ML17208A836

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-335/80-07 on 800415-18.Noncompliance Noted:Disconnected Lead & Temporary Jumper Log Not Reviewed by Operations Superintendent Prior to Refueling & Response to Joint Util Mgt Audit Not Received within 30 Days
ML17208A836
Person / Time
Site: Saint Lucie NextEra Energy icon.png
Issue date: 05/15/1980
From: Belisle G, Ruhlman W, Upright C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML17208A832 List:
References
50-335-80-07-01, NUDOCS 8007220088
Download: ML17208A836 (27)


See also: IR 05000335/1980007

Text

~S REoy

0

Cp

0O

lO

0

Y.

~O

>>>>*<<+

Report No. 50-335/80-07

UNITEDSTATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTAST., N.W., SUITE 3100

ATLANTA,GEORGIA 30303

Licensee:

Florida Power and Light Company

9250 West Flagler Street

Miami, FL

33101

Facility:

St. Lucie

Docket No. 50-335

License.,No.

DPR-67

I

Inspection at St. Lucie site near Fo

Pierce, Florida

Inspectors:

~ A. Ruhlma

a

at

Signed

G. A. Belis

e

Approved by:

C.

M. Upright

ti

ection Chief,

RONS Branch

/

SUMMARY

Inspection

on April 15-18,

1980

AreasInspected'te

igned

f~

n

ate

igned

This routine,

announced

inspection involved 48 inspector-hours

in office and 57

inspector-hours

on site in the areas of QA/QC Administration;

QA Program Review;

Housekeeping

and Cleanliness

Program;

Organization

and Administration;

QA

Audits; Receipt Storage

and Handling of Equipment

and Material; Offsi'te Support

Staff; Design, Design Changes

and Modifications; Design Changes

and Modifications

Program;

Test and Experiments

Program;

Maintenance;

and Personnel Qualification

Program.

Results

Of the twelve areas

inspected,

no items of noncompliance

or deviations

were

identified in ten areas;

two apparent

items of noncompliance

were found in two

areas

(Infraction, failure to'follow procedure,

Paragraph

14.c; Deficiency,

failure to follow procedures,

Paragraph 9.c.)

0VO2

2OOPP

j

q+~~l+ V

4

DETAIIS

Persons

Contacted

Licensee

Employees

""A. Bailey,

QA Supervisor

-J. Barrows,

QC Operations

Superintendent

+J. Bowers,

Maintenance

Supervisor

+R.-'Englmeier,

QA Assistant

Manager

-T...Essinger,

QA Assistant

Manager

T;~ Grozan, Licensing Engineer-Nuclear

Licensing

"R. Jennings,

Technical Supervisor

>D. Oliver, Stores

Supervisor

+N. Roos,

QC Inspector

+A. Siebe,

QA Assistant

Manager

-R. Spooner,

QA Supervisor

-J. Vaux,

QC Supervisor

-J. Vessely,

QA Director

-J. Walls,

QC Inspector

+N. Weems,

QA Assistant

Manager Construction

-C. Wethy, Plant Manager

Other licensee

employees

contacted

included

17 engineering personnel,

3

purchasing personnel,

2 operators

and

3 office personnel.

-Attended exit interview

Exit Interview

The inspection

scope

and findings were summarized

on April 15,

1980 at

Florida Power and Light, corporate offices in Miami, Florida and

on April 18,

1980 at the St.

Iucie site with those persons

indicated in paragraph

1

above.

At the St.

Lucie site exit the licensee

was informed that inspector

identified items 335/79-21-07,08

and 09 would be closed.

The licensee

was

also informed of the two items of noncompliance

(Paragraphs

9.c.

and 14.c.)

and five unresolved

items

(Paragraphs

5.a., 7.a., 7.b.,

10.c.

and 13.d.)

due to the inspectors'indings.

The licensee

acknowledged

the

inspectors'indings.

Licensee Action on Previous Inspection Findings

~

(Closed) Unresolved

Item (335/79-21-02)

Revise

QI 16-PR-PSL-1

and QI

18-PR/PSL-2 to procedural

requirement practices that were currently being

carried out to fulfillregulatory items.

QI 16-PR/PSL-3,gas

revised

and

approved

on September

27,

1979 so that item 4.1.4 now formalizes the

process for escalation of items which are not resolved'-'at

a ..lower level.

QI 18-PR/PSI-2

was also revised

and approved

on September

27,

1979 so that

item 5.2.1 is now expanded

to specify the

QC Supervisor's jurisdiction in

the area of material handling,

storage

and shipping.

This item is

resolved.

4.

Unresolved

Items

Unresolved items are matters

about which more information is required to

determine whether they are acceptable

or may involve noncompliance

or

deviations.

New unresolved

items identified during this inspection are

discussed in Paragraphs

5., 7.a., 7.b., 10.c.,

and 13.d.

