Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in IE Insp Repts 50-237/81-06, 50-249/81-04,50-254/81-03,50-265/81-03,50-295/81-05 & 50-304/81-03
ML17194A153
Person / Time
Site: Dresden, Quad Cities, Zion  
Issue date: 09/17/1981
From: Norelius C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Reed C
COMMONWEALTH EDISON CO.
References
NUDOCS 8109220475
Download: ML17194A153 (3)


See also: IR 05000237/1981006

Text

Docket No. 50-237,GQ:2'49\\

50-254, 50-265; 50-295, 50-304

Commonwealth Edison Company

ATTN:

Mr. Cordell Reed

Vice President

Post Office Box 767

Chicago, IL

60690

Gentlemen:

SEP 1 7 1981

IE HQ FILE CO'Pl

Thank you for your letter dated August 12, 1981, informing us of the steps

you have taken to correct the noncompliance which we brought to your atten-

tion in Inspection Reports No. 50-237/81-06; 50-249/81-04; 50-254/81-03;

50-265/81-03; 50-295/81-05; and 50-304/81-03 forwarded by our letters dated

May 1, July 15 and July 29, 1981.

We will examine these matters during a

subsequent inspection.

Your cooperation with us is appreciated.

cc:

Louis 0. DelGeorge, Director

of Nuclear Licensing

D. J. Scott, Station Supt.

N. Kalivianakis, Plant Supt.

K. Graesser, Station Supt.

cc w/ltr dtd 8/12/81:

DMB/Document Control Desk (RIDS)

Resident Inspector, RIII

Mary Jo Murray, Office of

Assistant Attorney General

RIII

,/,

Sincerely,

RIII

./

RIII

RIII

RIII

Af ~

Sclihlz/so

9/10/81

8109220475 810917

PDR ADOCK 05000237

Q

PDR

~,L

~~

Reimann

Hays

Williams

Norelius

'

\\,~

Commonw.ath Edison

One First Nati- Plaza, Chicago, Illinois

Address Reply to: Post Office Box 767

Chicago, Illinois 60690

Mr. James G. Keppler, Director

Directorate of Inspection and

Enforcement - Region III

U.S. Nuclear Regulatory Commission

799 Roosevelt Road

Glen Ellyn, IL

60137

August 12, 1981

Subject:

Dresden Station Units 2 and 3

Quad ~ities Staton Units 1 and 2

Zion Station Units l and 2

1 Supplemental Response to IE

Inspection Report Nos. 50-237/81-06

50-249/81-04, 50-254/81-03, 50-265/81-03,

50-295/81-05, 50-304/81-03,

NRC Docket Nos. 50-237/249,

50-254L265, and 50-295/304

Reference ( a) :

c . E. Norelius letter to Cordel 1 Reed

dated May 1 ' 1981 .

( b)

J. s. Abel letter to J. G. Keppler

dated June 1 5 ' 1981.

( c ) : c . E. Norelius letter to Cordell Reed

dated July 1 5 ' 1981 .

( d ) :

L . 0. DelGeorge letter to J. G. Keppler

dated July 24, 19 81

0

( e) : c. E. Norelius letter tu Cordell Reed

dated July 29, 19 81

0

Dear Mr. Keppler:

As discussed in References (b) through (e), Commonwealth

Edison has committed to revise the Quality Assurance Topical Report,

CE-1-A, to clearly identify the specific regulatory guides and

standards. which each site is committed to comply with.

This action

was taken in response to the subject Inspection Report transmitted

by Reference (a).

This is to inform you that we have submitted this proposed

revision in the E. D. Swartz letter to W. P. Haas dated August 7,

1981.

The letter with proposed *changes is attached for your

information.

AUG 1 4 1981

    • --

.J. G*. Keppler

-

2 -

August 12, 1981

As we have agreed, we will obtain reasonable assurance from

NRR of the acceptability of this change within 90 days after the

August 7, 1981, submittal date.

Should the proposed revision *

require implementation of new standards, or if changes are required

to gain NRR acceptance, we will provide your office with an

implementation schedule within 90 days after this submittal.

Please address any questions concerning this matter to this

off ice.

cc:

Very truly yours,

.

(*

/ /

.///) )* l. /l.:. ~**'.

')

./. -~/, :~U. <;-!Ll"~_;J-..k.-

.

f/

L. 0. DelGeorge

Director of Nuclear Licensing

Region III Inspector - Dresden

Region III Inspector - Quad Cities

Region III Inspector -

Zion

Attachment

lm

2418N