isolation Valve C-E EVP Task installation dwgs Force Mgr November 9 Ebasco/C-E HPSI Pump-technical Ebasco EVP Task interface between Force Mgr Ebasco/C-E Task Forces November 10 C-E/Ebasco HPSI Pump technical C-E EVP Task interface between Force Mgr Ebasco/C-E Task Forces November 10 Ebasco/C-E C-E input to Nov 3 Ebasco EVP Task meeting minutes; Force Mgr interface items 1 and 2