~

5.

Quality Assurance/Quality

Control Administration

In the previous review of this area

(August 1979, Report 50-335/79-11)

two

attributes of this program area

could not be reviewed since they were

corporate office functions.

These

two areas

were tracked

as items 335/79-

11-08 (verification of establishment

of responsibilities

and methods to

assure

review of overall effectiveness

of the

QA Program)

and 335/79-11-09

(Verification that methods exist and that actions

are taken to modify the

QA Program to provide additional emphasis in "identified problem areas").

These

items were reviewed at the corporate offices during this inspection

with the following results.

The program used

a Joint UtilityManagement Audit (JUMA) where personnel

from other utilities come in and perform a management

audit as the method

for reviewing the overall effectiveness

of the

QA Program.

In addition,

regular management briefings are held in which the outstanding audit

findings are reviewed.

These methods, collectively, meet the requirements

of the accepted

QA Program,

a'nd item 335/79-11-08 is closed.

Finding I of the

JUMA report documented

a tendency to address

only the

QA

findings, and not their cause.

This apparent

weakness

was also supported

by an apparent

trend of increased

findings.

This would indicate that the

Program

had not been modified to provide the required additional emphasis

ih identified problem areas.

However, although responses

to this finding

had been received,

a proposed corrective action statement

had not been

formulated.

Since the inadequacy

had been identified by the licensee's

internal audit system,

no citation is issued.

However, until the licensee's

corrective action has been formulated and reviewed for adequacy

by NRC,

this item (335/80-07-01) is unresolved.

With the opening of this item, the

- previous inspector followup item (335/79-21-09) is closed.

6.

Quality Assurance

Program Review

C

References:

(a)

Letter, R. E. Uhrig to R.

W. Ried, serial L-80-46,

dated February 6,

1980

(b)

(c)

QI 16-PR/PSL-1,

"Corrective Action",.~Revision 5

approved 9/27/79

QI 18-PR/PSL-2,

"Quality Control Surveillances",

Revision 6'approved

9/27/79

"3"

Reference

(a)

was issued to place St. Iucie Unit

1 under the accepted

Florida Power and Light Company Topical Quality Assurance. Report

(FPLTQAR

or TQAR).

References

(b) and (c) were reviewed to ascertain that previously

unresolved

item 335/79-21-02

concerns

had been incorporated into the

revisions;

these

are detailed in Paragraph

3 of this report.

Other portions of the Quality Assurance

Program had been .revised in various

implementing procedures.

Where these procedures

were reviewed

as part of

other inspection activities, they are identified in the. appropriate detail

paragraphs.

lg

No items of noncompliance or deviations

were identified.

7.

Housekeeping

and Cleanliness

Program

References:

(a)

QI 10-PR/PSI-5,

"Technical Specification Surveillance

Inspection of Reactor Building", Revision

1 dated 2/80

(b)

QI 13-PR/PSL-2,

"Cleanliness

Control Methods",

Revision

3 dated 3/80

a.

Program Review

Two separate

reviews were conducted.

Since the

TQAR contains

a

commitment (Appendix C) to comply with ANSI N45.2.3 - 1973 as modified

and endorsed

by Regulatory Guide 1.39 date 3/16/73,

reference

(b),

was

reviewed with respect to the

TQAR as supplemented

by the standard.

Within that framework, administrative controls for general plant

housekeeping

were reviewed to assure:

housekeeping

zones

had been

established;

control of housekeeping

during work activities was

specified which included return of excess

equipment to a storage

area

and prompt removal of combustible material

and debris.

A separate

review of cleanliness

controls

was conducted to verify establishment

of:

cleaning requirements for safety-related

components;

cleanliness,

cleanliness

classifications;

material accountability

and control when

appropriate;

and,

requirements. for cleaning o'f primary system

components,

including maintenance

and cleanliness

of previously cleaned

systems,

during rework, replacement,

or repair.

During the review the inspector

found that the current program does

not follow the TQAR's commitment to ANSI N45.2.3 in that no zones

are

used

as specified in paragraph

2.1 of the standard.

The licensee is

currently in the process of taking exceptions

to or 'providing alterna-

tive approaches

or incorporating into existing procedures

various

aspects

of the standards

listed in Appendix

C of the 7(AR.

This

process

was in progress prior to this inspection

and those items which

will require

NRR approval are or will be included in Revision 3 of the

TQAR. Since this specific" issue

was part of that ongoing 'process

and

has not been closed by NRR action based

on the licensee's

submittal as

-4-

of the end of the inspection, this item (335/80-07-02) will be unre-

solved until after issuance

of the approved Revision

3 of the

TQAR.

Several other items identified during this inspection have this

same

status,

and have therefore,

been assigned

the

same item number for

tracking purposes.

These

items are discussed

in paragraphs

8,

9d and

10d of this report.

b.

