Advises That Subsequent Programs for Future Outages Should Address Concern Re IGSCC Cracking.Summary Results of Augmented Insp Activities Submitted in Accceptable
ML17201J334
Person / Time
Site: Dresden Constellation icon.png
Issue date: 06/17/1988
From: Siegel B
Office of Nuclear Reactor Regulation
To: Bliss H
COMMONWEALTH EDISON CO.
References
GL-84-11, TAC-66619, NUDOCS 8807120639
Download: ML17201J334 (1)


Text

  • Docket No.

50-249 Mr. Henry Bl i S*S Nuclear Litensing Manager Cormnonwealth Edison Company Post Office Box 767 Chicago, Illinois 60690

Dear Mr. Bliss:

June 17,.*1988

.:*e A

DISTRIBUTION:

~c-k~\\~*~-!BD~ * **

PDIIl-R/F

  • t'Norrholm *.
  • I fJ BSiegel *J <

-. CYCheng. :.

.,, LLuther..

SUBJECT:

OUTAGE IGSCC INSPECTION PROGRAM* AT DRESDEN NUCLEAR POWER STATION UNIT 3 (TAC NO. 66619)

In your letter dated October *15, *1987, you submitted *'the IGSCC inspection plan for the Dresden 3.refueling outage in 1988.

Based upon a preliminary review, and discussions with.CECo (held during conferenc~ calls on February 5 & 9, 1988), the NRC staff determined.that the inspection plan described is consistent with the r~quiremerits of Generic Letter (GL) 84-11.

However, the***

scheme for expanding the inspection sample, when new flaws are found, does not comply with SL 84-11. Consequently, the staff has determine~ CECo's proposed alternative sample expansion scheme is not acce~table without some further justification. Since you have already completed your inspection and found no IGSCC indications *in any of, the piping welds exam,ined, this proposed alternative sample e~pansion SGheme had no impact on.. your 1988 outage inspection. Any subsequent programs submitte~ *far future outages at either

  • Dresden Unit Nos~ 2 *or 3 should address this concern.

~

The staff has also review~d the s~~ary r~sults of your.augmented inspection.

activities submitted in your letter dated June 17~ 1988 and has determined the results. are acceptable~

'~.

Sincerely Byron -Siegel, Seni~r Project Manager

.-~

Project Directorate III-2.

Enclosure:

As stated

  • PDIII-~*

LLuthe 6/..2.1 I 8 PDIII-2P~

BSei ge 1 : "7 6/ )1 /88 880712 0639 88061 7.

PDR ADOCK. 05000249 1 *

. _G --------- __

1,,__EDR

  • 1

_ _)

f

{~

(*

Division of Reactor Projects - III

  • IV, V_and Special Projects p rs :D L~~.

61,,, 1 /88