ML17202L204

From kanterella
Jump to navigation Jump to search
Forwards Safety Insp Repts 50-237/90-09 & 50-249/90-08 on 900221-0402.No Violations Noted
ML17202L204
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 04/13/1990
From: Shafer W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Reed C
COMMONWEALTH EDISON CO.
Shared Package
ML17202L205 List:
References
NUDOCS 9004240198
Download: ML17202L204 (3)


See also: IR 05000237/1990009

Text

.. l

_,.. ... at' ;! . .:"!).

Docket No. 50-237

Docket No! .so~249

Commonwealth Edison Company

ATTN:

Mr. Cordell Reed

Senior Vice Pre~ident

Post Office Box 767

Chicago, IL

60690

Gentlemen:

This refers to the rouf~he safety inspection conducted by s ... G. Du Pont,

D. E. Hills and B. L. Siegel, of this office on.February 21 through April 2,

1990,

of activities at Dresden Nuclear Power Station, Units 2*and 3

authorized by Operating Lic~nses No. DPR-19 and.No. DPR-25 and to the

discussion of our findings with Mr. E.* Eenigenbu~g and others at the

conclusion of the. inspection.

.

.

.

The enclosed copy of our inspection report identifies areas examined during

  • the inspection.

Within these areas, the inspettion consisted of a selective

examination of proceduies antj representative records, observations, and

interviews with personnel.

No violations with NRC tequirements were identified during the course of this,

inspect i o.n.

In accordance with 10 CFR 2:790, of the. Commission's Regulations, a copy of

this letter and the enclosure(s) will be placed in the NRC Public Document

Room.

We will gladly discus~ any questions you have coricerning this inspection.

Enclosure:

Inspection Report

No. 50-237/90009(DRP)

No. 50-249/90008(DRP)

See Attached Distribution

RIII

ftu<_

ful- Jones/jp

04//;//90

RIII

  1. t

Lerch

9004240198 900413

PDR

ADOCK 05000237

0

.

PDC

Sincerely;

llQrig1.nal ~1gned by w;u. Shafer"

W. D. Shafer, Chief

Reactor Projects Branch 1

RIII

Shafer

SEE ATTACHED. SHEET

.

. *. i>l

'!

Docket No. 50-237

Docket No. 50-249

Commonwealth Edison Company

ATTN:

Mr. Cordell Reed

Senior Vice President

Post Office Box 767

Chicago,* IL

60690

Gentlemen:

  • . APR t a 1900

This refers to the routine safe_ty inspection conducted by S. G. Du Pont,

D. E. Hills of this office and B. L. Siegel, of the Office of Nuclear

Reactor Regulation, on February.21 through April 2, 1990, of activities

at Dresden Nuclear Power Station, Units 2 and 3 authorized by Operating

Licenses No. DPR-19 and No. DPR-25 and to the discussion of our findings

with Mr. E. Eenigenburg and others at the conclusion of the inspect~on.

The enclose-a copy of our inspection report identifies areas examined during

the inspection.

Within thes~ areas, the inspection consisted of a sel~ctive

examination. of procedures and representative records, observations, and

inter.views with personnel.

No violations with NRC requirements were identified during the cour~e of this

inspection.

In accordance with 10 CFR 2.790, of the Commission's Regulations, a copy of

this letter and the enclosure(s) will be placed in the NRC Public Document

Room.

We will gladly discuss any questicins you have concerning this inspettion.

Enclos~re:

Inspection Report

No. 50-237/90009(DRP)

No. 50-249/90008(DRP)

See Attached Distribution

RIII .

Riii *

RIIi

Jones/jp

Lerch,

Hinds

04/ /90

Sincerely,

W. D. Shafer, thief

Reactor Projects Branch 1

'1

R~

sni ~r

.113 ~o.

Commonweal th Edi son Company

,.

Distribution

cc w/enclosure:

T. Kovach, Nuclear

Licensing Manager

E. D. Eenigenburg, S~ation Manager