Implementation

For implementation of housekeeping

and the routine cleanliness

require-

ments,

the licensee relies

on training of personnel

as

opposed to

detailed procedures.

As such,

housekeeping

and cleanliness

requirements

are not routinely delineated in work procedures.

To verify the adequacy

of this approach,

the inspector interviewed

one electrician

and one

special

crew maintenance

mechanic to determine their understanding

of

the requirements.

No items of noncompliance or deviations

were identi-

fied.

0

'hen cleanliness

requirements

are necessary

beyond the "routine"

level, the inspector

found that in all six cases

reviewed the

QC

Engineer

had attached

the appropriate

section(s)

of reference

(b) to

the Plant Work Order

(PWO).

However, the inspector

was unable to find

any written requirement to perform this function to assure that it

would be continued if a different

QC Engineer performed the

PWO review.

Administrative Procedure

0010432, "Plant Work Order", Revision 14,

dated 9/27/79,

contains

a requirement

(Paragraph

8.3.2) for the

QC

review of PWO's, but no specific requirement relative to specification

of cleanliness

levels is delineated.

As stated, all cases

reviewed

indicated that the licensee's

current practices

are acceptable,

there-

fore, no citation is issued for an inadequate

procedure

because

the

licensee

stated that the procedure

would be revised to reflect current

practices.

Until the stipulated revision has been

made

and reviewed

by NRC, this item (335/80-07-03) is unresolved.

8.

Organization

and Administration

Reference:

Letter, R. E. Uhrig to

W. P. Haass, serial I-79-337 dated

December

7,

1979

. The referenced letter notified the Quality Assurance

Branch of two

organizational

changes.

The first consisted of reorganizing the

QA

Department

so that there were four Assistant

Managers

instead of the

original five.

The inspector found that one manager

had been transferred

and that his functional area

had been absorbed

by an existing Assistant

Manager;

thus,

no new personnel

or different qualification requirements

were required or inspected.

The other change

involved shifting the reporting path of the Site Construction

Manager from the current position of Director of Construction to the Project

General

Manager.

The inspector held discussions

with the Director'f

Project Management (to whom the Project General

Manager reports) to ascertain

if any dilution of authority or discounting of the problem resolution

capability had been'ntended

or had occurred.

Based

on these discussions,

no adverse

impact on the

QA Program

was evident.

The referenced letter

states that these organizational

changes will be included in the final

submittal of Revision

3 of the FPLTQAR. As with the other items in this

report which can not be evaluated for adequacy until Revision

3 of the

FPLTQAR has

been

approved by NRR, this item is included as

a part of the

unresolved

item identified in paragraphs

7a,

9d and

10d of this report

which is designated

335/80-07-02.

9.

Quality Assurance

Audits

References:

(a)

QP-16.1,

"Corrective Action", Revision

2 dated

10/79

(b)

QP-18.1,

"Conduct of Quality Assurance

Department

Quality Audits", Revision

3 dated

1/80

(c)

QP-18.2,

"Scheduling of Quality Assurance

Department

Audit Activities", Revision

7 dated 3/79

a.

Program Review

The referenced

documents

were reviewed with respect to the requirements

of the FPLTQAR. Specific items reviewed included:

qualifications,

training and independence

of audit personnel;

programatic

requirements

and methods for assuring corrective actions,

issuance

of audit reports,

and determining

when reaudits

are necessary;

provisions for periodic

review of the audit program to determine status

and adequacy;

and,

criteria for and preparation of long range audit plans

and schedules.

The inspector also verified that the audited organization is required

to respond to audit findings, in writing, and that audit checklists or

procedures

are required for the audits.

Distribution requirements

were also reviewed.

As a result, of this review, an additional aspect

of an unresolved

item was identified and two areas

were found which

will be referred to NRR for consideration

during the review of Revision

3

of the FPLTQAR.

These

items are discussed

in paragraphs

d and

e

below.

b.

Implementation

The inspector reviewed audits at the Company offices

(QAE audits)

and

at the St.

Lucie site

(QAO audits).

The specific items evaluated

during the Program Review above were inspected for implementation.

The audits

reviewed were:

QAE-CNRB-80-1 conducted

between 2/13/80.,and

2/gOJ80

i

~ r~P,>

QAE-QAD-80-1 conducted

between 2/11/80 and 2/15/80.,

QAO-PSL-79-.09-174 conducted

between

10/12/79

and 11/9/79

QAO-PSL-80-02-182

conducted

between 2/19/80 and 3/3/80

QAO-PSL-80-02-184

conducted

between 3/3/80

and 4/2/80

QAO-PSL-80-004 conducted

between ll/26/79 and 1/29/80

One item of noncompliance

was identified as discussed

in paragraph

c

below.

Failure to Follow Procedures

- Audit Response

The Joint UtilityManagement Audit (JUMA), QAE-QAD-80-1, was conducted

February

11-15,

1980.

