Ack Receipt of 791121 & 1220 Ltrs Informing NRC of Steps Taken to Correct Violation Noted in IE Insp Rept 50-389/79-18
ML17207A862
Person / Time
Site: Saint Lucie NextEra Energy icon.png
Issue date: 02/21/1980
From: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Robert E. Uhrig
FLORIDA POWER & LIGHT CO.
Shared Package
ML17207A863 List:
References
NUDOCS 8003060467
Download: ML17207A862 (3)


See also: IR 05000389/1979018

Text

~S RKQ0

1$

~o

+rp

gO

++*++

In Reply Refer To:

RIX:JG

50-389/ 9-1

UNITEDSTATES

NUCLEAR REGULATORYCOMMISSION

REGION II

101 MARIETTAST., N.W., SUITE 3100

ATLANTA,GEORGIA 30303

FEB 21 1980

~-sp'lorida

Power and Light Company

Attn:

R. E. Uhrig, Vice President

Advanced

Systems

and Technology

Post Office Box 529100

Miami, FL

33152

Gentlemen:

Thank you for your letters of November 21,

1979,

and December

20,

1979, informing

us of the steps

you have taken to correct the items of noncompliance

concerning

activities under

NRC Construction Permit No.

CPPR-144 brought to your attention

in our letter of November 5,

1979.

In your November

21 letter you requested

reconsideration

of the noncompliance

dealing with failure to follow procedures

in purchase of safety-related

Service

Level I protective coating materials

(Part

A of Appendix A to letter RII:JJL

50-389/79-18).

This request

was based

on discovery of documentation after com-

pletion of the inspection which indicates that the protective coating materials

were purchased

as safety-related

as required by Procedure

ASP-8.

This noncompliance

was discussed

at length by the inspector with site personnel

during the inspection.

The inspector

emphasized

that his main concern

was the ongoing application of

protective coating materials inside the containment building which apparently

had

not been inspected

when they were received

on site to insure that the materials

met specification requirements.

Except for the assignment

of a lay number to the

receiving inspection

(NRR) report, there

was no documentation

to verify that

materials

were inspected

when they were received

to assure

compliance with speci-

fication requirements.

Though it appears

you have complied with the requirements

of Procedure

ASP-8,

you did not meet the requirements

of Procedure

QI7.1, "Instruc-

tion for Receiving Inspection of Seismic or Safety-Related

Material".

Therefore,

the

noncompliance will stand.

In addition,

as discussed

in the telephone

discussion

held between

E.

Sherman of

your staff and J.

Lenahan of this office on February

14,

1980, it is our under-

standing that you will provide a supplemental

response

to this office by March

0,

1980, clarifying statements

made in Part

B of the attachment

to your November

letter.

Sincerely,

James

P. O'Reilly

Director

cc:

(see

page

2)

8008060

+6'

Florida Power and Light Company

FEB Rl 1980

cc:

C.

M. Wethy, Plant Manager

Post Office Box 128

Ft. Pierce,

FL

33450

Nat Weems, Assistant

QA Manager

Post Office Box 128

Ft. Pierce,

FL

33450