APPENDIX
SALP BOARD REPORT
U. S. NUCLEAR REGULATORY COMMISSION
REGION III
SYSTEMATIC ASSESSMENT OF LICENSEE PERFORMANCE
50-237/88001; 50~249/88001
Inspection Report No.
Cormnonwealth Edison Company
Name of Licenee
Dresden Station
Name of Facility
January 1, 1987 through January 31, 1988
Assessment Period
8807130025 880630
ADOCK 05000237*
0
SALP 7
DRESDEN STATION
A.
Summary of Meeting with Commonwealth Edison on May 2, 1988
The findings and conclusions of the SALP Board are documented in Report
No. 50-237/88001; 50-249/88001 and were discussed with the licensee on
May 2, 1988, at the Dresden Station in Morris, Illinois. The licensee's
regulatory performance was presented and found acceptable in each
functional area.
We plan to closely monitor trends in your station
improvement plan, both at the station and at meetings with you.
While the meeting was primarily a discussion between the licensee and
NRC, it was open to members of the public as observers.
The following licensee and NRC personnel were in attendance, as well
as the noted observer~.
Cormnonwealth Edison Company
B. L. Thomas, President
C. Reed, Senior Vice President
L. 0. DelGeorge, Assistant Vice President
N. J. Kalivianakis, General Manager (BWR)
E. D. Eenigenburg, Station Manager
H. Bliss, Nuclear Licensing Manager
J. Zucchi, Assistant Station Security Administrator
0. Farrar, Technical Services Manager
R. Bishop, Operations Assessments
G. Wagner, Production Services MGR
G. Diederich, Station Manager - LaSalle
J. Silady, Nuclear Licensing Administrator
D. Shoyer, Waste Systems Engineer
T. Cresla, Assistant Supt - Work Planning
D. Adam, Rad-Chem Supervisor
0. Wheeler, Site Superintendent - PAES
S. Stiles, Training Supervisor
B. Geir, Q.C. Superintendent
R, Ralph, Licensing Engineer
J. Acterberg, Technical Staff Supervisor
J. Mayer, Station Security Administrator
C. Schroeder, Services Superintendent
J. Wojciga, Production Superintendent
L. Gerner, Superintendent - Performance Improvement
J. Bitel, Manager - Nuclear Safety
K. Yates, On Site Nuclear Safety
B. Zank, Operating Engineer
W. Betourne, QA
R. *Stols, QA Engineer
J. Brunner, Assistant Superintendent - Technical Service~
J. Kotowski, Assistant Superintendent - Operations
D. Booth, Master Electrician
G. Wink, Master IM
M. Strait, Master MM
R. Meadows, Maintenance Staff Supervisor
G. Griffiths, Storero_onj Supervisor.
E. Dennis, District Supervisor
G. Smith, Operating Engineer
S. Kerr, IR
J. Krisch, Personnel Supervisor
E. Armstrong, Regulatory Assurance Supervisor
R. Tuetken, PACS, Construction Manager - BWR
A. Kief, Senior Financial Coordinator
K. Brennan, Regulatory Assurance Group Leader
D. VanPelt, Assistant Supervisor Maintenance
J. Coonan, Maintenance Improvement
R. Jeisy, INPO Coordinator
W. Shewski, Manager, Quality Assurance
V. Gengler, Station Security Force Supervi$or
U.S. Nuclear Regulatory Commission
A. Bert Davis, Regional Administrator
W. L. Forney, Chief, Reactor Projects Branch 1
M. A. Ring, Chief, Reactor Projects Section lB
M. Grotenhuis, Project Manager
S. DuPont, Senior Resident Inspector
P. Kaufman, Resident Inspector
D. Jones, Project Inspector
R. Lickus, Chief, State and Government Affairs
Illinois Department of Nuclear Safety
Robert D. Schulz, Section Chief
B.
Comments Received from Licensee
Commonwealth Edison's response to the Dresden SALP 7 Board Report
dated June 1, 1988, had no comments addressing the specific content of
the report.
Because there are no comments, this Appendix contains no
changes to the SALP Report.
C.
Regional Administrator's Conclusions Based on Consideration of Licensee
Comments
I have concluded that the overall ratings in the affected areas have
not changed.