Letter QAD-80-013 made the distribution of the

JUMA report to those individuals responsible for answering

one or more

of the three findings on February 20,

1980.

When the inspector

reviewed

this audit at the Corporate Offices on April 15,

1980, the response

to

Finding N3 had not been received.

This is contrary to the

FPLTQAR and

procedure

QP-18.1 which require

a response

within 30 calendar

days.

Paragraphs

5.4.3

and 5.4.4 of QP-16.1 specify

a series of actions to

be taken if a required response

is inadequate

or not received in the

specified time; these actions

were not carried out.

These failures to

follow procedures,

collectively, constitute

an item of noncompliance

(335/80-07-04).

When the licensee

was informed of this item, the responsible

organiza-

tion wrote the required

response

and it was provided to the inspector

prior to leaving for the site on April 15,

1980.

d.

Exception to ANSI N45.2.12

QP-18.1,

Paragraph

5.2, item 1, states

that onsite activity audits

conducted

by the construction

and operating plant groups

may omit the

pre-audit conference.

Paragraph

4.3.1 of ANSI N45.2.12

makes this

conference

manditory for all audits.

The licensee's

proposed Revision

3 to the FPITQAR takes

an exception to this requirement of the standard.

This item is combined with similar items discussed in paragraphs

7a,

8

and

10d of this report which will be evaluated after Revision 3 of the

FPLTQAR is accepted

by NRR.

This collective unresolved

item is desig-

nated 335/80-07-02.

e.

Item Referred to NRC Management for Review

The licensee's

procedure,

QP-18.1,

described,two

typm of audits;

management

audits

and activity audits.

Section 5.5 oMithat procedure

addresses

distribution of these audits by stating the management

audits shall be distributed to "appropriate

management

personnel

within the Company"; activity audits are to be distributed, at a.

minimum, to "the responsible

supervisor of the audited organization".

In all cases

reviewed,

the licensee

had made what the inspector

determined

was appropriate distribution.

However, in the absence

of

any more speci'fi'c criteria or a definitive distribution system,

the

inspector could not assure

himself that all audit reports

would be

distributed to appropriate

personnel.

Personnel

responsible for

determining distribution were interviewed.

One person stated that he

made distribution based

on past audit reports

and to anyone else

who

had indicated that he wanted

a copy.

ANSI N45.2.12,

the standard

followed by the FPLTQAR in this area,

states

(Section 4.4.6) that

distribution of the report shall include responsible

management

of

both the audited

and auditing organizations.

The current

QA program does not make use of reaudits,

as such; correc-

tive actions

are closed out, but no overall reaudit is conducted until

the area is again scheduled

as part of the routine program.

The ANSI

standard

addresses

this issue

by stating

(Paragraph

4.5.2) that followup

action may be accomplished

through written communication,

reaudit, or

.

other appropriate

means.

The inspector discussed

with the licensee

the possibility, especially

when several

items are found during the

audit of an area, that while individual corrective actions

could be

appropriate,

the combination of corrective actions

could produce

another problem.

Thus, in some cases,

a reaudit of the area

would be

necessary

to truly assess

the adequacy of the corrective action.

In both of the areas

mentioned

above,

the words in 10 CFR 50, Appendix

B, Criterion KVIII are

no more specific than the words in the ANSI

Standard

N45.2.12.

The licensee's

TQAR is currently under review by

NRR. These

two issues will be forwarded to NRC management for evaluation.

For tracking purposes

only since

no licensee action is required,

these

issues

are assigned

item 335/80-07-05.

10.

Receipt,

Storage

and Handling of Equipment

and Material

References:

(a)

QI 7-PR/PSL-1,'"Control of Purchased

Material, Equipment

and Services," Revision 4, dated 3/80

(b)

QI 7<<PR/PSL-2,

"Receiving Inspection", Revision

6

approved

2/80

(c)

QI 8-PR/PSL-l, "Identification and Control of Material,

Parts

and Components",

Revision

2 dated

2/79

(d)

QI 13-PR/PSL-l,

"Handling, Storage

and Shipping",

Revision 5 dated 3/80

(e)

QI 7-S-l, "Control of Purchased

Mater'.al", Revision

4

dated 3/79

~ c ~also selected

reviewed to determine that proper controls were in place:

Nuclear Steam Supply, System Diaphram,

MNS8 574-.3764

-9-

Unit jjl Containment Airlock Gasket,

MNS// 082-107

PT Developer,

MNSN 711-097

There is

a nearby warehouse

where large items are stored.

The inspector

selected

the following two items

and verified that these

items were

given the

same controls

as those received at the main warehouse:

10" safety-relief valve,

PO 21540-06461,

Item 30,

MNS// 572-1880

1/4" stainless

steel pipe,

schedule

40,

PO 67204-34353,

MNSN

561"636

As

a result of the above review and the tour of the warehouse,

one

unresolved

item, an additional aspect of another unresolved

item, and

an item to be referred to NRR for evaluation were identified,

These

items are discussed in paragraphs

c, d,

and

e below.

