Letter Sequence Response to RAI |
---|
|
|
MONTHYEARM170193, GE-Hitachi Nuclear Energy Americas, LLC - Submittal of Response to NRC Request for Additional Information2017-07-31031 July 2017 GE-Hitachi Nuclear Energy Americas, LLC - Submittal of Response to NRC Request for Additional Information Project stage: Response to RAI ML17312B3592018-01-18018 January 2018 Information Needed for the GE Hitachi Exemption Request for Alternate Decommissioning Schedules for Licenses DPR-1, DR-10 and TR-1 at the Vallecitos Nuclear Center (EPID No. L-2017-LLA-0052) (Docket Numbers: 50-18, 50-183, 50-70; License Nu Project stage: Other M180064, GEH Response Plan for NRC Request for Additional Information2018-03-28028 March 2018 GEH Response Plan for NRC Request for Additional Information Project stage: Request ML18123A3042018-05-21021 May 2018 GE Hitachi Response Plan for NRC Request for Additional Information Project stage: RAI M190202, GEH - Third Reply to NRC Request for Information Needed for GE-Hitachi Exemption Request for Alternate Decommissioning Schedules2019-11-15015 November 2019 GEH - Third Reply to NRC Request for Information Needed for GE-Hitachi Exemption Request for Alternate Decommissioning Schedules Project stage: Request ML20071G4112020-03-16016 March 2020 Request for Additional Information, GE Hitachi Request for Alternate Decommissioning Schedules for the Shutdown Reactors at the Vallecitos Nuclear Center Project stage: RAI M200102, GEH - Response to NRC Request for Additional Information (Rai), March 16, 20202020-07-15015 July 2020 GEH - Response to NRC Request for Additional Information (Rai), March 16, 2020 Project stage: Response to RAI ML20197A0122020-07-15015 July 2020 GEH - Response to NRC Request for Additional Information (Rai), March 16, 2020 Project stage: Response to RAI ML20174A1162020-07-15015 July 2020 Vbwr Request for Additional Information Enclosure Project stage: RAI ML20174A1152020-07-15015 July 2020 GE Hitachi Nuclear Energy - Vallecitos Nuclear Center, Vbwr Alternate Decommissioning Schedule - Request for Additional Information - License Numbers: DPR-1 (Docket Number 50-18); DR-10 (Docket Number 50-183); and TR-1 (Docket Number 50-70) Project stage: RAI 2018-05-21
[Table View] |
|
---|
Category:Letter type:M
MONTHYEARM220026, GE-Hitachi Nuclear Energy Americas, LLC - GEH Notification of GE Company Stock Beneficial Ownership Filings2022-02-11011 February 2022 GE-Hitachi Nuclear Energy Americas, LLC - GEH Notification of GE Company Stock Beneficial Ownership Filings M210154, GEH Notification of GE Company Stock Beneficial Ownership Filing2021-11-22022 November 2021 GEH Notification of GE Company Stock Beneficial Ownership Filing M210146, GEH - Description of Process for Decommissioning the Vallecitos Nuclear Center Shutdown Reactors2021-11-11011 November 2021 GEH - Description of Process for Decommissioning the Vallecitos Nuclear Center Shutdown Reactors M200167, Amended GEH Annual Shutdown Reactor Reports for the Year 20192020-12-16016 December 2020 Amended GEH Annual Shutdown Reactor Reports for the Year 2019 M200102, GEH - Response to NRC Request for Additional Information (Rai), March 16, 20202020-07-15015 July 2020 GEH - Response to NRC Request for Additional Information (Rai), March 16, 2020 M200062, GEH Request to Extend RAI Response Due Date to July 15, 20202020-04-14014 April 2020 GEH Request to Extend RAI Response Due Date to July 15, 2020 M200045, GE-Hitachi Nuclear Energy Americas, LLC - Transmittal of Annual Shutdown Reactor Reports for the Year 20192020-03-25025 March 2020 GE-Hitachi Nuclear Energy Americas, LLC - Transmittal of Annual Shutdown Reactor Reports for the Year 2019 M200039, GEH - Vallecitos Nuclear Center Getr Site Specific Cost Estimate and Decommissioning Funding Plan2020-03-0606 March 2020 GEH - Vallecitos Nuclear Center Getr Site Specific Cost Estimate and Decommissioning Funding Plan M190202, GEH - Third Reply to NRC Request for Information Needed for GE-Hitachi Exemption Request for Alternate Decommissioning Schedules2019-11-15015 November 2019 GEH - Third Reply to NRC Request for Information Needed for GE-Hitachi Exemption Request for Alternate Decommissioning Schedules M190146, GE Hitachi Nuclear Energy - License Amendment Request - Revision to Radiological Emergency Plan (REP) Public Supplement2019-08-23023 August 2019 GE Hitachi Nuclear Energy - License Amendment Request - Revision to Radiological Emergency Plan (REP) Public Supplement M190131, GE Hitachi Nuclear Energy License Amendment Request - Revision to Radiological Emergency Plan (REP) Public2019-07-17017 