ML17194A326

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-237/81-31 & 50-249/81-23,on 811013-14,16,19 & 20.No Noncompliance Noted.Major Areas Inspected: Surveillance Procedures,Surveillance Activities & Revisions to Licensee QA Program
ML17194A326
Person / Time
Site: Dresden  
Issue date: 12/03/1981
From: Baker K, Connaughton K
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML17194A324 List:
References
50-237-81-31, 50-249-81-23, NUDOCS 8112160231
Download: ML17194A326 (5)


See also: IR 05000237/1981031

Text

U.S. NUCLEAR REGULATORY COMMISSION

REGION III

Report No. 50-237/81-31; 50-249/81-23

Docket No. 50-237; 50-249

License No. DPR-19; DPR-25

Licensee:

Commonwealth Edison Company

P. 0. Box 767

Chicago, IL

60690

Facility Name:

Dresden Nuclear Power Station, Units 2 and 3

Inspection At:

Dresden Site, Morris, Illinois

Inspection Conducted:

October 13-14, 16, 19-20, 1981

11.a,~

Inspector:

K. A. Connaughton

Approved By:~hief

Management Programs Section

Inspection Summary

/?14/17

Inspection on October .13-14, 16, 19'."20, 1981 (Report. No. 50-249/81-23;

50-237/81-31)

Areas Inspected:

The inspector reviewed surveillance procedures; surveillance

activities; procedures and activities associated with inservice testing of

pumps and valves; revisions to the licensee's quality assurance program and

quality procedures.

The inspection involved a total of 28 inspector-hours

onsite and six inspector-hours in office by one NRC inspector.

Results:

Of the four areas inspected, one apparent item of noncompliance

was identified; failure to analyze and document valve leak rate testing

in accordance with inservice test requirements (paragraph 2.d).

8112160231 811204

PDR ADOCK 05000237

-~--

--- -

lj'9~

  • .:

DETAILS

1.

Persons Contacted

  • D. Scott, Plant Manager

D. Farrar, Administrative and Technical Services Assistant Superintendent

  • J. Brunner, Technical Staff Supervisor

D. Ringo, Technical Staff

E. Rawly, Technical Staff

W. Hildy, Instrument Maintenance Master Mechanic

M. Wright, Operating Engineer

R. Cohen, Technical Staff

  • G. Tanner, Quality Assurance

H. Waclaw, Instrument Maintenance

The inspector also contacted several other licensee employees, including

plant engineering and administrative personnel.

  • Denotes those attending the exit .interview.

2.

Surveillance

a.

Surveillance Activities

Surveillance activities were reviewed to ascertain the following:

whether or nqt tests were conducted in accordance with properly

approved procedures at the required frequencies; whether or not

test results received proper review and approval; and whether or

not appropriate corrective action was taken when acceptance

criteria were not met.

The*following surveillance activities,

performed between January 1, 1981 and October 10, 1981 were

included in the review:

DOS 400-2 Rev. 2, "Rod Worth Minimizer Prestartup Surveillance"

DOS 1600-13 Rev. 2 "Suppression Chamber to Reactor Building

Vacuum Breaker Operability Test for 2/3-1601-314 and B"

DOS 6600-1 Rev. 11 "Diesel.Gene~ator Sur~eillance Tests"

DOS 6900-1 Revs. 4 & 5 "D-213 Weekly and Monthly Storage

Battery Checks"

DOS 6900-4 Rev. 0 "D-2/3 Quarterly Storage Battery Checks"*

DOS 7500-2 Rev. 2 "Removing Moisture From SBGT Charcoal

Absorbers/SBGT Surveillance Tests"

DIS 500-5 Rev. 1 "SCRAM Discharge Volume Level Sensors

Calibration Check"

- 2 -

i.! .

DIS 500-6 Rev. 1 "Condenser Low Vacuum SCRAM"

DIS 1600-2 Rev. 1 "Drywell High Pressure SCRAM"

Monthly surveillance testing conducted in accordance with DOS 6900-1,

Revision 4, between January 21, 1981 and April 2, 1981 revealed that,

several storage battery cell voltage and specific gravity measure-

ments did not meet acceptance criteria.

The procedure required that

if cell voltage and specific gravity acceptance criteria were not

met, charge equalization was to be carried out for 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> .and

voltage and specific gravity measurements taken seven days later.

This requirement was stated on "Checklist G" (the data sheet used

to record volta,ge and specific gravity measurements) of the

procedure.

The licensee performed the required actions, however,

if acceptance criteria for cell voltage and specific gravity were

not met when remeasured seven days after the scheduled monthly

test, no further action was taken.