Small Water Leak in Warehouse

QI 13-S-1, paragraph

5.2.1B requires that the warehouse

be weathertight.

The storage levels specified in other procedures

dictate that water

leakage into the warehouse is not acceptable.

During the tour of the

main warehouse,

the inspector noted

a small (approximately three

square

inches)

puddle of water on the floor between

two racks of

material; it had not rained at the site for three days.

The licensee

initiated action to have the leak in the roof reviewed

and to make

necessar'y provision for repair.

Since the size of the leak was very small,

and since

no material in

storage

was or could be affected by the leak,

no citation is appropriate.

However, until the required repairs

have been effected

and reviewed,

this item (335/80-07-06) is unresolved.

Exceptions to ANSI N45.2.2

During the program review, the inspector noted several

areas

where the

current procedures

do not meet the FPLTQAR's commitment to ANSI N45.2.2.

As before,

the licensee

was aware of these differences

and was in the

process of including exceptions,

alternative

approaches,

or current

program modifications.

During the implementation review,

a requirement

of a current procedure

was not yet in place

((Paragraph

5.2.1 or QI

7-S-1); this was

a program to control limited shelf life items.

Again, the development

and implementation of this program is dependent

on the conditions

imposed by Revision

3 of the FPLTQAR. These items,

collectively, are combined with the other aspects

of..-t)e program which

can not be evaluated until Revision

3 of the

FPLTQAR x.s accepted

by

NRR. The item is designated

335/80-07-02

and other 'aspects

are addressed

in paragraphs

7a,

8 and 9d of this report.

Although the list below is

not all inclusive, the inspector noted the following specific'ifferences

between the current program and the current

FPLTQAR commitments;

"10-

Paragraph

2.2 of the standard

requires procedures

to contain

sufficient detail to provide for the listed items

a basis for

receiving in accordance

with the standard.

There .was no check-

list provided for the "shipping damage inspection" of paragraph

5.2.1

(performed by Stores personnel),

and the

4 line entry for

acceptance

criteria on the

gC Inspector's

checklist does not

cover the

16 specific line items of paragraph 5.2.2 of the standard.

Personnel

interviewed could not detail the specific requirements

of the standard

from memory.

While a copy of the standard

was

available in the receiving area,

personnel

interviewed stated

that the copy was not used while performing the inspection.

Paragraph

5.2.1 of the standard

requires

the completion of the

"shipping damage inspection"

PRIOR to unloading;

the licensee's

procedures

specify that the inspection is to be performed

AFTER

unloading.

Paragraph

5.6 and others of the standard

require packages

to be

marked in accordance

with the very specific requirements

of

Appendix A 3.9; these

requirements

are not currently met or

inspected.

Paragraph

6.4.2(6) of the standard

requires

the meggering of

rotating equipment in storage

on a periodic basis;

no program

currently exists to perform this function.

Paragraph

6.4.2(7) of the standard

requires

the rotating of the

shafts of all rotating equipment in storage; this is not currently

being accomplished.

Paragraph

7.4 of the standard

specifies

a hoisting equipment

qualification and certification program;

the licensee is taking

exceptions

to some specific requirements in this section based

on

a previous inspection at the Turkey Point facility (50-250/79-11;

50-251/79-11).

The equipment classification requirements

of paragraph

2.7 of the

standard

are not currently in use.

Paragraph

2.4 of the standard

requires that ALL personnel

performing

inspections

be qualified/certified in accordance

with ANSI N45.2.6;

currently the Stores personnel

who perform the "shipping damage

inspection" are not meeting this requirement.

The inspector did not find any cases

where the

absentee

of the above

items adversely affected the ability of the hquipmen~q perform its

safety-related

function.

While the lack of a program For controlling

items with a limited shelf life had such

a potential,

no items had

currently been stored for a length of time where deterioration would

be expected to begin.

While rotation and meggering were not performed

in storage,

these

items are

checked during and after installation;

-11-

this could adversely affect unit reliability, but not safety.

The

inspector also stated that he had

NOT performed

a detailed line-by-line

review of the standards

involved; this review was part of the licensee's

ongoing "baseline

document" review.

e.

Item Referred to NRC Management for Evaluation

In reviewing stored items,

the inspector noted that safety-related

components

are not identified as such.

The only differentiation is

based

on the designation

"QC Required",

"Receiving Inspection Required",

and "No Substitution Allowed".

Such items

as the Pressurizer

Manway

Gasket,

the Unit 1 Containment Airlock Gasket,

various valves,

breakers

and pumps which are safety-related

are ordered

as

"No QC Required"

based

on the fact that,

under the licensee's

program,

they are

"Commer-

cial Grade".