July 2019 GE Hitachi Nuclear Energy License Amendment Request - Revision to Radiological Emergency Plan (REP) Public M190065, GE-Hitachi Nuclear Energy Americas, LLC - Second Reply to NRC Request for Information Needed for GE-Hitachi Exemption Request for Alternate Decommissioning Schedules2019-03-28028 March 2019 GE-Hitachi Nuclear Energy Americas, LLC - Second Reply to NRC Request for Information Needed for GE-Hitachi Exemption Request for Alternate Decommissioning Schedules M190066, GE-Hitachi Nuclear Energy Americas, LLC - Annual Shutdown Reactor Reports for the Year 20182019-03-27027 March 2019 GE-Hitachi Nuclear Energy Americas, LLC - Annual Shutdown Reactor Reports for the Year 2018 M190044, GEH Response to NRC Request for Additional Information2019-02-26026 February 2019 GEH Response to NRC Request for Additional Information M180219, (Vnc) Organization Change2018-12-17017 December 2018 (Vnc) Organization Change M180214, GE-Hitachi Nuclear Energy - Unconditional Release of Route 84 Frontage Section of Vallecitos Nuclear Center (Vnc) Site2018-12-14014 December 2018 GE-Hitachi Nuclear Energy - Unconditional Release of Route 84 Frontage Section of Vallecitos Nuclear Center (Vnc) Site M180200, GE-Hitachi Nuclear Energy Americas, LLC - Response to NRC Request for Additional Information (RAI) Interim Status Report2018-10-23023 October 2018 GE-Hitachi Nuclear Energy Americas, LLC - Response to NRC Request for Additional Information (RAI) Interim Status Report M180115, GEH Response to NRC Request for Additional Information (RAI)2018-05-31031 May 2018 GEH Response to NRC Request for Additional Information (RAI) M180070, GEH Annual Shutdown Reactor Reports for the Year 20172018-03-29029 March 2018 GEH Annual Shutdown Reactor Reports for the Year 2017 M180064, GEH Response Plan for NRC Request for Additional Information2018-03-28028 March 2018 GEH Response Plan for NRC Request for Additional Information M180053, GEH/GNF-A Financial Assurance of Decommissioning Funds - Supplemental Information2018-03-19019 March 2018 GEH/GNF-A Financial Assurance of Decommissioning Funds - Supplemental Information M188002, GEH Request for Additional Time to Respond to NRC Request for Additional Information2018-02-0707 February 2018 GEH Request for Additional Time to Respond to NRC Request for Additional Information M170193, GE-Hitachi Nuclear Energy Americas, LLC - Submittal of Response to NRC Request for Additional Information2017-07-31031 July 2017 GE-Hitachi Nuclear Energy Americas, LLC - Submittal of Response to NRC Request for Additional Information M170158, GEH Request for Additional Time to Respond to NRC Request for Additional Information2017-06-21021 June 2017 GEH Request for Additional Time to Respond to NRC Request for Additional Information M170124, (Vnc) Organization Change2017-05-0909 May 2017 (Vnc) Organization Change 2022-02-11
[Table view] |
Text
GE Hitachi Nuclear Energy HITACHI Scott P. Murray Manager, Facility Licensing 3901 Castle Hayne Road P.O. Box 780 Security Related Information Notice Wilmington, NC 28402 The Attachment to this letter contains security related USA information which is to be withheld from public T (91 0) 819-5950 disclosure in accordance with 10CFR2.390 and scott.murray @ge.com RIS 2005-31 . The remainder of this letter can be made public upon removal of the Attachment.
M170193 July 31, 2017 Jack D. Parrott, Senior Project Manager Reactor Decommissioning Branch Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 ATTN: Document Control Desk
Subject:
GEH Response to NRC Request for Additional Information
References:
- 1) Letter, S. P. Murray to Director NMSS, GEH VNC Request for Alternate Decommissioning Schedules, 7/10/15
- 2) Letter, S. P. Murray to Director NMSS, GEH VNC Request for Alternate Decommissioning Schedules, Additional Information, 10/15/15
- 3) Letter, GEH Vallecitos Nuclear Center (VNC) Request for Alternate Decommissioning Schedules for DPR-1, DR-1 0 and TR-1 Licenses, Exemption Request, 7/15/16
- 4) Letter, J. D. Parrott (NRC) to S.P. Murray (GEH) Request for Additional Information, 5/16/17
- 5) Letter, S. P. Murray to J. D. Parrott GEH Request for Additional Time to Respond to NRC Request for Additional Information, 6/21/17
Dear Mr. Parrott:
Attached is GE Hitachi Nuclear Energy Americas LLC (GEH) response to your letter dated May 16, 2017 (Reference 4).
Please contact me if you have any questions or would like to discuss this matter further.
5 1';.1 Scott P. Mu~, Mana~
Facility Licensing J12
'JeV Commitments: None
Attachment:
GEH Response Dated 7/31/17 Cc: B. Watson, USNRC NMSS SPM 17-032