The inspector was informed

that Commonwealth Edison's Quality Assurance Department had made

a similar finding during an audit conducted in April of 1981, and

that as a result, a new revision of procedure DOS 6900-1 was .issued

for conducting monthly storage battery tests.

This procedure

rev1s1on contained .new acceptance criteria for cell voltage and

specific gravity.

These new acceptance criteria insured adequate cell capacity, but

were slightly less conservative than those they replaced.

The

inspector determined that these new acceptance criteria were met

in earlier and subsequent tests perform~d between January 1, 1981

and October 10, 1981.

No items of noncompliance were identified.

b.

S~rveillance Procedures

The inspector reviewed several surveillance tests selected from

the Technical Specifications to ensure that the tests were covered

by properly.approved procedures; that these procedures contained

adequate preparation or 1prerequisites, included acceptance criteria,

and pro~ided for system restoration following testing.

The follow-

ing procedures were examined:

DOS 400-2 Rev. 2 "Rod Worth Minimizer Prestartup Surveillance"

DOS 1600-13 Rev. 2 "Suppression Chamber to Reactor Building

Vacuum Breaker Operability Test for 2/3-1601-31 A & B"

DOS 6600-1 Rev. 11 "Diesel Generator Surveillance Tests"

DOS 6900-4 Rev. 0 "D-2/3 Quarterly Storage Battery Checks"

DOS 7500-2 Rev .. 2 "Remoying* Moisture From SBGT Charcoal

Absorbers/SBGT Surveillance Tests"

- 3 -

.,..

DIS 500-6 Rev. 1 "Condenser Low Vacuum SCRAM"

DIS 1600-2 Rev. 1 "Drywell High Pressure SCRAM"

No items of noncompliance were identified.

c .. Inservice Testing Program - Pumps_

The inspector *reviewed the licensee's pump testing program to

verify compliance with the requirements of 10 CFR 50.55a(g).

Pump

test records revealed that tests had been conducted on all applic-

able pumps at the required frequencies with properly approved

procedures.

Test methods were found to be satisfactory.

The inspector noted that all required documentation was available,

but rather disorganized.

The inspector urged licensee representa-

tives to assemble required documentation (Le., pump records,

inservice test plans and records of test) in a more orderly format

for easy reference.

The inspector had this concern in light of

the fact that responsibility for coordinating the program and

maintaining required documentation would soon be changing hands.

Also, the inspector could not verify that the licensee was

analyzing pump test data within 96 hours0.00111 days <br />0.0267 hours <br />1.587302e-4 weeks <br />3.6528e-5 months <br /> after the test as

required by Subarticle iWP 3220.* The licensee agreed to revise

test procedures .to include a record of the time a test is com-

pleted and the time an analysis of test results is completed.

  • A-Sectibq XI of the ASME Boiler and Pressure Vessel Code, 1974

Edition and Addenda through Summer of 1975.

\\

No items of noncompliance were identified.

d.

Inservice Testing Program - Valves

The inspector reviewed the lic~nsee's valve iesting ~~ogram t6

verify compliance with the requirements of 10 CFR S0.55a(g).

Examination of the licensee's approved ISI valve test program,

status summaries, and several test procedures revealed that the

licensee had performed tests at the required frequencies~ .

Appropriate acceptance criteria was provided for all testing

except Category A valve leakage-rate testing.

Specified maximum

allowable leak rates for each valve was not included in inservice

test documentation.

Additionally, the licensee was not analyzing

valve leakrates in accordance with paragraph IWV 3420(f) *Section

XI of the ASME Boiler and Pressure Vessel Code, 1974 Edition and

Addenda through Summer of 1975 nor implementing the corrective

action requirements of paragraphs IWV 3420(g)(l) and (2) *Section

XI of the ASME Boiler and Pressure Vessel Code, 1974 Edition and

Addenda through Summer of 1975.

This is an item of noncompliance identified in Appendix A.

(50-237/81-31-01)

(50-249/81-23-01)

- 4 -

3.

Quality Assurance Program

The inspector reviewed revisions to the licensee's quaJity assurance

program described in Topical Report CE-IA.

These .revisions were made

between January 1, 1981, and the time of this inspection.

The inspector

interviewed quality assurance personnel to assess their understanding

of each revision and to discuss specific changes made to implementation

procedures (quality procedures) to accomodate these program revisions.

The inspector reviewed applicable quality assurance procedures and

found that they had been revised, where necessary, to reflect revisions

to the quality assurance program.

.

No items of noncompliance were identified.

4.

Exit Interview

The inspectors met with licensee representatives denoted in Paragraph

1 at the conclusion of the inspection on October 20, 1981.

The in-

spectors summarized the purpose and the scope of the inspection and

the findings.

- 5 -