While no specific inadequacy

was noted during the inspec-

tion, copies of the licensee's

implementing procedures will be forwarded

to NRC Headquarters

for possible

review in conjunction with the

current

NRR evaluation of the

FPLTQAR Revision 3.

Since

no specific

action is required or requested

from the licensee,

this item is desig-

nated

as

an inspector followup item and is assigned

the number 335/80-

07-07 for tracking purposes

only.

ll.

Quality Control Surveillances

References:

(a)

QI 18-PR/PSL-2,

"Quality Control Surveillances,"

Revision

6 dated

10/79

(b)

QI 18"PR/PSL-3, "Quality Control Monitoring", Revision

2 dated

6/79

One of the Quality Assurance audit functions involves verification of

adequate

QC coverage of significant site activites.

The inspector

reviewed

fifty QC Surveillance reports

taken from a period between

September

19,

1979 and February 28,

1980.

These surveillances

covered various site

activities including maintenance,

operations,

receiving inspection

and

monitoring of work activities.

No items of noncompliance

or deviations

were identified,

12.

Offsite Support Staff

References:

(a)

EPP QI 1.2

QA Program Delegation to Participating

Organizations

by Power Plant Engineering,

Revision 0,

Dated 4/ll/77

(b)

EPP QI 2.2

QA Indoctrination and Training, Revision 1,

Dated 3/17/80.

(c)

EPP QI 2.3 Classification of Activities,"'Structures,

Systems

and Components,

Revision 0, Dated 3/7/80.

-12-

(d), EPP QI 2.3B, Classification of Structures,

Systems

and

Components,

St.

Lucie Plant, Revision 0, Dated 3/7/80.

(e)

EPP QI 3.1, Control of EPP Design, Revision 2, Dated

10/19/72.

(f)

(g)

EPP QI 3.2, Identification and Control of Design

Interfaces-EPP

Design, Revision 0, Dated 4/7/78.

EPP QI 3.3, Plant Changes/Modifications,

Revision 1,

Dated 3/19/79.

(h)

EPP QI 3.4, Control of Field Design Changes,

Revision

0, Dated 4/25/78

EPP

AP 2.3, Workload Planning

and Management,

Revision

0, Dated 6/15/78

FPL QA ASL, Quality Assurance

Department

Approved

Suppliers List Dated 4/1/80.

(k)

QI PUR l-l, Instructions for Implementating the

Purchasing

Department

(Operating Plants) Quality

Assurance

Program, Revision 3, Dated 1/10/79.

(m)

QI PUR 2-1, Instructions for Indoctrinating, Training,

and Qualifying Purchasing

Personnel

(Operating Plants)

for Nuclear Procurement,

Revision 3, Dated 1/10/79.

QI PUR 4-1, Instructions for Processing

and Routing of

Procurement

Documents for Spare Parts

and Replacement

Items Revision 5, dated 8/21/78.

(n)

QI PUR 6-1, Document Control, Revision 3, dated 8/21/78.

(o)

QI PUR 17-1, Instructions for Storage

and Maintenance

of Purchase

Orders

and Related Documentation,

Revision 0,

'Dated 2/7/80.

(p)

FPL QAM, Quality Assurance

Manual

QP 18.1,

Conduct of Quality Assurance

Department Quality

Audits Revision 3, Dated 1/10/80.

Program Review

r

CI'

-~g~$

~

The Referenced

documents

were reviewed to verify that, the licensee

established

administrative controls to describe the'esponsibilities,

authority and lines of communications available for personnel

who

perform the following offsite support functions:

(1)

Design

-13"

(2)

Technical Support

r

(3)

Quality Assurance

(4)

Procurement

(5)

Construction

(6)

Interface

Between onsite

and Offsite Functions

.

Additionally, the inspector verified that the procedures

are in conformance

with the requirements

of 10 CFR 50, Appendix B and the licensee's

approved

QA Program.

b.

Implementation

The inspector interviewed

one manager,

one group leader

and one staff

member in the diciplines mentioned,

where possible,

and verified they

understood their responsibilities

and authorities

and that they were

qualified for their related work.

The inspector

reviewed the results of two QA audits;

QAS-EPP-79-2

and

QAP-PUR-79.1

and ascertained

that corrective action for identified

deficiencies

had been

completed in a satisfactory

manner.

No items of noncompliance

or deficiency were identified.

~

~

13.

Design, Design

Changes

and Modifications

References:

(a)

EPP QI 3.1, Control of EPP Design, Revision 2, Dated

10/19/72.

(b)

EPP QI 3.2, Identification and Control of Design Inter-

faces-EPP

Design, Revision 0, Dated 4/7/78.

(c)

EPP QI 3.3, Plant Changes/Modifications,

Revision 1,

Dated 3/19/79.

I-

4

(d)

EPP QI 3.4, Control of Field Design Changes,

Revision

0, Dated 4/7/78.

(e)

QP 3.1, Evaluation of Contractor Design, Revision 2,

Dated 4/28/78.

(f)

QP 3.2, Identification of Control Design Interfaces,

Revision 1, Dated 6/6/79.

II

(g)

OP 3.4, Plant

Changes

and Modifications, for Operating

Plants, Revision 2, Dated 8/14/78.

-14-

(h)

gP 3.6, Control of FPL Originated Design, Revision

2

Dated 9/28/79.

'I

(i)

(}P 6.6,

FPL Drawing Control, Revision 1, Dated 8/6/79

(j)

T(}R 3.0, Design Control, Revision 1, Dated 8/15/76

a.

Program Review

The referenced

documents

were reviewed with respect

to the licensees

accepted

QA Program

and ANSI N45.2.11,

1974,

as committed to by that

program.

The inspection verified that design

changes

were reviewed in

accordance

with the Technical Specifications

and the Established

gA

Program;

that design

changes

were conducted in accordance

with approved

written procedures;

that acceptance

test records

were reviewed and

approved; that operating procedures

and modifications were made

and

approved; that installation procedures

were adequate for the identified

function; that drawings were changed to reflect the modifications;

that records

were maintained

as required

and that installation of the

modification was

as described in the design

change

package.

b..

Implementation

The inspector

reviewed the design

changes

and modification area

and

verified that design

changes

and modifications are in conformance with

the requirements

of the Technical Specifications

and

10 CFR 50.59.

Eleven safety-related plant changes/modification

packages

were reviewed.

The specific items reviewed were:

(1)

PC/M 150-76, Ioss of Diesel Generator

Control Power Annunciator.

(2)

PC/M 335-78, Replace

Selected Hydraulic Restraints with Mechanical

Seismic Restraints

(3)

PC/M 454-78,

Charging

Pump Discharge Pulsation

Damper Phase l.

(4)

PC/M 485/78,

Steam Generator Modifications Rim Cut

(5)

PC/M 512-78, Install Hour Meters

on Charging

Pump Breakers

(6)

PC/M 521-79,

Add Union to Auxiliary Feed

Pump Turbine Bearing

Cooling Water Lines.

(7)

PC/M 535-79

7

Clip.

(8)

PC/M 550-79,

Steam Generator Primary Mainway Gasket Retainer

~ f

~W~

~~p

~

CEA Guide Tube Modification

(9)

PC/M 569/79, Autoinitiation of ESFAS "CIS" Upon Actuation of

"SIAS".

-15-

(10)

PC/M 411-78,

Containment Cooler Relief Valve Flanges

(ll)

PC/M 293-77,

Temporary Test Connections for Charging System.

As

a result of the review the inspector identified one unresolved

item

as discussed

in Paragraph

c. below.

c.

Incomplete Documentation

In reviewing PC/M 485-78 the inspector noticed that the procedures

for

completion of the work by the contractor required certain steps

to be

witnessed

and signed off.

Upon termination of the work these

completed

records

were taken by the contractor.

The licensee verified by a

telephone

conversation to the contractor

on 4/17/80 that the records

were available in the contractor

home office and copies

would be sent

to the licensee within 10 working days of the telephone

conversation.

Until these

records

can be reviewed this item is unresolved

(335/80-

07-08).

14.

Design Changes

and Modifications Program

References:

(a)

QI3PR/PSC-l,

Design Control After Fuel Ioad, Revision 5,

Dated 10/79.

(b)

QP 3.4 Plant

Changes

and Modifications for Operating

Plants,

Revision 2, Dated 8/14/78.

(c)

AP 0010124 Control and Use of Jumpers

and Disconnected

Leads in Safety Related

Systems,

Revision 5, Dated

3/2/79.

a

~

Program Review

The referenced

documents

were reviewed with respect to the licensee's

accepted

QA Program

and the requirements

of 10 CFR 50.59

and ANSI

45.2.11Property "ANSI code" (as page type) with input value "ANSI</br></br>45.2.11" contains invalid characters or is incomplete and therefore can cause unexpected results during a query or annotation process.,

1874,

as committed to by that program.

The inspection

was to

verify that procedures

had been established

for control of design

and

modification change requests;

that procedures

and responsibilities for

design control have been established;

that administrative controls for

design document control have been established;

that responsibility

had been established

in writing to assure

necessary

implementation;

that administrative controls

and responsibilities

have been established

to assure that design

changes

and modification are incorporated into

plant procedures,

operator training and the updating of plant drawings

in a timely manner; that controls have been developed

which define

changes

of communication between design organizations

and responsible

individuals; that administrative controls r'equire

rec'deeds

of design

documentation

and review be collected

and transmitted for storage;

that design

changes

be accomplished in accordance

with approved

procedures;

that controls require post modification acceptan'ce

testing be performed

and results

approved; that responsibility has

been assigned <or identifying post modification testing requirements

and acceptance

criteria;

and that responsibility and methods for

reporting design

changes

and modifications to the

NRC in accordance

with 10 CFR 50.59 have been assigned.

The conclusion with respect to

the acceptability of this area is given in Paragraph

b.

P'

~

Temporary modifications

(Use of jumpers

and disconnected

leads in

safety related

systems)

were reviewed to assure that controls require

the review and approval of temporary modifications in accordance

with

the Technical Specifications

and

10 CFR 50.59; thai controls require

the use of approved procedures;

that controls require records

be

maintained of status of jumpers

and disconnected

leads; that controls

require functional testing of equipment following removal of temporary

modifications;

and that controls require periodic reviews of records

of jumpers

and disconnected

leads including a check of outstanding

entries.

Conclusions with respect to the acceptability of this area

are given in Paragraph

b.

Implementation

The licensee

program for design

changes

and modifications

was reviewed

at St.

Lucie site.

The program had previously been inspected

during

the

QA inspection in March,

1979 at Florida Power and Light corporate

offices.

This inspection is documented in IE Inspection Report 50-250,

50-251/79-11.

During this review the inspector identified one item of

noncompliance

as discussed

in Paragraph

c

c.

Failure to Follow Procedure

The Technical Specifications, Section 6.8.1, states in part that

written procedures

shall be established,

implemented

and maintained.

AP 0010124 Control and Use of Jumpers

and Disconnected

Leads in Safety-

Related

Systems

Section 5.4, requires in part that the

IRC Supervisor

and the Assistant Superintendent Electrical Maintenance,

are responsible

for reviewing, with the Operations

Supervisor,

the disconnected

lead

and temporary jumper log prior to each refueling.

Contrary to the above,

the IRC Supervisor

and the Assistant Superin-

tendent Electrical Maintenance

and the Operations

Superintendent

did

not review the Disconnected

Lead and Temporary Jumper Iog prior to the

refueling that

commenced

March 15,

1980.

This failure to follow

procedure constitutes

an item of noncompliance

(335/80-07-09).

15.

Test and Experiments

Program

References:

(a)

TQR 11, Test Controls, Revision 0, dat'el '1/23/76.

e

(b)

QP 11.1, Test Control Construction,

Revision 1, dated

8/15/75.

'

-17-

(c)

QP 11.2, Test Control-Operation,

Revision 0, dated

9/15/74.

(d)

QP 11.3, Test Control - Pre-Operational

and Startup

Test, Revision 0, dated 9/1/74

(e)

gP 11.4, Test Control Program, Revision 1, dated

8/16/76.

ac

Program Review

The inspector verified that

a formal method has

been established

to

handle requests

or proposals for conducting plant tests

and experi-

ments involving safety related

components,

systems

or structures;

that

provisions

have been

made to assure test and experiments will be

performed in accordance

with approved written procedures,

that respon-

sibilities have been assigned for reviewing and approving test

and

experimental procedures;

that a system,

including assignment

of

responsibility,

had been established

to assure that all proposed tests

and experiments will be reviewed to determine whether they are described

in the FSAR and that responsibilities

have been assigned

to assure

that safety evaluations

as required by 10 CFR 50.59 will be developed

to assure that it does not involve an unresolved safety question or a

change in the Technical Specifications.

Implementation

The licensees

program for test

and experiments

was reviewed at the

St. Iucie site with respect to the referenced

documents.

One test

performed in 1977,

Charging System Pulsation

and Vibration Testing,

was reviewed.

No items of noncompliance or deficiency were identified.

16.

Maintenance

The references

and program review for this area are identified in IE Inspec-

tion Report 50-335/79-21,

paragraph

9.

The inspector reviewed the circum-

stances

associated

with the following maintenance activities on safety

related

equipment to determine if the reporting requirements

of the Technical

Specifications

were adhered to:

PWO 2941, Fuel Handling Building Ventilation

PWO 2963, Replace

Gasket in FCB-23-5

PWO 2863, Inspect "C" CCW Pump

PWO 2902, Replace

"B" Charging

Pump Stuffing Box

/

-.18"

PRO 2940, Replace

Gasket in FCV 23-6.

PRO 2942, Fuel Oil Ieak in "B" Diesel Generator

PRO 2934,

Repack "A" Charging

Pump

No items of noncompliance

or deviation were identified.

17.

Personnel Qualification Program

The references

and program preview for this activity are given in IE

Inspection Report 335/79-21,

paragraph

6.

The inspector

reviewed the

permanent

and alternate

membership of the

Company Nuclear Review Board and

verified that their qualifications were in accordance

with established

requirements.

As a result of this review, inspector followup item

335/79-21"07 is closed.